CHAPTER Env-A 1800 ASBESTOS
MANAGEMENT AND CONTROL
Statutory
Authority: RSA 141-E:4
REVISION NOTE #1:
Document #9298, effective 10-21-08,
made extensive changes to the wording, format, structure, and numbering of
rules in Env-A 1800 by including and renumbering rules
in He-P 5000, entitled “Asbestos Management Rules”, originally filed by the
Department of Health and Human Services.
He-P 5000 had been transferred to the Department of Environmental
Services by 2008, 249:28, effective 9-12-05.
Document #9298 superseded all prior
filings for rules in He-P 5000 and Env-A 1800,
including Document #8304, which had readopted Env-A
1800 with amendments effective 3-15-05.
Document #8304 had included and renumbered many definitions formerly in
Env-A 100 as filed under Document #6482-A, effective 4-1-97. The filings prior to Document #9238 affecting
rules numbered He-P 5000 and Env-A 1800 included the
following documents:
He-P
5000
#4269,
eff 6-24-87
#4951,
eff 10-11-90
#5982,
eff 2-2-95
#6369,
EMERGENCY, eff 11-12-96, EXPIRED 3-12-97
#6557,
eff 8-15-97
#7326,
INTERIM, eff 7-28-00, EXPIRED 1-24-01
#7467,
eff 3-23-01
Env-A 1800
#6482-B,
eff 4-1-97 (formerly Env-C 400)
#8304,
eff 3-15-05
REVISION NOTE #2:
Document #12172, effective 5-5-17, adopted, readopted,
readopted with amendments, or repealed all of the rules in Chapter Env-A 1800, which
involved extensive renumbering within the chapter. Document #12172 replaced all prior filings
for rules in the former Chapter Env-A 1800.
Document #10695, effective 10-18-14, was the
only prior filing affecting rules in the former Chapter Env-A
1800 since Document #9298, effective 10-21-08.
Those rules in the former Env-A 1800 which were
not affected by Document #9298 did not expire on 10-21-16 since they were
extended pursuant to RSA 541-A:14-a until replaced by the rules in Document
#12172, effective 5-5-17.
REVISION
NOTE #3:
Document
#14104, effective 11-1-24, readopted with amendments Chapter Env-A 1800. Amendments
included inserting new rules, deleting rules, amending rules, and extensively
renumbering the remaining rules within the chapter, which had contained Part
Env-A 1801 through Part Env-A
1814 but now contained Part Env-A 1801 through Part
Env-A 1820.
Document #14104 replaces all prior filings for rules in the former
Chapter Env-A 1800.
The new
rules inserted as amendments to Env-A 1800 by Document
#14104 include the following definitions in Part Env-A
1802:
Env-A 1802.04 “Approved
training course”
Env-A 1802.12 “Asbestos
containing building material (ACBM)”
Env-A 1802.14 “Asbestos
disposal site entity”
Env-A 1802.15 “Asbestos
exposure”
Env-A
1802.20 “Certification holder”
Env-A 1802.23 “Electronic
means”
Env-A 1802.29 “Friable
asbestos material”
Env-A 1802.31 “Homeowner”
Env-A 1802.40 “Presumed
asbestos-containing material (PACM)”
Env-A 1802.47 “School
building”
The following rules with substantive
requirements were inserted as amendments to Env-A 1800
by Document #14104:
Env-A 1803.02 General
Homeowner Asbestos Removal Procedures.
Env-A 1803.03 Disturbance
of Asbestos-Containing Asphalt Roofing Materials.
Env-A 1803.04 Disturbance
of Asbestos-Containing Cementitious Roofing or Siding Material.
Env-A 1803.05 Homeowner
ACM Packaging and Labeling Procedures.
Env-A 1803.06 Homeowner
Notice of Asbestos Disposal.
Env-A 1803.07 Homeowner
ACM Disposal Procedures.
Env-A 1803.08 Homeowner
Waste Shipment Records.
Env-A
1817.09 Appeal.
Env-A
1818.09 Appeal.
The following definitions in Part
Env-A 1802 were deleted by Document #14104:
Env-A
1802.03 “Analytical service”
Env-A
1802.04 “Approved training provider”
Env-A
1802.16 “Authorized representative”
Env-A
1802.20 “Crumb”
Env-A
1802.21 “Department”
Env-A
1802.33 “Major asbestos abatement
project – Class S demolition
Env-A
1802.34 “Major asbestos abatement
project – Class S renovation
Env-A
1802.37 “Model accreditation plan (MAP)”
Env-A
1802.40 “Private dwelling”
Rule Env-A
1805.03 titled “Records Maintained On Site” was also
deleted by Document #14104.
The prior filings affecting the
deleted definitions and Env-A 1805.03 included the
following documents:
#9298, eff 10-21-08 (See Revision Note #1 at chapter
heading for Env-A 1800)
#12172, eff 5-5-17 (See Revision Note #2 at chapter heading
for Env-A 1800)
There were no other filings affecting Chapter Env-A 1800 after Document #12172, effective 5-5-17, until Document #14104. Those rules in the former Env-A 1800 which were not affected by Document #9298 did not expire on 10-21-16 since they were extended pursuant to RSA 541-A:14-a until replaced
PART Env-A 1801 PURPOSE; SCOPE;
SUBMISSIONS; INCORPORATION OF FEDERAL REQUIREMENTS
Env-A 1801.01 Purpose.
(a) The purpose of this chapter is to protect the
health of the general public by ensuring that asbestos
is managed in a manner that prevents the release of asbestos fibers to the
environment and human exposure thereto.
(b) It is intended that the rules in this chapter
be used in conjunction with other federal, state, and local requirements for
managing and controlling asbestos, including but not limited to:
(1)
Administrative rules established by the department pursuant to RSA 149-M,
including but not limited to Env-Sw 901 and Env-Sw 2100; and
(2)
Federal regulations, including those relating to worker safety,
established by:
a. U.S.
Occupational Safety and Health Administration in 29 CFR 1910 and 29 CFR 1926;
and
b. U.S.
Environmental Protection Agency (EPA) in 40 CFR 61 and 40 CFR 763.
Source. (See
Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for
Env-A 1800) #14104, eff
11-1-24, EXPIRES: 11-1-34
Env-A 1801.02 Applicability. Subject to Env-A
1803, this
chapter shall apply to the following:
(a) Any person who owns or operates any facility
that has asbestos-containing material (ACM) or regulated
asbestos-containing material (RACM) on the premises;
(b) Any person involved in asbestos abatement
or disturbance of asbestos at an asbestos disposal site, including, but not limited to, analytical
laboratories, consultants, industrial hygienists, supervisors, and workers;
(c) Any source, other than an inactive waste
disposal site that ceased operating by July 10, 1981, subject to 40 CFR 61,
Subpart M;
(d) Any structure, installation, or building
previously subject to this chapter, regardless of its current use or function;
(e) Training,
licensure, and certification of persons engaged in:
(1)
Asbestos abatement, as defined by RSA 141-E:2, II;
(2)
School asbestos abatement planning, as defined by RSA 141-E:2, VIII; and
(3)
Activities involving the disturbance of asbestos at asbestos disposal
sites, as defined by RSA 141-E:2, III; and
(f) Any person involved in a project with the
potential to release asbestos fibers during building
maintenance, construction, renovation, demolition, or other similar activities;
or processing, transport, and disposal activities.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1801.03 Submissions
To and Other Contact With the
Department.
(a) Any application, request, report,
notification, or other information required or allowed by this chapter to be
provided to the department in writing shall be sent or delivered as specified
in Table 1801-1:
Table 1801-1: Methods of Submission with Address/Other
Contact Information
|
Method
of Submission |
Address |
|
First-class mail |
P.O. Box 95, Concord, NH 03302-0095 |
|
Delivery (commercial service or in-hand) |
29 Hazen Drive, Concord, NH |
(b) Any application, request, report, notification, or
other information required or allowed by this chapter to be provided to the
department by telephone or email shall be directed as specified in Table
1801-2:
Table 1801-2:
Contact Information for Telephone and Electronic Communications
|
Method of Contact |
Contact Information |
|
Email for Env-A 1803 - 1813 |
asbestos@des.nh.gov |
|
Email for Env-A 1814 - 1820 |
Asbestos.licensing@des.nh.gov |
|
Telephone for Env-A 1803 - 1813 |
603-271-0820 |
|
Telephone for Env-A 1814 - 1820 |
603-271-4609 |
(c)
Submission of a notification by electronic means pursuant to Env-A 1806, shall be in accordance with Env-C 214, “Cross-media
electronic reporting rule (CROMERR) compliance”, and 40 CFR 3, “Cross-media
reporting,” effective November 4, 2022.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1801.04 Federal
Definitions Incorporated. Terms used
in this chapter that are defined in 40 CFR 61.141 shall be as reprinted in
Appendix D, except for the following:
(a) Asbestos;
(b) Facility;
(c) RACM; and
(d) Remove.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1801.05 National
Emission Standards For Asbestos.
(a) Under the authority of RSA 141-E:4, XVI(c),
the owner or operator of a facility subject to this chapter shall
comply with 40 CFR 61, subpart M, as in effect on July 1, 2023
except for the following provisions of 40 CFR:
(1)
61.145(c)(1)(i);
(2)
61.145(c)(1)(ii);
(3)
61.145(c)(1)(iv);
(4)
61.149(c)(2);
(5)
61.150(a)(4);
(6)
61.150(a)(5);
(7)
61.150(b)(3);
(8)
61.151 with respect to disposal sites not operated after July 9, 1981;
(9) 61.151(c);
(10)
61.152(b)(3);
(11) 61.154(c);
(12) 61.154(d);
(13)
61.155(a); and
(14)
61.157.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1801.06 AHERA
Regulations. A person involved in
an asbestos abatement project in a school shall comply with the
requirements of this chapter and the provisions of 40 CFR 763, subpart E, as in
effect on July 1, 2023, except for the provisions of 40 CFR 763.97 and 763.98.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1802 DEFINITIONS
Env-A 1802.01 “Aggressive
sampling” means air sampling which takes place while air is being physically
agitated, which, upon analysis, is likely to give the highest airborne
concentration of asbestos.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.02
“Amended water” means “amended water” as defined in 29 CFR 1926.1101(b),
as reprinted in Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.03 “Accredited
training
course” means any training course that has received EPA approval or an
EPA-approved state accreditation program.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.04 “Approved
training course” means any training course that meets the requirements of Env-A 1814.03, that is being offered by a training provider that
meets the requirements of Env-A 1814.05.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.05 “Asbestos” means “asbestos” as defined
in RSA 141-E:2, I, as reprinted in Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.06 “Asbestos abatement” means “asbestos
abatement” as defined in RSA 141-E:2, II, as reprinted in Appendix C. As
used in this chapter, this term includes “renovation operation.”
Source. (See
Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for
Env-A 1800) #14104, eff
11-1-24, EXPIRES: 11-1-34
Env-A 1802.07 “Asbestos
abatement entity” means any contractor, employer, or person involved in any
major or minor asbestos abatement.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.08 “Asbestos
abatement project designer” means an individual who has met the criteria
in Env-A 1816.06 and been issued a certification
pursuant
to Env-A 1815 to:
(a) Conduct, plan, design, and develop procedures
for asbestos abatement; or
(b) Provide other substantive direction
or criteria for asbestos abatement.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.09 “Asbestos
abatement supervisor” means an individual who has met the criteria in
Env-A 1816.02 and been issued a certification pursuant to Env-A 1815 to direct and control the asbestos abatement
work of an asbestos abatement worker.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1802.10 “Asbestos abatement worker”
means an individual who has met the criteria in Env-A
1816.03 and been issued a certification pursuant to Env-A 1815 to perform asbestos abatement work under the
supervision of an asbestos abatement supervisor.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.11 “Asbestos-containing material (ACM)” means
any material that contains any type of asbestos in an amount greater than one
percent by weight, area, or volume, either alone or mixed with other fibrous or
non-fibrous materials. As used in this chapter, this term includes “asbestos-containing
building materials,” “asbestos-containing waste materials,” and “presumed
asbestos containing materials”.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.12
“Asbestos-containing building material (ACBM)” means
“asbestos-containing building material” as defined in 40 CFR 763.83, as
reprinted in Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.13 “Asbestos
disposal site” means “asbestos disposal site” as defined in RSA 141-E:2, III, as
reprinted in Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.14 “Asbestos disposal site entity” means any
contractor, employer, or individual seeking to disturb asbestos at an asbestos
disposal site.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.15 “Asbestos exposure” means exposure to airborne
asbestos that would occur if an individual were not using respiratory
protective equipment or other personal protective equipment.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.16 “Asbestos
Hazard Emergency Response Act (AHERA)” means the Asbestos Hazard Emergency
Response Act, Public Law 99-519, promulgated by the U.S. Congress on October
22, 1986.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.17 “Asbestos
inspector” means an individual who has met the criteria in Env-A 1816.04, has been issued a certification pursuant to Env-A 1815, and is capable of
identifying asbestos hazards in a commercial, private, or residential structure.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.18 “Asbestos management planner” means an
individual who has met the criteria in Env-A
1816.05 and been issued a certification pursuant to Env-A
1815 to assess the health hazard posed by ACM, determine the appropriate
response action, and develop a schedule for implementing a response action.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1802.19 “Building owner” means the
person in whom legal or beneficial title to a facility is vested. The term includes a duly-authorized
representative of the building owner.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.20
“Certification holder” means the individual whose name appears on the
certification.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.21 “Clean
room” means an uncontaminated area or room which is part of the worker
decontamination enclosure system and includes storage for workers’ street
clothes and clean protective equipment.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.22 “Contractor” means “contractor” as defined in RSA
141-E:2, IV, as reprinted in Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.23 “Electronic
means”, as applied to the submittal of notifications, applications, reports or
other documents to the department, means submission through an electronic
reporting system, designed and intended to be used for submitting documents
electronically to the department.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.24 “Emergency
asbestos abatement” means “emergency renovation operation”, as defined in 40
CFR 61.141, as reprinted in Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1802.25 “Encapsulant” means a material that is applied
to an ACM in order to prevent the ACM or any of its
components from being exposed to ambient conditions.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1802.26 “Encapsulation” means the application of an
encapsulant to ACM to control the release of asbestos fibers into the air,
either by using bridging encapsulants, which create a membrane over the surface
of the ACM, or by using penetrating encapsulants, which penetrate the ACM and
bind its components together.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.27 “Equipment
room” means a contaminated area or room which is part of the worker
decontamination enclosure system and which provides
for the storage of contaminated clothing and equipment.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.28 “Facility”
means any institutional, commercial, industrial, residential, public or private
building, installation or structure, work place, ship,
utility infrastructure, active waste disposal site, inactive asbestos
disposal
site operated after July 9, 1981, or rental dwelling.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.29 “Friable
asbestos material” means “friable asbestos material” as defined in RSA 141-E:2,
VI, as reprinted in Appendix C. The term
includes “friable ACM.”
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.30
“High-efficiency particulate air (HEPA)” means “high-efficiency
particulate air” as defined in 40 CFR 763.83, as reprinted in Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1802.31 “Homeowner” means any individual
who, alone or jointly and severally with others, has legal title to any single family property.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.32 “License holder” means
the asbestos
abatement entity or asbestos disposal site (ADS) entity, as applicable,
whose name appears on the license.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.33 “Loose”
means subject to movement by or in air, such as powder or fibers which can
easily be blown or shaken from the hand.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.34
“Maintenance worker” means an individual who engages in work activities
designed or intended to contribute to the on-going routine maintenance of a
facility, including but not limited to building maintenance, electrical work,
plumbing, carpentry, masonry, custodial services, and heating services, and
whose primary occupation is not asbestos abatement.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.35 “Major asbestos abatement” means any asbestos
abatement activity that affects more than 10 linear feet of RACM on
pipes, 25 square feet of RACM on the surface of structures other than pipes or
ducts, or 3 cubic feet of RACM on facility components where the length or
area could not be measured, but that occurs within the context of renovation or
demolition.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.36 “Manager” means any individual who is responsible
for the control, operation, or maintenance of a building, facility, school, or
rental dwelling which is owned by another person.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.37
“Minor asbestos abatement” means any asbestos abatement renovation activity
which encompasses not more than 10 linear feet of RACM on pipes, 25
square feet of RACM on the surface of structures other than pipes,
or 3 cubic feet of RACM on facility components where the length or area
could not be measured that occurs within the context of a renovation or
demolition. The term does not include larger projects
that are divided into smaller segments.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.38 “Owner or
operator” for the purpose of this chapter means “owner or operator of a
demolition or renovation activity” as defined in 40 CFR 61.141, as reprinted in
Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.39 “Person” means “person” as defined in RSA
125-C:2, X, as reprinted in Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.40 “Presumed asbestos-containing material (PACM)”
means “presumed asbestos containing material” as defined in 29 CFR
1910.1001(b), as reprinted in Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.41 “Regulated Asbestos-Containing Material (RACM)”
means “regulated asbestos-containing material” as defined in RSA 141-E:2, VII,
as reprinted in Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.42 “Removal” means the stripping of any ACM from
surfaces or components within or at a facility.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.43 “Rental dwelling” means any property
that
is occupied by someone other than the homeowner or the homeowner’s spouse,
partner, dependents, or children.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.44 “Responsible person” means each
individual who has managerial, supervisory, or substantial
decision-making authority and responsibility for the activities of a license
holder, including:
(a) For a corporation, the following:
(1) All
officers and directors;
(2) All
shareholders, if a privately held corporation, or all shareholders holding 10
percent or more of the corporation’s debt or equity, if a publicly traded
corporation; and
(3) All
management and supervisory personnel;
(b) For a partnership, all partners, whether
general or limited, and all management and supervisory personnel;
(c) For an association or other organization, all
principals, members, and participants, as applicable, and all management and
supervisory personnel; and
(d) For a municipality or other political
subdivision of the state, the individuals elected or appointed to oversee or
manage the prudential affairs of the political subdivision, and the managers
and supervisors of the department(s) that will perform work under the authority
of the license.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.45 “School” means
any non-profit institution, whether private or public, day or residential,
that provides elementary or secondary education, or both, including
kindergarten but excluding day care centers.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.46 “School asbestos abatement planning” means “school
asbestos abatement planning” as defined in RSA 141-E:2, VIII, as reprinted in
Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.47 “School building” means “school building” as defined in
40 CFR 763.83, as reprinted in Appendix D.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.48 “Sheeting” means any waterproof
material which can be used to make air-tight barriers. The term includes “sheets”.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.49 “Shower
room” means a room between the clean room and the equipment room in the worker
decontamination enclosure with running water that is suitably arranged for
complete showering during decontamination.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.50 “Small-scale, short-duration
activities (SSSD)” means “small-scale, short-duration activities (SSSD)” as
described in 40 CFR 763, subpart E, appendix C, July 1, 2023 edition, as
reprinted in Appendix D, provided that such activities affect no more
than 3 linear feet of asbestos surface on pipes or 3 square feet of
asbestos-containing building material on the surface of structures other than
pipes.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.51 “Structural
member” means “structural member” as defined in RSA 141-E:2, IX, as reprinted
in Appendix C.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.52 “Tape” means a high quality
duct tape or similar adhesive material that can resist both moisture and wear.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1802.53 “Type A
project” means major asbestos abatement involving 500 linear feet or
more of RACM on pipes, 1,000 square feet or more of RACM on the surface of
structures other than pipes, or 100 cubic feet or more of RACM on facility
components where the length or area could not be measured.
Source. #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A
1802.54 “Type B project” means major
asbestos abatement involving at least 260 linear feet but less than 500 linear
feet of RACM on pipes, 160 square feet but less than 1,000 square feet of RACM
on the surface of structures other than pipes, or 35 cubic feet but less than
100 cubic feet of RACM on facility components where the length or area could
not be measured.
Source. #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1802.55 “Type C
project” means major asbestos abatement involving less than 260 linear
feet of RACM on pipes, 160 square feet of RACM on the surface of structures
other than pipes, or 35 cubic feet of RACM on facility components where the
length or area could not be measured.
Source. #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A
1802.56 “Utility infrastructure” means any active or
abandoned above-ground or underground system intended to convey a service, such
as electricity, or to remove a waste, such as sewage, or to store a material,
such as fuel, that is either constructed or insulated with ACM, including but
not limited to transite pipe, electrical line, water
line, sewer line, heating line, roadway, or storage tank.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36 (formerly Env-A 1802.53),
PART Env-A 1803
HOMEOWNER REQUIREMENTS FOR ASBESTOS ABATEMENT AND DISPOSAL
Env-A 1803.01 Homeowner Requirements.
(a)
The homeowner
of a private, single-family property, not used as a rental dwelling, who
performs asbestos abatement on, or disposes of ACM from, that property
shall
only be subject to the requirements in this Part, except as
noted in (b), below, provided:
(1) The homeowner personally performs the asbestos
abatement or disposes of the ACM; and
(2) The asbestos abatement is not done within
6 months of selling or renting the property.
(b) After completing asbestos abatement
pursuant to (a), above, a homeowner who wants to demolish a private,
single-family property shall follow the applicable requirements specified in
Env-A 1804 through Env-A
1812.
(c) The single-family property shall include any
building or structure used or intended for human habitation, and all other
buildings and structures, located within the same lot as designated on a
municipal tax map.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1803.02 General
Homeowner Asbestos Removal Procedures.
(a) To prevent the release of fibers
until properly packaged in accordance with Env-A
1803.05, the homeowner shall:
(1)
Adequately wet all ACM with amended water before removal; and
(2)
Maintain the ACM wet during and after removal.
(b) The homeowner shall carefully lower, not
drop, throw, or slide, all ACM to the ground or floor.
(c) The homeowner shall remove non-load
supporting structural members not previously stripped of ACM as follows:
(1)
Intact or in large sections whenever possible; and
(2) By
carefully lowering, not dropping, throwing, or sliding, those structural
members to the floor.
(d) The homeowner shall remove ACM that is not
associated with structural members as follows:
(1) In
small sections; and
(2) By
not allowing the ACM to accumulate on the floor.
(e) Following removal, the homeowner shall
perform cleanup procedures using repeated HEPA vacuuming and wet cleaning
techniques until no visible residue is observed in the work area.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1803.03 Disturbance of Asbestos-Containing Asphalt
Roofing Materials. In addition to
the requirements in Env-A 1803.02, homeowners who
remove asbestos-containing asphalt roofing materials from the roof of a
structure, shall comply with the following:
(a) Not sand, saw, grind, abrade, or otherwise
treat the roofing material in a manner that might create a
fine dust or particles; and
(b) Protect the surrounding ground
with poly drop cloths such that no roofing material will come
into contact with the ground.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1803.04 Disturbance
of Asbestos-Containing Cementitious Roofing or Siding Materials. In addition to the requirements in Env-A 1803.02, homeowners who remove asbestos-containing
cementitious siding or roofing materials from the side or roof of the
structure, shall comply with the following:
(a) Not sand, saw, grind, abrade, or otherwise
treat the ACM in a manner that might create a fine
dust or particles;
(b) Protect the surrounding ground prior to
removal with poly drop cloths such that no ACM will come into
contact with the ground; and
(c) Remove the cementitious ACM intact, to the
extent possible, by prying out or cutting fasteners.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1803.05 Homeowner
ACM Packaging and Labeling Procedures.
(a) Before completing asbestos abatement or
disposing of ACM, the homeowner shall package ACM in accordance with Env-Sw 901.06, and as follows:
(1) For
all loose ACM, take the following actions to prevent the release of fibers:
a. Adequately wet the ACM with amended water;
b. Place the ACM into leak-tight containers or
double impermeable bags of at least 6 mil thickness each; and
c. Seal the containers or bags with tape, as applicable;
(2)
Wrap large components or structural members that were removed intact in
2 leak-tight layers of 6 mil sheeting and seal the sheeting with tape;
and
(3)
Line the containers, into which bulk unwrapped asbestos waste is placed,
with at least 20 mil of sheeting.
(b)
The homeowner shall label
ACM, in accordance with Env-Sw 901.06, and as
follows:
(1) Label the containers or wrapped materials
using warning labels, as follows:
a. Printed in letters
of sufficient size and contrast so as to be readily
visible and legible; and
b. As specified in 29 CFR 1910.1001(j)(5) or
1926.1101(k)(8); and
(2) For asbestos-containing
waste material to be delivered to a permitted disposal facility, label
containers or wrapped materials with the name of the homeowner and the location
at which the waste was generated.
Source. (See
Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for
Env-A 1800) #14104, eff
11-1-24, EXPIRES: 11-1-34
Env-A 1803.06 Homeowner
Notice of Asbestos Disposal.
(a) In addition to the requirements of Env-A 1803.05, the homeowner transporting ACM for disposal, or
engaging a person or entity to dispose of the ACM, shall:
(1)
Complete and submit the “Homeowner Notice of
Asbestos Disposal” form NHDES-A-01-029 dated August 20, 2024, and available
at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-029 or via the
department’s website at www.des.nh.gov, containing the
information as specified in (b) below;
(2)
Submit the form to the department by mail, hand-delivery or electronic
means, such that the form is postmarked or received by the department no later
than the day on which such transport for disposal begins;
(3) Retain a copy of the form for at least 2 years
from the date the notification was postmarked, delivered to or received by the
department; and
(4)
Provide a copy of the form required in (1) above, to the person engaged
to dispose of the ACM, at the time the ACM is collected.
(b) The homeowner shall provide the following on
the form required in (a)(1), above:
(1) The
homeowner’s name, mailing address, telephone number, telephone type, and, if available,
email address;
(2) The
physical address of the property where the ACM was generated;
(3) The date when the ACM will be picked up;
(4) The quantity(ies) of
ACM to be transported and disposed:
(5) The name, mailing address, and contact
information, including name, email address, telephone number, and telephone type, of
the asbestos waste transporter;
(6) The name, physical address,
and contact information, including name, email address, telephone number, and telephone type, of
the asbestos waste disposal facility; and
(7) A certification that:
a. The homeowner has read and
understands the New Hampshire asbestos management and control rules, Env-A 1800;
b. The homeowner prepared the
notice in conformity with Env-A 1800; and
c. All information contained
herein, including any supplements attached hereto, is true, complete, and not
misleading to the best of the homeowner’s knowledge and belief.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1803.07 Homeowner
ACM Disposal Procedures. After
submittal of the notice specified in Env-A 1803.06,
the homeowner shall remove packaged ACM from the work site as soon as
practical, but no later than 30 days, following the completion of the abatement
work by either:
(a)
Delivering the ACM to a permitted
disposal facility; or
(b)
Having the ACM picked up for disposal by
a transporter.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1803.08 Homeowner
Waste Shipment Records
(a) Within 30 days after delivering ACM to a
permitted disposal facility, the homeowner shall submit a copy of the waste
shipment record to the department by mail, hand delivery, or electronic means.
(b)
If the ACM is picked up for disposal by
a transporter, the homeowner shall submit, within 30 days of the pickup, to the
department by mail, hand delivery, or electronic means:
(1) A copy of the waste shipment record signed by
a representative of the permitted disposal facility; or
(2) A statement that the waste shipment record
signed by a representative of the permitted disposal facility has not been
received.
(c) If a statement pursuant to (b)(2) above is
submitted, then the homeowner shall:
(1) Within 35 days of the date
the ACM was accepted by the initial transporter, contact the transporter or the
permitted disposal facility to determine the status of the waste shipment; and
(2) Within 10 business days of
contacting the permitted disposal facility or transporter, submit a written
report to the department, including the following information:
a. A
copy of the waste shipment record for which a confirmation
of delivery was not received; and
b. A cover letter signed by the homeowner
explaining the efforts taken to locate the asbestos waste shipment and the
results of those efforts.
(d) Pursuant to 40 CFR 61.150, the waste shipment record shall include the
following information:
(1) Name, mailing address, and telephone
number of the homeowner;
(2)
Physical address where the ACM was generated;
(3) Name and address of the state office
responsible for administering the asbestos NESHAP program;
(4) Number of containers used to transport the
ACM;
(5)
Approximate quantity of each type of ACM in cubic meters or cubic yards;
(6) Name and telephone number of the permitted
disposal facility representative;
(7) Name and physical site location of the
permitted disposal facility;
(8) Date of transport;
(9) Name, address, and telephone number of the
transporter(s);
(10) A certification by each transporter of
the contents of this consignment as follows:
a. They are fully and accurately described by proper shipping name;
b. They are classified, packed, marked, and labeled; and
c. They are in all respects in proper condition for transport by
highway according to applicable international and government regulations; and
(11) A certification of receipt of the ACM
covered by the waste shipment record by the permitted disposal facility
representative.
(e) If the homeowner delivers the ACM to a
permitted disposal facility, the homeowner shall provide a copy of the waste
shipment record to the permitted disposal facility at the same time as the
delivery.
(f) The
homeowner shall retain a copy of all waste shipment records for at least 5
years from the date that the ACM was received by the waste disposal facility.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1804 INSPECTIONS
Env-A 1804.01 Inspections
Required Prior to Commencing Demolition or Renovation.
(a) Except as provided in (e) and (f),
below, prior to undertaking any demolition or renovation of any facility, the owner
or operator shall provide for an inspection, as required by 40 CFR 61.145(a)
and 29 CFR 1926.1101(k)(2)(i), by an asbestos inspector of the affected
portion(s) of the facility for the presence of ACM.
(b) The owner or operator shall ensure that the
inspection required by (a), above, meets the
requirements of (c), below.
(c) The inspection required by (a), above, shall
be valid only if:
(1)
A written report summarizing the inspection findings is created and
available as specified in (d)(3), (d)(4) and (h)(3); and
(2) All
samples are collected and analyzed, as specified in (d)(2), below.
(d) The asbestos
inspector shall:
(1) Conduct the inspection required by (a),
above, in accordance with the requirements of (c), above;
(2) Have all samples, other than those samples
assumed to be asbestos, from an inspection:
a.
Collected
in accordance with 40 CFR 763.86; and
b.
Analyzed
by an asbestos analysis service which meets the criteria set forth in Env-A 1813;
(3)
Create a written inspection report including the type, category,
condition, amount, and location of ACM;
(4) Retain a copy of the inspection report
for 5 years after the date the inspection was completed; and
(5) Submit to the department a copy of the
inspection report within 3 business days of a request by the
department.
(e) If a state or local government agency
declares a facility or portion of a facility structurally unsound or in danger
of imminent collapse, the requirement to conduct an inspection pursuant to (a),
above, and to remove all asbestos prior to demolition pursuant to Env-A 1809.01, shall not apply if the owner or operator:
(1)
Submits to the department a notification and
documentation, as specified in Env-A 1806.05(e), from the state or local
government agency that the facility was determined to be structurally unsound
and in danger of imminent collapse; and
(2)
Presumes that the facility contains asbestos and complies with all other
applicable requirements of Env-A 1805 through Env-A 1812.
(f) For a renovation or demolition of a structure
having 4 or fewer units, the owner or operator shall not be required to conduct
an inspection pursuant to (a), above, if the facility component to be impacted
by the renovation or demolition only includes materials made solely of wood,
stone, fiberglass, glass, plastic, metal, foam, or rubber.
(g) For a demolition or renovation involving
asbestos abatement, the owner or operator shall comply with the recordkeeping
requirements specified in Env-A 1805.
(h) For a demolition or
renovation not involving asbestos abatement, the owner or operator shall:
(1) Keep the inspection report, in paper or
electronic format, on-site and readily available for review for the duration of
the demolition or renovation activities;
(2) Retain the inspection report for 5 years after
completion of the demolition or renovation; and
(3) Submit to the department a copy of the
inspection report within 3 business days of a request by the department.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1804.02 Compliance
Inspections.
(a) Upon the request of the department, in
conjunction with any inspection pursuant to RSA 141-E:8 or RSA 141-E:13, the
owner or operator, building owners, or managers shall
review building records for references to ACM used in construction or repairs
and provide all information found to the department in writing within 10
business days of the request.
(b) If, during an
inspection pursuant to RSA 141-E:8 or RSA 141-E:13, the department observes material
suspected of being friable ACM, then:
(1)
The department shall provide written notification to the owner or
operator, building owner, or manager; and
(2)
The owner or operator, building owner, or manager shall have an
inspection as specified in Env-A 1804.01 conducted within 15
business days after the date of the notification in (1), above.
(c) If ACM is found during the inspection, the owner
or operator, building owner, or manager shall have
an asbestos inspector:
(1)
Collect a minimum of 3 bulk samples of the material;
(2)
Collect air samples; and
(3) Have the samples analyzed by an asbestos
analysis service which meets the criteria set forth in Env-A 1813.
(d) The owner or operator, building owner,
or manager shall:
(1) Keep
a copy of the inspection report and analytical results for at least 5 years after the
sampling is completed; and
(2)
Submit a copy of the inspection report and analytical results to the department
or
other interested parties within 3 business days of receipt of a written request.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1804.03 Determination of Damage or Deterioration. For purposes of RSA 141:8, friable ACM shall
be deemed to be deteriorated or damaged if:
(a) The material has pulled away from the
underlying surface; or
(b) Evidence of physical damage exists, such as
gouges or cuts in the material or debris matching the material is on the
surface below the material.
Source. (See
Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for
Env-A 1800) #14104, eff
11-1-24, EXPIRES: 11-1-34
Env-A 1804.04 Determination
of the Potential for Significant Human Exposure. As a result of an inspection under RSA
141-E:8 or RSA 141-E:13, the department shall determine that there is a
potential for significant human exposure if:
(a) There is an increase in the proximity of
friable ACM to an air plenum or direct air stream;
(b) There is an increase in the visibility and
accessibility of friable ACM to building occupants and maintenance workers; or
(c) An increase or change in the degree of
activity in
or around the building increases the risk the friable ACM will be released into
the air, including air movement, vibration, installing new machinery, and
moving of building occupants.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1804.05 Inspection
and Compliance Monitoring Fees.
(a) Whenever the department conducts an
inspection under RSA 141-E:7, RSA 141-E:8 or RSA 141-E:13, with or without
collecting and analyzing samples, in order to evaluate
compliance with RSA 141-E, the department shall charge a fee for the
inspection.
(b) The fee charged shall be the sum of the
individual personnel testing and monitoring fee as specified in (c), below.
(c) The individual personnel testing and
monitoring fee shall be the sum of the following for each department employee
who participates in the inspection:
(1)
Travel costs, based on the state of New Hampshire’s standard mileage
reimbursement rate;
(2)
Lodging costs, if lodging is or becomes necessary due to the amount of
time needed for travel and the inspection, the distance from Concord, and
weather conditions;
(3)
Cost of meals, if the time needed for the inspection and travel exceeds
4 hours;
(4)
Costs of specialty equipment and consumable supplies, where these costs
were incurred specifically in order to carry out the
specific inspection; and
(5) The
product of the number of hours or portion thereof which the employee spent
traveling and inspecting, multiplied by the hourly
rate, including benefits, of that employee.
(d) The department shall send the invoice
for
the fee to the owner or operator of the facility.
(e) The owner or operator shall pay the
fee
within 30 days of the date of the department’s invoice.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1805 RECORDKEEPING
Env-A 1805.01 Documents To Be
Retained On-Site.
(a)
During
asbestos abatement, each asbestos abatement entity at
a
facility where a major or minor asbestos abatement is occurring shall keep
the
following documents on-site and readily available for review, as
applicable,
in electronic or paper format, for the duration of the asbestos abatement:
(1) A
current copy of this chapter;
(2) Copies of the decontamination procedures used for
the decontamination enclosure system required by Env-A
1808.05 or any other procedures which have been established to prevent
contamination of areas outside the work area;
(3)
Copies of procedures to be followed during medical or fire emergencies,
including phone numbers of the nearest emergency facilities;
(4)
Copies of all certifications and proof of current training certificates
held
by all asbestos abatement supervisors and workers engaged in the
asbestos abatement;
(5)
Records of all asbestos abatement-related air sampling results;
(6) A copy of the
inspection report prepared by the asbestos inspector;
(7)
A copy of any written notification concerning the asbestos abatement
submitted to the department pursuant to Env-A 1806;
(8)
The
work plan for the asbestos abatement;
(9) A copy of the asbestos abatement entity license;
(10) A copy of any alternative procedure and
approval pursuant to Env-A 1811.02; and
(11) Daily temperature
records as specified in Env-A 1805.02(a).
(b) The requirement in (a), above, shall not
apply to SSSD activities.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1805.02 Required Records.
(a)
Pursuant to 40 CFR 61.145(c)(7)(iii), the asbestos abatement entity shall
record the temperature at the beginning, middle, and end of each workday for
any periods when wetting operations are suspended pursuant to Env-A 1812.01(g).
(b) After asbestos abatement is complete, each asbestos
abatement entity for a facility where major or minor asbestos abatement
has occurred shall record and maintain the following information, as
applicable, in electronic or paper format, for each asbestos abatement:
(1) The
name, title, and address of each asbestos abatement supervisor and
worker who participated in the asbestos abatement;
(2) The
address of the asbestos abatement;
(3) The
work plan for the asbestos abatement;
(4) All
notifications and revisions submitted to the department pursuant to Env-A 1806;
(5) Waste
shipment records and disposal site slips for all RACM taken from the asbestos
abatement site;
(6) The
estimated amount of RACM involved in the asbestos abatement;
(7) The
scheduled and actual starting and completion dates and, if an actual date
differs from the date originally scheduled, a statement of reasons for the
difference(s);
(8)
Documentation of compliance with all applicable requirements of this chapter;
(9)
Copies of all asbestos-related correspondence with the department and
other state and federal agencies concerning the project, including but not
limited to building or demolition permits, notices of violation, or other
documents relating to permits;
(10) The
name and address of the asbestos disposal facility to which the RACM was taken;
(11)
Information regarding any air sampling, including:
a.
Methodology and results of clearance testing pursuant to Env-A 1808.06, conducted during the abatement process;
b.
Fiber concentration methodology and results pursuant to Env-A 1808.04(e);
c. The
name and address of any consultant(s) hired to perform such sampling; and
d. The
name and address of any asbestos analytical service(s) employed to analyze such
samples, pursuant to Env-A 1813;
(12)
Descriptions of worksite accidents and asbestos exposure;
(13) A copy of the report
summarizing the findings of the inspection, as required by Env-A 1804.01(c)(1);
and
(14) Documentation regarding any alternative
procedure used and approval received, pursuant to Env-A
1811.02.
(c)
After asbestos abatement is complete, each owner or operator of a facility
where major or minor asbestos abatement has occurred shall record and maintain
the following information, as applicable, in electronic or paper format, for
each asbestos abatement:
(1) A copy of all notifications and revisions
submitted to the department pursuant to Env-A 1806;
(2) A copy of the waste shipment records and
disposal site slips for all RACM taken from the asbestos abatement site;
(3) A copy of the clearance air sampling and
clearance determination; and
(4) A copy of the report summarizing the
inspection findings required by Env-A 1804.01(c)(1).
(d) The requirements of (b) and (c), above, shall
not apply to SSSD activities.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1805.03 Retention of
Records.
(a)
Upon request by the department, the asbestos abatement entity and owner
or operator shall submit the records described in
Env-A 1805.02 to the department within 3
business days.
(b)
Except as provided in (c), below, the asbestos abatement entity
and owner or operator shall not destroy records unless they are
more than 30 years old, dated from the completion of the asbestos abatement.
(c) For an asbestos abatement at
a school, the owner or operator shall maintain records for 3 years
after each triennial inspection.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1806 NOTIFICATION REQUIREMENTS AND FEES
Env-A 1806.01 Notification
for Minor Asbestos Abatement.
(a) Except as provided in (b) and (c),
below, the owner or operator of minor asbestos abatement shall not be required
to notify the department regarding that project.
(b)
If the minor asbestos abatement is being done as part of a demolition,
then the owner or operator shall submit an “Asbestos Demolition Notification”
form as required by Env-A 1806.05.
(c) The owner or operator of a minor asbestos abatement project shall submit an “Asbestos Transport for Disposal Notification” form as required by Env-A 1806.07.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1806.02 Requirements
for
Major Asbestos Abatement.
(a)
The owner or operator shall provide the following:
(1) Notification to the department, and as
specified in Env-A 1806.03 and Env-A
1806.04, for each major asbestos abatement;
(2) If the asbestos abatement is being done as
part of a demolition, an “Asbestos Demolition Notification” form, as required
by Env-A 1806.05; and
(3) An “Asbestos Transport for Disposal
Notification” form for the transport for disposal as required by Env-A 1806.07.
(b)
The owner or operator shall create a work plan containing engineering controls
and work practices necessary to comply with all applicable asbestos
requirements.
(c)
Upon request by the department, the owner or operator
shall submit by mail, hand delivery, or electronic means to the department,
within 3 business days of the request, a copy of the work plan for each asbestos
abatement conducted.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1806.03 Notification
Requirements for Major Asbestos Abatement.
(a) In any notification specified in Env-A 1806.02(a)(1), the owner or operator shall:
(1) Complete and submit the “Asbestos
Abatement Notification”, form NHDES-A-01-016, dated August 20, 2024, available
at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-016 or via the department’s website
at www.des.nh.gov; and
(2) Provide the following information:
a. An indication of whether the notice is a new or
revised notification;
b. The amount of the fee included with the form;
c. An indication of whether the project is an
emergency asbestos abatement;
d. For emergency asbestos abatement, the following:
1. Date and hour that
the emergency occurred;
2. A description
of the sudden, unexpected event; and,
3. An
explanation of why immediate action is needed to address a
public health or safety hazard or to avoid imposing an unreasonable
economic hardship;
e. Name, physical address, county, and floor or room
number, if applicable, of the facility being demolished or renovated;
f. Description
of the facility or affected part of the facility including the size in square
feet, number of floors, year constructed, current use, and prior use of the facility;
g. Date of the inspection, name of the person
who conducted the inspection, and certification number of the asbestos inspector;
h. Type of inspection, including visual and
analytical methods, employed to detect the presence of ACM;
i. If analytical methods were used, describe those;
j. List the types of asbestos and location in the facility;
k. An estimate of the approximate amount of RACM
to be removed from the facility in terms of length of pipe in linear feet,
surface area in square feet on other facility components, or volume in cubic
feet if off the facility components;
l. Scheduled start and completion dates of
asbestos removal work or any other activity, such as site preparation that
would break up, dislodge, or similarly disturb asbestos material in a
demolition or renovation;
m
Weekly work
schedule including days of the week and time of day of work;
n. Description of planned asbestos abatement
work to be performed and method(s) to be employed, including demolition or
renovation techniques to be used and description of affected facility components;
o. Description of work practices and engineering
controls to be used, including asbestos removal and waste-handling emission control procedures;
p. Name and mailing address of the facility owner
and asbestos abatement entity;
q. Contact information, including name, email
address, telephone type, and telephone number for the facility owner or designee;
r. Contact information, including name, email
address, telephone type, and telephone number for the asbestos abatement entity;
s. Description of procedures to be followed if
unexpected RACM is found or Category II nonfriable ACM becomes crumbled,
pulverized, or reduced to powder;
t. A certification that at least one person
certified as required by Env-A 1816.02 relative to
asbestos abatement supervisor certification requirements shall, at all times, supervise the asbestos abatement described by
this notification;
u. License number of the asbestos abatement
entity; and
v. A certification that:
1. The owner or operator has read and
understands the New Hampshire asbestos management and control rules, Env-A 1800;
2. The notification is prepared in conformity
with Env-A 1800; and
3. All information contained in the
notification, including any supplements attached, is true, complete, and not
misleading to the best of the owner or operator’s
knowledge and belief.
(b) For asbestos abatement at a school subject to
AHERA, attach a copy of the design plan to the notification submitted, pursuant
to (a), above.
(c) The initial
notification required by Env-A 1806.02 and the
notification fee, as required by Env-A 1806.08, shall:
(1)
Contain the information specified in (a) and (b), above, as applicable;
(2) Be
submitted to the department by mail, hand delivery, or electronic means; and
(3) Be
submitted such that the notice and fee are postmarked or received by the
department at least 10 working days before any asbestos abatement
begins.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1806.04 Revised
Notifications for Major Asbestos Abatement.
(a) The owner or operator shall submit a revised
notification to the department, as specified in (b) through (f) below, if any
of the following occurs during an asbestos abatement:
(1) The
asbestos abatement entity assigned to the asbestos abatement changes;
(2) The
type of asbestos affected changes;
(3) The
completion date of the asbestos abatement changes;
(4) An unscheduled change, of more than one day,
to the dates or hours of operation occurs;
(5) The
amount of asbestos affected changes by 20% or more;
(6) The
amount of asbestos increases resulting in an increase in the notification fee
required under Env-A 1806.08(b);
(7) The start date of the asbestos abatement
changes; or
(8) Additional locations within a facility where
asbestos is to be removed are added to the asbestos
abatement.
(b) The
owner or operator shall submit a revised notification for changes specified in
(a)(1) through (a)(6) by:
(1) Notifying the department within 24 hours via
telephone as specified in Env-A 1801.03(b) or electronic means;
(2)
Completing the revised notification form as specified in Env-A 1806.03(a);
(3)
Submitting the form and revised notification fee, as specified in Env-A 1806.08, to the department by mail, hand delivery,
or electronic means; and
(4)
Ensuring that the form and fee are postmarked, delivered to the
department, or received by the department within 48 hours of notifying the
department pursuant to (b)(1) above.
(c) For changes specified in (a)(6), above, the
owner or operator shall also submit the notification fee required in Env-A
1806.08(b)(1) or (b)(2), as applicable, minus any amount already paid, pursuant
to Env-A 1806.08(b)(2) or (b)(3), as applicable.
(d) If the revised start date of the asbestos
abatement, pursuant to (a)(7) above, is earlier than the original start date of
the asbestos abatement, the owner or operator shall:
(1)
Complete the revised notification form as specified in Env-A 1806.03(a),
above;
(2)
Submit the revised notification form and notification fee, as specified
in Env-A 1806.08, to the department by mail, hand
delivery, or electronic means; and
(3)
Ensure that the revised notification form is postmarked, delivered to
the department, or received by the department at least 10 working days before
the revised start date of the asbestos abatement.
(e) If the revised start date of the asbestos
abatement, pursuant to (a)(7) above, is later than the original start date of
the asbestos abatement, the owner or operator shall:
(1)
Notify the department by telephone or electronic means at least 24 hours
before the original start date; and
(2)
Submit the revised notification form, as specified in Env-A 1806.03(a),
and the revised notification fee, as specified in Env-A 1806.08, to the
department by mail, hand delivery, or electronic means such that the form and
fee are postmarked, delivered to the department, or received by the department
within 24 hours of notifying the department, pursuant to (1) above.
(f) At least 10 days before work begins in a new
location, as specified in (a)(8) above, the owner or operator shall mail, hand-deliver, or submit by electronic means, the following
to the department:
(1) The
revised notification form as specified in Env-A 1806.03(a) and revised
notification fee, as specified in Env-A
1806.08; and
(2) For a project at a school subject to AHERA, a
revised design plan showing that the new location has been properly inspected
for asbestos, in accordance with Env-A 1804.01.
(g) For asbestos abatement, an initial
notification and any subsequent revised notifications shall expire on the
completion date specified in the notification, unless a revision is received by
the department as specified in (b) through (f) above,
as applicable.
(h) For any revisions to be made to a
notification other than those listed in (a), above, the owner or operator
shall submit, by mail, hand delivery, or electronic means, a revised
notification form, as specified in Env-A 1806.03(a), and revised notification
fee as specified in Env-A 1806.08, to the department within 2 business days of
discovering the need to revise the form or of being requested by the department
to revise the form.
(i) To cancel a
previously submitted notification which has not expired pursuant to (g), above,
the owner or operator shall submit, by email or electronic means, a request to
cancel the notification to the department including:
(1) The
facility address; and
(2) The start and completion dates of the
asbestos abatement.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A
1806.05 Notification for Demolitions.
(a)
The owner or operator shall provide notification to the department for each
demolition
by completing and submitting the “Asbestos Demolition Notification” form,
NHDES-A-01-023, dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-023 or via the
department’s website at www.des.nh.gov.
(b)
The notice required by (a), above, shall include the following
information:
(1) An indication of whether the notice is new or
revised;
(2) An indication of whether the project is an
ordered demolition;
(3) For facilities where ordered demolition will
occur, include:
a. The name of the state or local government;
b. The name and title of the state or
local government representative who has ordered the demolition;
c. The date that the order was issued;
d. The date on which the demolition was ordered
to begin; and
e. The company name, mailing address, and
contact information, including name, email address, telephone type, telephone
number, and license number of the asbestos abatement entity;
(4) Name, county, and physical address of the
facility being demolished;
(5) Description of the facility or affected part
of the facility including the size in square feet, number of floors, year constructed,
current use, and prior use of the facility;
(6) Except as specified in Env-A 1804.01(e) and
(f), date of the inspection, name of the person who conducted the inspection,
and certification number of the asbestos inspector;
(7) Type of inspection, including visual and
analytical methods, employed to detect the presence of ACM;
(8) If analytical methods were used, describe those;
(9) If applicable, an
indication that there is no ACM present;
(10) If applicable, an indication of whether ACM
or RACM was present, as follows:
a. The amount of ACM or RACM;
b. The name of the individual or entity that
conducted the asbestos abatement, if required; and
c. The date the asbestos abatement was completed;
(11) Scheduled start and completion dates of demolition;
(12) Weekly work schedule including days of the
week and time of day of work;
(13)
Description of planned demolition work to be performed and method(s) to
be employed, including demolition techniques to be used and description
of affected facility components;
(14) Description of work practices and engineering
controls to be used including asbestos removal and waste-handling emission
control procedures;
(15) Name and mailing address of the facility
owner and demolition contractor;
(16)
Contact information, including name, email address, telephone type, and
telephone number for the facility owner or designee;
(17) Contact information, including name, email
address, telephone type, and telephone number, for the demolition contractor;
(18) Description of procedures to be followed if
unexpected RACM is found or Category II nonfriable ACM becomes crumbled,
pulverized, or reduced to powder;
(19) An indication of whether the project is being
done at a residential property with 4 or fewer dwellings or not; and
(20) A certification that:
a. The owner or operator has read and
understands the New Hampshire asbestos management and control rules, Env-A 1800;
b. The notification is prepared in conformity
with Env-A 1800; and
c. All information contained on the form,
including any supplements attached to the form, is true, complete, and
not misleading to the best of the owner or operator’s knowledge and belief.
(c) Except as provided in (e), below, the
notification required by (a), above, shall:
(1)
Contain the information specified in (b), above;
(2)
Except as provided in (h), below, be submitted by mail, hand delivery,
or electronic means; and
(3)
Except as provided in (h), below, be submitted to the department such
that the notice is postmarked, delivered to the department, or received by the
department, at least 10 working days before any demolition activity begins.
(d) The owner or operator shall provide
notification under (a), above, even if:
(1) No ACM is contained in the facility; or
(2) The
project is a minor asbestos abatement.
(e) As specified in Env-A 1804.01(e), if a state
or local government declares that a facility or portion of a facility is
structurally unsound or in imminent danger of collapse, then the owner or
operator shall:
(1) Submit the notification required by (a), above;
(2) Submit the notification form as specified in
(a), above, such that it is postmarked or received by the department as early as possible before,
but not later than, the following working day after beginning an ordered
demolition; and
(3)
Attach a copy of the documentation from the state or local government
regarding the facility, that includes:
a. Name and title of the person who made the
determination that the facility or portion of the facility is unsafe or
structurally unsound;
b. A description of the person’s qualifications
to make the determination;
c. The date when the determination was made; and
d. A description regarding the reason that the
facility or portion of the facility is unsafe or structurally unsound.
(f) If the start date of a demolition other than
a demolition described in (e), above, or (h), below, is later than the start
date specified in a previously submitted notification, the owner or operator
shall:
(1) Notify the department by e-mail at least 24
hours before the original start date; and
(2) Submit a revised notification form,
containing all of the information specified in (b) above, and the fee specified
in Env-A 1806.08(b)(5), to the department by mail, hand delivery, or electronic
means such that the form is postmarked or received by the department within 24
hours of notifying the department, pursuant to (f)(1) above.
(g) If the start date of a demolition other than
a demolition described in (e), above, or (h), below, is earlier than the start
date specified in a previously submitted notification, the owner or operator
shall submit a revised notification form containing all of the information
specified in (b) above and the fee specified in Env-A 1806.08(b)(5), to the
department by mail, hand delivery, or electronic means such that the revised
notification form and fee are postmarked, delivered to the department, or received
by the department at least 10 business days before the revised start date of
the demolition.
(h) For a project at
a single-family property or a residential building containing 4 dwelling units or less, either the homeowner or the owner
or operator, as applicable, shall give notice to the department by electronic
means 5 business days in advance of the start of demolition as follows:
(1)
Submit the notification form specified in Env-A
1806.07; and
(2)
Submit one of the following:
a. A copy of an inspection report, as specified
in Env-A 1804.01, showing that no asbestos was found
in the facility; or
b. At least one of the following documents
showing that the proper removal of asbestos from the facility has been
completed:
1. A copy of the air clearance results as
specified in Env-A 1808.06; or
2. A copy of a waste shipment record as
specified in Env-A 1812.03.
(i) If a revision to
the notice in (h), above, is needed the homeowner or owner or operator shall
follow the requirements in (k) and (l), below, to make any revisions to the
notification.
(j) To cancel a previously submitted
notification, the homeowner, owner or operator shall submit, by email or
electronic means, a request to cancel the notification to the department,
including:
(1) The
facility address; and
(2) The start and completion dates of the
demolition specified in the notification.
(k) Except as provided in (l), below, for any
revisions to a notification other than those listed in (f) and (g), above, the
homeowner, owner or operator shall submit, by mail, hand delivery, or
electronic means, a revised notification form specified in (a), above, and
revised notification fee as specified in Env-A 1806.08, to the department
within 2 business days of discovering the need to revise the form or of being
requested by the department to revise the form.
(l) For any revisions to a notification submitted
pursuant to (h) above, the homeowner, owner or operator shall submit any
revised notification form and fee specified in (j), above, by electronic means
only.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1806.06 Notification
for Emergency Asbestos Abatement.
For emergency asbestos abatement, the owner or operator shall:
(a) Notify the department by e-mail with
the information required by Env-A 1806.03(a), as follows:
(1) As early as possible prior to abatement; or
(2) If prior notice is not possible, within 24 hours of
the beginning of each emergency asbestos abatement activity; and
(b) Submit by mail, hand delivery, or
electronic means the notification form, as specified in Env-A
1806.03(a), and notification fees, if applicable, as specified in Env-A 1806.08, to the department such that it is postmarked or received by the
department no later than 48 hours after beginning an emergency asbestos
abatement.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1806.07 Notification for Transport for Disposal.
(a) In addition to the requirements in Env-A 1812.02, the owner or operator transporting ACM for
disposal or engaging a person or entity to dispose of the ACM shall:
(1)
Complete and submit the “Asbestos Transport for Disposal Notification”,
form NHDES-A-01-024 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-024
or via the
department’s website at www.des.nh.gov, containing the
information specified in (b), below;
(2) Submit
the notification form to the department by mail, hand-delivery, or electronic
means such that the notification form and notification fee are postmarked or
received by the department no later than the day on which such transport for
disposal begins; and
(3)
Provide a copy of the notification form required by (1), above, to the
person or entity engaged to dispose of the ACM at the time the ACM is
collected.
(b) The notification form required by (a)(1),
above, shall include:
(1)
Whether the material to be transported is ACM or RACM;
(2) The
name and mailing address of the facility owner;
(3) The
physical address and facility name where the material is located;
(4) The
date when the material will be picked up;
(5) The
name and physical address of the disposal site;
(6) The
quantity(ies) of material to be transported and disposed;
(7)
Contact information, including name, email address, telephone type, and
telephone number, for the facility owner or designee;
(8) The name, mailing address, and contact
information, including name, email address, telephone type, and telephone
number, of the asbestos waste transporter;
(9)
Contact information, including name, email address, telephone type, and
telephone number, for the asbestos waste disposal facility; and
(10) A
certification that:
a. The
owner or operator has read and understands the New Hampshire asbestos
management and control rules, Env-A 1800;
b. The
notification is prepared in conformity with Env-A
1800; and
c. All
information contained on the form, including any supplements attached thereto,
is true, complete, and not misleading to the best of the owner or operator’s
knowledge and belief.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1806.08 Notification Fees.
(a) The owner or operator providing notification
to the department shall also submit the nonrefundable fee specified in (b),
below, as applicable, with the notification.
(b) Notification fees shall be nonrefundable
and as
follows:
(1) For
each notification of a type A project:
a. For
notifications submitted in calendar year 2026, $575; and
b. For
notifications submitted in calendar year 2027 and subsequent years, $725;
(2) For each notification of a type B project:
a. For notifications submitted in calendar year
2026, $450; and
b. For notifications submitted in calendar year
2027 and subsequent years, $600;
(3) For
each notification of a type C project:
a. For
notifications submitted in calendar year 2026, $100; and
b. For
notifications submitted in calendar year 2027 and subsequent years, $125;
(4) For
each annual notification, pursuant to Env-A 1806.09:
a. For notifications submitted for calendar year
2026, $1,500;
b. For
notifications submitted for calendar year 2027, $2,000; and
c. For
notifications submitted for calendar year 2028 and subsequent years, $2,500;
and
(5) For
each revised notification pursuant to Env-A 1806.04(a)(1) through (a)(8), and
Env-A 1806.05(f) and (g):
a. For notifications submitted in calendar year
2026, $40; and
b. For
notifications submitted in calendar year 2027 and subsequent years, $60.
(c) The following activities shall not be
assessed a fee:
(1) Minor asbestos abatement, as defined pursuant
to Env-A 1806.01;
(2) Initial demolition notification, pursuant to
Env-A 1806.05;
(3) Initial ordered demolition, pursuant to Env-A
1806.05(e); and
(4) Transport for disposal, pursuant to Env-A 1806.07.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1806.09 Annual
Notification.
(a) In lieu of the separate notification required
pursuant to Env-A 1806.02, and subject to (d), below, the owner or operator of
a facility expected to undergo a major asbestos abatement in the next calendar
year may file an annual notification to cover the period from January 1 of the
new calendar year to December 31 of the same year.
(b) The owner or operator shall complete and
submit:
(1) The
“Annual Asbestos Notification” form NHDES-A-01-028 dated January 1, 2026,
available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-028 or via the department’s website at www.des.nh.gov, containing the information specified in (e)
below;
(2) The notification form to the department by
mail, hand delivery, or electronic means; and
(3) The
notification form and associated fee, as specified in Env-A 1806.08(b)(4), such
that the form and fee are postmarked or received by the department at least 10
working days prior to the start of the new calendar year.
(c) This section shall only apply to individual
type C projects at the facility.
(d) The owner or operator shall submit separate,
individual notifications and fees as specified in Env-A
1806.03 and Env-A 1806.08 for each type A or type B
project that occurs at the facility.
(e) The notification form required by (b)(1),
above, shall include:
(1) Name, physical address, and county of the
facility being demolished or renovated;
(2) Description of the facility or affected part
of the facility including the size in square feet, number of floors, year
constructed, current use, and prior use of the facility;
(3) Name and mailing address of the facility owner;
(4) Contact information, including name, email
address, telephone type, and telephone number for the facility owner or designee;
(5) A certification that at least one person
certified, in accordance with Env-A 1816.02, will
supervise the asbestos abatement described by this
notification at all times; and
(6) A certification that:
a. The owner or operator has read and
understands Env-A 1800, the New Hampshire asbestos
management and control rules, Env-A 1800;
b. The notification is prepared in accordance
with Env-A 1800; and
c. All information contained on the form,
including any supplements attached thereto, is true, complete, and not
misleading to the best of the owner’s or operator’s knowledge and belief.
(f) Upon request by the department, the owner or
operator shall submit by mail, hand delivery, or electronic means to the
department within 3 business days of the request, a copy of the work plan or
inspection report for each asbestos abatement conducted under an annual
notification.
(g) After filing an annual notification, the
owner or operator shall submit quarterly reports by mail, hand delivery, or
electronic means to the department stating one of the following:
(1) That no activities have been performed; or
(2) Detailing each asbestos abatement performed under
such annual notification, as follows:
a. Name of the asbestos abatement entity;
b. Start and completion dates of removal;
c. Description of inspection conducted,
including date, type, and name of the person or entity who performed the inspection;
d. Name of the asbestos abatement supervisor and
certification number;
e. Description of activity including location, amounts, and type
of ACM removed; and
f. Name of the person or entity who provided a
clearance determination and dates when clearance determinations were done.
(h) The owner or operator shall submit quarterly
reports required by (g) within 30 days of the end of each quarter.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
PART Env-A 1807 WORK
PRACTICE REQUIREMENTS FOR MINOR ASBESTOS ABATEMENT
Env-A 1807.01 Minor
Asbestos Abatement Work Practices.
(a) The owner or operator shall ensure that any
person involved in minor asbestos abatement shall be certified in accordance
with Env-A 1815 and Env-A
1816.
(b) Any person
involved in minor asbestos abatement shall be certified in accordance with Env-A 1815 and Env-A 1816, unless
exempt under the provisions of Env-A 1815.02.
(c) Any person performing a minor asbestos
abatement shall do the following:
(1) Prevent the release of asbestos
fibers into the ambient air; and
(2) Implement the following, minimum work practices and
engineering controls:
a. Install barriers such as glovebags to assure that fibers released during abatement
activities are contained within the work area;
b. Use HEPA vacuum equipment
and wet cleaning techniques to clean up the work area following abatement until
no visible residue is observed; and
c. Follow the removal, disposal, and waste
shipment requirements specified in Env-A 1812.01
through 1812.03.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1808 GENERAL WORK PRACTICE REQUIREMENTS FOR MAJOR ASBESTOS
ABATEMENT
Env-A 1808.01
Requirements for All Major Asbestos Abatement. Except as provided in Env-A
1810.01, each owner or operator of a facility at which any
type of major asbestos abatement is or may be undertaken shall ensure
compliance with this part and part Env-A 1812.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1808.02 Asbestos
Abatement Entity
and Personnel.
(a) The owner or operator shall ensure that the
asbestos abatement entity and personnel involved in a major asbestos abatement
are licensed and certified, respectively, in accordance with Env-A 1815 and Env-A 1816.
(b) Prior to performing any of the activities
described in Env-A 1808.03 through 1808.05, any
asbestos abatement entity or personnel involved in major asbestos abatement
shall be licensed or certified pursuant to Env-A 1815
and Env-A 1816.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1808.03 Site Preparation.
(a)
Prior to the start of the abatement, the owner or operator shall prepare each
work area as follows:
(1)
Post telephone numbers of the nearest emergency facilities in a location
that is visible from the work area;
(2)
Ensure that all heating, ventilation, and air conditioning (HVAC)
systems in or passing through the work area are turned off, and take other
measures, such as taping over on/off switches, to prevent accidental start-ups
of the HVAC system;
(3)
Isolate contaminated areas from uncontaminated areas with air-tight
barriers over all openings between the work area and uncontaminated areas,
including but not limited to windows, doorways, elevator openings, corridor
entrances, ventilation openings, drains, ducts, grills, grates, diffusers, and
skylights, but excluding the decontamination enclosure system doorways, using
sheeting having a minimum thickness of 6 mil;
(4)
Post warning signs, as specified in 29 CFR 1910.1001(j)(4), at all
entrances to the work area;
(5) For
movable objects in the work area:
a.
Remove all uncontaminated objects;
b. For
all contaminated objects:
i. Decontaminate the
object; or
ii.
Prepare the object for disposal as asbestos waste prior to removal from
the work area; and
c.
Remove objects specified in b. from the work area;
(6) For
non-movable objects in the work area:
a. Decontaminate all contaminated objects; and
b. Cover with sheeting having a minimum thickness of 4
mil secured in place; and
(7) Except as provided in (b), below, completely
cover all uncontaminated floors, walls, ceiling surfaces and HVAC
system components in the work area with sheeting as follows:
a. Size and install so as to
minimize seams;
b. Do not locate sheeting seams at any
floor/wall, wall/wall or ceiling/wall corners;
c. Cover the floor with a minimum of 2 layers
of at least 6 mil sheeting and extend the sheeting at least 12 inches up each wall;
d. Cover the walls with a minimum of one layer
of at least 6 mil sheeting and extend the sheeting at least 12 inches across
the floor;
e. Cover the ceiling with a minimum of one
layer of at least 6 mil sheeting and extend the sheeting at least 12 inches
down each wall; and
f. Cover all intake and exhaust openings and
any seams in all HVAC system components with a minimum of 2 layers of at least
6 mil or thicker sheeting or with tape.
(b)
For vinyl asbestos floor tile or vinyl asbestos floor sheeting that has
mastic or felt backing, protective sheeting shall be used as follows:
(1) Ceiling sheeting as specified in (a)(7)e.
shall not be required; and
(2) Wall sheeting as specified in (a)(7)d. shall be 4 mil or thicker and cover the bottom 4 feet of each wall.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1808.04 Work
Area Ventilation.
(a) Prior to the
disturbance of asbestos, the owner or operator shall establish proper work area
ventilation as required by (b) through (e), below, in the containment area
established pursuant to Env-A 1808.03(a)(3).
(b) The work area shall be served by a sufficient number of negative pressure ventilation units
with HEPA filtration to provide one containment area air change every 15
minutes.
(c) The unit(s) shall be operated to maintain a
minimum static pressure differential of 0.02 inches of water from the time that
barrier construction is completed through the time acceptable final clean air
monitoring results are obtained.
(d) The negative pressure ventilation units shall
exhaust filtered air to the outside of the facility wherever practical.
(e) If exhausted to interior spaces, the exhaust
shall be monitored for fiber release by:
(1) Using a continuous, direct reading instrument
equipped with a data recorder located at the exhaust to record the
concentration of fibers in the air being measured; or
(2) Taking daily air samples at the exhaust and
having them analyzed to determine fiber concentration in the known volume of
air that was sampled using one of the techniques specified in Env-A 1813.03, as expeditiously as practical but no more than 24
hours after sampling.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1808.05 Worker
Decontamination.
(a)
Prior to the disturbance of asbestos, the owner or operator shall establish
proper worker decontamination as required by (b) through (i),
below, in the containment area established pursuant to Env-A 1808.03(a)(3).
(b) Each asbestos abatement site shall have a 3-stage
worker
decontamination enclosure system contiguous to the work area.
(c) The worker decontamination enclosure systems
shall consist of a clean room, shower room, and equipment room, separated from
each other by doorways with at least 2 overlapping sheets.
(d) The shower room shall have running
water that is at least 85ş F or can be mixed at the tap to achieve 85ş F.
(e) Shower room waste water
shall be collected and disposed of as asbestos waste or filtered through a 5 micron filter.
(f) Except for the doorways, the worker
decontamination enclosure system shall be airtight.
(g) All personnel entrances to and exits from the
work area shall be through the decontamination enclosure system.
(h) Each worker exiting from the work area shall
thoroughly shower so as to remove all asbestos fibers
before entering the clean room.
(i) No asbestos-contaminated individual or item
shall enter the clean room.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1808.06 Clearance
Testing.
(a) At
the completion of an asbestos abatement, or phase of that abatement, but prior
to dismantling the containment and decontamination system, the owner or
operator shall obtain the services of an independent industrial hygienist to
conduct clearance air sampling.
(b) Prior to clearance sampling, the independent
industrial hygienist shall conduct a thorough visual inspection of the work
area for the presence of visible residue.
(c) If visible
residue is found by the independent industrial hygienist, the owner or operator
shall continue cleaning the work area as specified in Env-A 1812.01(f).
(d) After determining that no visible residue
remains in the work area, the independent industrial hygienist shall take
sufficient volumes of air for clearance sampling to accurately determine, to a
95 percent probability, fiber concentrations to 0.010 fibers/cubic centimeter
(f/cc) of air.
(e) The independent industrial hygienist
shall conduct clearance air sampling no sooner than the earlier of 6 hours from the
time the cleanup procedures of wet wiping and HEPA vacuuming are completed, or
such time as all surfaces in the work area have dried. If all work area surfaces are dry at the
completion of the cleanup procedures, no waiting period shall be required prior
to beginning air sampling.
(f) The independent industrial hygienist
shall use aggressive sampling:
(1) To ensure that any fibers deposited on
surfaces within the work area are included in the sample;
(2) For all clearance sampling in schools and
school buildings; and
(3) In all areas where
uncontaminated wall, ceiling, and floor surfaces in
the work area are covered with sheeting.
(g) The owner or operator shall ensure that the
asbestos abatement entity does not dismantle the containment and worker
decontamination system until clearance air sampling demonstrates the presence
of no more than 0.010 fibers of length greater than 5 microns per cubic
centimeter of air as determined by the following:
(1) Except as provided in (2), below, phase contrast
optical microscopy, performed as described in “Asbestos and Other Fibers by
PCM: Method 7400, Issue 3”, National Institute of Occupational Safety and
Health (NIOSH) Manual of Analytical Methods (NMAM), 5th Edition,
June 14, 2019, available as noted in Appendix B; and
(2) For projects at schools subject to AHERA,
transmission electron microscopy (TEM) performed as stated in 40 CFR 763,
subpart E, appendix A: “Mandatory and Non-mandatory” or as defined and accepted
by the National Institute of Standards and Technology (NIST) for TEM
accreditation.
(h) The industrial hygienist shall submit copies
of the clearance air sampling results to the owner or operator, and the
department, by mail, hand delivery, or electronic means, within 30 days of the
date of the clearance air sampling.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1809 SPECIFIC WORK PRACTICE REQUIREMENTS FOR DEMOLITION,
ENCLOSURE AND ENCAPSULATION
Env-A 1809.01 Specific Requirements for
Demolition.
(a) Except as provided in Env-A 1804.01(e)
and 40 CFR 61.145(c)(1)(iii), prior to any demolition, including by intentional
burning, of a structure or portion of a structure, the owner or operator shall
remove all ACM in accordance with the applicable provisions of this chapter,
subject to (b) below and part Env-A 1812.
(b) If a major asbestos abatement is performed as
part of a demolition, then the owner or operator shall not dismantle the
containment and worker decontamination system until clearance air sampling
demonstrates the presence of no more than 0.10 fibers of length greater than 5
microns per cubic centimeter of air as determined by the following:
(1) Except as provided in (2), below, phase contrast
optical microscopy, performed as described in “Asbestos and Other Fibers by
PCM: Method 7400, Issue 3”, NIOSH NMAM,
5th Edition, June 14, 2019, available as noted in Appendix B; and
(2) For projects at schools subject to AHERA,
TEM performed as stated in 40 CFR 763, subpart E, appendix A: “Mandatory and
Non-mandatory” or as defined and accepted by the NIST for TEM accreditation.
(c) If a structure is being moved intact from one
location to another, the owner or operator shall not be required to remove ACM
prior to moving the structure if the ACM in the structure will not be disturbed
and meets the requirements in 40 CFR 61.145(c)(1)(i)
and (c)(1)(iv).
(d)
For an ordered demolition, pursuant to Env-A 1804.01(e), the owner or operator
shall:
(1)
Prevent the release of asbestos fibers by adequately wetting ACM with
amended water and maintaining ACM wet during demolition;
(2) Handle
all debris
in accordance with Env-A 1812.02(a), (b) and (d); and
(3) Submit
a waste shipment record in accordance with Env-A
1812.03.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1809.02 Specific
Requirements for Enclosure of RACM.
When an owner or operator chooses to abate RACM via enclosure, the owner
or operator shall comply with the requirements of Env-A
1808 and the following:
(a) Ensure that enclosures are airtight and of
permanent construction, such that the area being enclosed is inaccessible;
(b) Prior to commencing work, wet all RACM that
has the potential to be disturbed during the installation of hangers, brackets,
or other portions of the enclosure; and
(c) Designate enclosures for RACM by posting
permanent signs, labels, color coding, or some other readily visible mechanism
on the enclosure to warn individuals who may be required to disturb the
enclosure.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1809.03 Specific
Requirements for Encapsulation of RACM.
When an owner or operator chooses to abate RACM via
encapsulation, the owner or operator shall comply with the requirements of Env-A 1808 and the following:
(a) Ensure that filler material applied to gaps
in existing material contains no asbestos, adheres well to the substrate, and
provides a suitable base for the encapsulant;
(b) Apply encapsulants using only low pressure airless spray equipment with nozzle pressure
and tip size set according to the manufacturer’s recommendations; and
(c) Specifically designate
encapsulated RACM by placing permanent signs, labels, color coding, or some
other readily visible mechanism on the encapsulated RACM to warn individuals
who may in the future be required to disturb the material.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1810 ALTERNATIVE WORK PRACTICE REQUIREMENTS FOR
SPECIFIC ACM
Env-A 1810.01 Applicability.
(a) The owner or operator of a facility who
removes asbestos roofing materials, asbestos siding, and other preformed
cementitious asbestos materials shall comply with this Part.
(b) If the conditions specified in this Part are
not met, then the owner or operator shall be subject to the requirements of
Env-A 1808.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1810.02 Asbestos-Containing
Asphalt Roofing Materials.
(a) The owner or operator who removes non-friable
asbestos-containing asphalt roofing material from a roof and does not sand,
saw, grind, abrade, or otherwise treat the roofing material in a manner that
might create a fine dust or particles, shall comply
with the following:
(1) The
surrounding ground shall first be protected with poly drop cloths such that no
roofing material can come into contact with the
ground; and
(2) All roofing material waste shall be removed,
packaged, labeled, and disposed of as specified in Env-A 1812.01(b), Env-A
1812.01(c), Env-A 1812.01(g), Env-A 1812.02 and Env-A 1812.03.
(b) The owner or operator performing major
asbestos abatement of asbestos roofing material who removes RACM from a roof, shall
comply with
following:
(1) The
asbestos abatement entity and workers shall be licensed and certified in
accordance with Env-A 1815 and Env-A 1816;
(2) All
roofing material waste shall be removed, packaged, labeled, and disposed of as
specified in Env-A 1812.01(b), Env-A 1812.01(c), Env-A 1812.01(g), Env-A 1812.02 and Env-A 1812.03;
(3) A
HEPA-filtered tool shall be used to prevent generation of visible emissions;
(4) Water shall be applied at the point of
abrasion with a hose or an airless sprayer and in sufficient
volume so that no visible emissions result from the operation other than water spray;
(5) All site preparation requirements specified
in Env-A 1808.03(a); and
(6) All worker decontamination requirements
specified in Env-A 1808.05.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1810.03 Asbestos-Containing
Cementitious Roofing or Siding Materials.
The owner or operator who removes cementitious ACM from the side or roof
of a building and does not sand, saw, grind, abrade, or otherwise treat the ACM
in a manner that might create a fine dust or
particles, shall comply with the following:
(a) The asbestos abatement entity and workers
shall be licensed and certified in accordance with Env-A
1815 and Env-A 1816;
(b) The surrounding ground shall first be
protected with poly drop cloths such that no ACM can come
into contact with the ground;
(c) Cementitious ACM shall be removed intact, to
the extent possible, by prying out or cutting fasteners;
(d) Cementitious ACM shall be carefully lowered
to the ground, not dropped, thrown, or slid;
(e) All ACM waste shall be removed, packaged,
labelled, and disposed of in accordance with Env-A 1812.01(b), Env-A
1812.01(c), Env-A 1812.01(g), Env-A 1812.02 and Env-A 1812.03; and
(f) All site preparation requirements specified
in Env-A 1808.03(a) shall be completed.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1811 WORK PRACTICE REQUIREMENTS FOR GLOVEBAGS AND OTHER
ALTERNATIVE PROCEDURES
Env-A 1811.01 Glovebags.
(a) The owner or operator shall use glovebags only in accordance with the provisions of this
section, Env-A 1808.03(a)(1) through (a)(5) and Env-A
1808.05.
(b) The owner or operator shall use glovebags only under such conditions that their use will
not threaten any release of fibers at locations outside of the glovebag, including placing a single layer of 6 mil
sheeting under the glovebag.
(c) The owner or operator shall use glovebag procedures to conform with the requirements of 29
CFR 1926.1101(g)(5)(ii)(B)(1) through (9), July 1, 2023.
(d) Following completion of a glovebag
procedure or series of glovebag procedures in a
contiguous area during major asbestos abatement, the owner or operator shall
ensure that clearance inspection and air sampling are conducted in accordance
with Env-A 1808.06.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1811.02 Other
Alternative Procedures.
(a) The owner or operator shall submit any
request for an alternative procedure to an asbestos abatement requirement
specified in Env-A 1807 through Env-A
1810, Env-A 1811, Env-A
1812.01 and Env-A 1812.02 as follows:
(1) Complete a request for a waiver containing
the information required in Env-A 1820.03(a)(1) through Env-A 1820.03(a)(7);
(2) Submit the request as
follows:
a. If the requirement is specified in 40 CFR
61.145, then submit to both EPA Region I and the department; and
b. If the requirement is not specified in 40 CFR
61.145, then submit only to the department; and
(3) Follow the requirements in (c) and (e), below.
(b) The department shall not approve an
alternative procedure for control of emissions from an
asbestos abatement activity unless:
(1) The EPA approves the
request in writing or notifies the department in writing that the requested
procedure does not need to be approved by the EPA; and
(2) The
criteria specified in (d), below, are met.
(c) After obtaining a written approval or waiver
from the EPA and at least 10 days in advance of the proposed
starting date for an alternative abatement procedure, the owner or operator
shall submit the following to the department to use the alternative procedure:
(1) The
notification form as specified in Env-A 1806.02 and
the fee as specified in Env-A 1806.08;
(2)
Attach such additional information as is necessary to identify the
unique aspects of the asbestos abatement that led to the request; and
(3)
Attach a detailed explanation of how the alternative procedure will be
used.
(d) The department shall approve the alternative
procedure if:
(1) The
alternative procedure provides an equivalent or greater measure of control of
asbestos fiber release than the procedure required by these rules; or
(2) Using the alternative procedure creates an
equivalent or lower potential hazard to life, health, and property than using
the procedures required by these rules.
(e) No work using an alternative procedure shall
begin without the written approval or abstention of EPA Region I, for requests
pursuant to (a)(2)a., and the department.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1812 ACM
REMOVAL AND DISPOSAL REQUIREMENTS
Env-A 1812.01 ACM Removal Procedures.
(a)
Except for an ordered demolition, as provided in Env-A 1809.01(d), the
procedures specified in this section shall apply to all removal of ACM.
(b) The owner or operator shall take the
following actions to prevent the release of fibers until properly packaged in
accordance with Env-A 1812.02(a):
(1) Adequately wet all ACM with amended
water before removal; and
(2) Maintain the ACM wet during and after
removal.
(c) The owner or operator shall carefully lower
all ACM to the ground or floor, not drop, throw, or slide the ACM.
(d) The owner or operator shall remove structural
members not previously stripped of ACM as follows:
(1) Intact or in large sections whenever
possible; and
(2) By carefully lowering, not dropping,
throwing, or sliding, them to the floor.
(e) The owner or operator shall remove ACM that
is not associated with structural members in small sections and by not allowing
the ACM to accumulate on the floor.
(f) Following removal, the owner or operator
shall perform cleanup procedures using repeated HEPA vacuuming and wet cleaning
techniques until no visible residue is observed in the work area.
(g) Pursuant to 40 CFR 61.145(c)(7), if the
temperature at the point of wetting is below 0 degrees Celsius or 32 degrees
Fahrenheit, then the owner or operator may suspend wetting and keep records as
specified in Env-A 1805.02(a).
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1812.02 ACM
Disposal Procedures.
(a)
Prior to removing ACM from containment or from the facility location, if an
ordered demolition, the owner or operator shall package ACM in accordance with
Env-Sw 901.06 and as follows:
(1) For
all loose ACM take the following actions to prevent the release of fibers:
a. Adequately wet the ACM with
amended water;
b.
Place the ACM into leak-tight containers or double impermeable bags of
at least 6 mil thickness each; and
c. Seal
the containers or bags with tape, as applicable;
(2) Wrap
large components or structural members that were removed intact leak-tight in 2 layers
of 6 mil sheeting and seal the sheeting with tape; and
(3) Line the containers, into which bulk unwrapped
asbestos waste is placed, with at least 20 mil of sheeting.
(b) After completing abatement work or an ordered
demolition, the owner or operator shall:
(1) Properly
label packaged ACM prior to delivering ACM to a permitted disposal facility or
having the ACM picked up for disposal by a transporter, label ACM in accordance
with Env-Sw 901.06, and as specified in (2) and (3), below;
(2) As
specified in 40 CFR 61.150(a)(1)(iv), label the containers or wrapped materials
using warning labels, as follows:
a. Printed
in letters of sufficient size and contrast so as to be
readily visible and legible; and
b. As
specified in 29 CFR 1910.1001(j)(5) or 1926.1101(k)(8); and
(3) For
asbestos-containing waste material to be delivered to a permitted disposal
facility, label containers or wrapped materials with the name of the generator
and location at which the waste was generated.
(c)
Except as provided in (e), below, the owner or operator shall remove
packaged ACM, from the work site as soon as practicable, but in
no event longer than 30 days, following the completion of the abatement work,
in accordance with the following removal procedures:
(1) By either:
a. Delivering the ACM to a permitted disposal
facility; or
b. By having the ACM picked up for disposal by
a transporter; and
(2) By submitting an “Asbestos Transport for
Disposal Notification” form, as specified in Env-A
1806.06; and
(d) The owner or operator shall transport and
dispose of the ACM, as specified in 40 CFR 61.150, specifically including 40
CFR 61.150(d), as referenced in Env-A 1801.04 and Env-Sw 901.04.
(e) The owner or operator of
asbestos abatement conducted under an annual notification filed pursuant to
Env-A 1806.09 shall be exempt from the time limit
specified in (c), above, provided the owner or operator:
(1)
Manages the ACM, in accordance with Env-Sw 901;
(2)
Removes the ACM from the facility, no later than 30 days after facility closure,
in accordance with the following removal procedures:
a. By delivering the ACM to a permitted
disposal facility; or
b. By having the ACM picked up for disposal by
a transporter; and
(3) If a subsequent annual notification is not
submitted, then remove packaged ACM from the worksite by January 31 of the
following year.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1812.03 Waste Shipment Record
(a) Within 30 days after delivery of ACM to a
permitted disposal facility or the ACM is picked up for disposal by a
transporter, the owner or operator shall submit a copy of the waste shipment
record to the department by mail, hand delivery, or electronic means.
(b) If
the ACM is picked up for disposal by a transporter, the owner or operator shall
submit to the department by mail, hand delivery, or electronic means:
(1) A copy of the waste shipment record signed
by a representative of the permitted disposal facility; or
(2) A statement that the waste shipment record
signed by a representative of the permitted disposal facility has not been
received.
(c) If
a statement pursuant to (b)(2) above is submitted, then the owner or operator
shall:
(1) Within 35 days of the date
the ACM was accepted by the initial transporter, contact the transporter or the
permitted disposal facility to determine the status of the waste shipment; and
(2) Within 10 business days of
contacting the permitted disposal facility or transporter, submit a written
report to the department, including the following information:
a. A copy of the waste shipment
record for which a confirmation of delivery was not
received; and
b. A cover letter signed by the
owner or operator explaining the efforts taken to locate the asbestos waste
shipment and the results of those efforts.
(d) The waste shipment record shall include the
following information:
(1) Name, mailing address, and
telephone number of the owner or operator;
(2) Physical address where the
ACM was generated;
(3) Name and address of the state
office responsible for administering the asbestos NESHAP program;
(4) Number of containers used to transport the ACM;
(5) Approximate quantity of each type of ACM in
cubic meters or cubic yards;
(6) Name and telephone number of the permitted
disposal facility representative;
(7) Name and physical site location of the
permitted disposal facility;
(8) Date of transport;
(9) Name, address, and telephone number of
transporter(s); and
(10) A certification by each transporter of the
contents of this consignment as follows:
a. They are fully and accurately described by
proper shipping name;
a. They are classified, packaged, marked, and
labeled; and
b. They
are in all respects in proper condition for transport by highway, according to applicable international and
government regulations; and
(11) A certification of receipt of the ACM
covered by the waste shipment record by the permitted disposal facility
representative.
(e) If
the owner or operator delivers the ACM, the owner or operator shall provide a
copy of the waste shipment record to the permitted disposal facility at the
same time as delivery.
(f)
The owner or operator shall retain a copy of all waste shipment records for at
least 5 years from the date received at the permitted disposal facility.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1813 ASBESTOS ANALYTICAL REQUIREMENTS
Env-A
1813.01 Applicability. This part shall apply to the analysis of all
asbestos samples.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1813.02 Analytical Proficiency. The following criteria shall apply to the
analysis of asbestos:
(a)
For air sampling proficiency standards, the laboratory analysis of air
samples shall be performed by the following:
(1) A laboratory presently accredited for asbestos
analysis by the American Industrial Hygiene Association (AIHA);
(2) An analyst presently listed in the AIHA
Asbestos Analysis Registry; or
(3) An individual who has successfully completed
the NIOSH Course #582 “Sampling and Evaluating Airborne Asbestos” and whose laboratory
presently shows evidence of a proficient rating in the AIHA Proficiency
Analytical Testing Program (PAT Program);
(b)
For bulk sampling proficiency standards, the laboratory shall show
evidence of a current proficiency rating in the National Volunteer Laboratory
Accreditation Program (NVLAP), such as being listed in the most recent copy of
the Federal Register containing the EPA’s Accredited Laboratories AHERA list
for Accredited Polarized Light Microscopy Laboratories; and
(c)
The analysis of bulk samples shall be performed by, or under the
supervision of, an analyst who has successfully completed an approved course of
training in the techniques and procedures for identification of asbestos in
bulk samples such as the McCrone Institute Bulk Analysis course.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1813.03 Analytical Techniques.
(a)
Clearance air samples shall be submitted for analysis to a laboratory
that uses phase contrast microscopy (PCM) for the analysis of air samples for
asbestos content unless accredited by the NIST for TEM, in which case the
laboratory may analyze air samples using TEM.
(b)
Analytical procedures for PCM shall be in accordance with NIOSH Method
7400, Issue 3, entitled “Fibers” published in the NIOSH Manual of Analytical
Methods, 5th Edition, June 14, 2019, available as noted in Appendix
B. Air volumes sampled shall be
sufficient to accurately determine, to a 95 percent probability, fiber
concentrations of 0.01 fibers/cubic centimeters of air (f/cc).
(c)
Analytical procedures for TEM shall be as stated in 40 CFR Part 763,
subpart E, appendix A: “Mandatory and Non-Mandatory” or as defined and accepted
by the NIST for TEM accreditation.
(d) Analytical procedures for PLM shall be as
stated in 40 CFR Part 763, subpart E, appendix E: “Interim Method of the
Determination of Asbestos in Bulk Insulation Samples” or as defined and
accepted by the NIST for PLM accreditation.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A
1814 APPROVAL OF ASBESTOS TRAINING
PROVIDERS AND COURSES; OBLIGATIONS OF TRAINING PROVIDERS
Env-A
1814.01 Training Approval.
(a) Prior to any training
activity, a training provider offering training
courses, in accordance with the model accreditation plan (MAP), described in 40
CFR 763, Subpart E, Appendix C, that are intended to fulfill licensure and
certification requirements for asbestos abatement and school asbestos planning,
shall:
(1) Provide
notification pursuant to (b), below, of an accredited training course to be
held in New Hampshire, at least 10 working days prior to offering the
accredited training course; or
(2) Submit an application to the department, pursuant to Env-A 1814.02 and Env-A 1814.04, to be
able to offer an approved training course.
(b) Prior to offering an
accredited training course in New Hampshire, the training provider shall
complete and submit to the department by mail, hand delivery, or electronic
means, on or attached to the “Accredited Training Course Notification”, form
NHDES-A-01-025, dated August 22, 2024, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-025 or via the department’s website at www.des.nh.gov, the following information:
(1) Name,
mailing address, telephone number, telephone type, fax number and email
address of the training
provider;
(2) Name(s) of
the specific course(s);
(3) Date
and time that the course(s) will be held;
(4) Location
where the courses will be held;
(5) Whether the
course(s) are intended for initial certification or as a refresher;
(6) Name of the
state or federal agency that approved the course(s);
(7) A copy
of all approval(s) given by state and federal agencies to the training provider
for the accredited
training course: and
(8) A certification by a responsible person that:
a. The applicant has read and understands the
New Hampshire asbestos management and control rules, Env-A 1800;
b. The notification is prepared in conformity
with Env-A 1800; and
c. All
information contained on the form, including any supplements attached thereto,
is true, complete, and not misleading to the best of the applicant’s knowledge
and belief.
(c) A training provider offering an accredited
training course in New Hampshire shall allow a representative of the department
to audit courses and review examinations without cost to the department.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1814.02 Request for Approval of
Training Course.
(a) A training provider seeking approval
of one or more training course(s) shall complete and submit to the department
by mail, hand delivery, or electronic means, on or attached to the “Approval of
Asbestos Training Provider and Courses”, form NHDES-A-01-026, dated August 22,
2024, and located at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-026 or via the department’s website at www.des.nh.gov,
the following for each proposed course:
(1) The name(s) of the specific
course(s) for which approval is sought;
(2) Whether the course(s) is intended for
initial certification or as a refresher;
(3) An outline of each course as
follows:
a. The topics to be covered;
b. Amount of time to be
given to each topic;
c. Name(s) of the
instructor(s) for each topic; and
d. Name of the
individual(s) responsible for developing the instructional program for each topic;
(4) A copy of the instruction
manual for each course and all printed material to be provided to the
student(s) for each course;
(5) A description of the
teaching methods to be employed, including a description of any audio-visual
aids to be used;
(6) A description of the
hands-on training to be provided and facility to be used, including the
following:
a. Protocol for instruction;
b. Number of students to be
accommodated; and
c. The number of instructors;
(7) A description of the
equipment that will be used in both classroom lectures and in hands-on training;
(8) A list of the name and
qualifications of each individual who will provide the
training for each course, including education, training and experience;
(9) An example of the written
examination to be given in each course;
(10) A copy of the certificate
of completion to be given to successful course participants for each course;
and
(11) Any additional information
that may be needed to demonstrate that the proposed course will meet the
criteria for approval specified in Env-A 1814.03.
(12) A statement signed by a responsible person certifying that:
a. The applicant has read, and understands, the
New Hampshire asbestos management rules;
b. The application was prepared in conformity with
the rules for asbestos control; and
c. All information contained in the application,
including any supplements attached, is true, correct, and not misleading to the
best of the applicant’s knowledge and belief.
(b) For each training certificate, the training
provider shall include the following minimum information on the certificate:
(1) A
unique certificate number;
(2) Name of
the person who received the training;
(3)
Discipline of the training course completed;
(4) Date(s) and location of the training course;
(5) Date of
the examination;
(6) An
expiration date of one year after the date upon which the person successfully
completed the course and examination;
(7) The
name, address, and telephone number of the training provider that issued the
certificate; and
(8) A
statement that the person receiving the certificate has successfully completed
the requisite training for asbestos accreditation under TSCA Title II (the
MAP.)
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1814.03 Criteria for Approval of
Training Courses. The department
shall approve a training course for which an application is submitted pursuant
to Env-A 1814.02 or Env-A 1814.08(b) if the following
criteria are met:
(a)
The training course will be offered by an approved training provider
pursuant to Env-A 1814.04 and Env-A 1814.08;
(b)
For a training course required for certification, the course is specific
to the discipline and meets the requirements for that
discipline as set forth in the MAP;
(c)
The topic or subject of instruction will be presented through a
combination of lectures, demonstrations, and field trips or hands-on practice;
(d)
For a course requiring hands-on training, the course will:
(1) Be presented in an
environment suitable to permit participants to have actual experience
performing tasks associated with asbestos abatement;
(2) Not be replaced by
demonstrations not involving individual student participation; and
(3) Maintain a student to
instructor ratio of not greater than 10 to one;
(e)
The training course will meet the following time restrictions:
(1) The total hours required by
AHERA shall be completed within a 2-week time frame;
(2) Attendees shall not be
required to attend more than 8 hours of actual training in a single 24-hour
period; and
(3) Evening instruction shall
not exceed a maximum of 4 hours in any single session;
(f)
For an asbestos training course outlined in the MAP, no fewer than 2
qualified instructors will provide the training, except that one instructor may
conduct courses for asbestos abatement workers provided that the instructor is
both field-experienced and qualified;
(g)
For a training course for asbestos abatement workers, asbestos abatement
supervisors, asbestos inspectors, asbestos management planners, or asbestos
abatement project designers, the course will meet those
requirements specific to each discipline as set forth in the MAP;
(h)
Successful completion of a course for asbestos abatement workers,
asbestos inspectors, and asbestos management planners will be demonstrated by
achieving a score of at least 70 percent on a written examination consisting of
50 multiple choice questions;
(i) Successful completion of a course for
asbestos abatement supervisors and asbestos abatement project designers will be
demonstrated by achieving a score of at least 70 percent on a written
examination consisting of 100 multiple choice questions;
(j) If the proposed course is a refresher
training course, the course will:
(1) Meet the applicable
requirements as set forth in the MAP;
(2) Be specific to only one
AHERA discipline; and
(3) Require successful
completion of the course to be demonstrated by achieving a score of at least 70
percent on a written examination consisting of 25 multiple choice questions;
and
(k) The instructor for a training course is
qualified based on their education, training, and experience to teach the
course.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1814.04 Request
for Approval of Training Providers.
Any person who wishes to obtain department approval as a training
provider shall complete and submit to the department by mail, hand delivery, or
electronic means, on, or as an attachment to, the “Approval of Asbestos
Training Provider and Courses” form specified in Env-A 1814.02(a), the
following:
(a) The name, physical address, mailing address,
email address, fax number, telephone type, and telephone number of the
applicant and all alternative or previous names under which the applicant
conducts or intends to conduct training;
(b) Whether the application is new or a renewal
of an approval;
(c) Whether the applicant is licensed, certified,
or permitted by the EPA or any state other than New Hampshire, to provide
training for one or more asbestos training courses;
(d) If applicable, attach a copy of each written
approval from the EPA and each state agency that has licensed, certified, or
given other forms of approval to the applicant to provide asbestos training
courses, including the name, mailing address, and telephone number of a contact
person at the EPA or the state agency giving such approval;
(e) Whether any state or federal agency has taken
any of the following with regard to environmental,
health, or safety requirements against the applicant within the previous 10
years:
(1)
Enforcement action; or
(2)
Action related to training provider or training course approval, such as
suspension, revocation, or denial;
(f) If applicable, attach a copy of each state or
federal enforcement action or other action against the applicant including
information as to whether or how the action was resolved, if not previously
submitted to the department;
(g) If there are any unresolved or pending state
or federal enforcement or approval actions against the applicant with regard to asbestos abatement training or work, an
explanation of the circumstances surrounding the actions which demonstrates
that the applicant can be expected to adhere to applicable requirements if
approved as a training provider pursuant to this part;
(h) Any additional information that might be
needed to demonstrate that the training provider meets the criteria specified
in Env-A 1814.05;
(i) The name, title,
mailing address, email address, telephone type, and telephone number of a
contact for the applicant; and
(j) A statement signed by a responsible person
certifying that:
(1) The
applicant has read, and understands, the New Hampshire asbestos management and
control rules, Env-A 1800;
(2) The
application was prepared in conformity with Env-A
1800; and
(3) All
information contained in the application, including any supplements attached,
is true, complete, and not misleading to the best of the applicant’s knowledge
and belief.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1814.05 Criteria
for Approval of Training Providers.
The department shall approve a training provider for which an
application is submitted pursuant to Env-A 1814.04 or
Env-A 1814.08(b) if all of the following criteria are
met:
(a)
All of the information required by Env-A
1814.04 or Env-A 1814.08(b), as applicable, has been submitted;
(b)
The applicant has signed the certification required by Env-A 1814.04(i);
(c)
If information is submitted in response to Env-A 1814.04(f) or Env-A
1814.08(b)(1), the department makes a determination
that the applicant can be expected to adhere to applicable requirements if
approved as a training provider pursuant to these rules; and
(d)
The applicant issues or will issue a training certificate, as specified
in Env-A 1814.02(b) to each student who successfully completes an initial or
refresher course.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1814.06 Training Provider
Responsibilities. Each training
provider approved pursuant to Env-A 1814.07 shall:
(a)
Comply with the recordkeeping requirements for training providers as set
forth in the MAP;
(b)
Retain records for a minimum of 5 years from the date that the course
was taught, of the following:
(1) The title of each initial
and refresher course taught;
(2) The date(s) on which the
course was provided; and
(3) The name, address, and date
of birth of each student who successfully completed the course;
(c)
Notify the department in writing within 30 days following any change in
course content, training aids used, facility used, or other matters that would
alter the instruction from that described in the application. Minor changes in agenda, such as guest
speakers, if otherwise qualified, and course schedule shall be exempt from this
notification requirement;
(d) Distribute and use as part of the
course content any information or training aids
furnished by the department which reflect changes in federal regulations or
state rules;
(e)
Allow a representative of the department to audit courses and review
examinations without cost to the department;
(f)
Provide written notification to the department at least 10 working days
prior to providing any asbestos approved training courses, including:
(1) Name of training provider;
(2) Course(s) to be given; and
(3) Location and date(s) of
course(s);
(g)
Make the records retained in accordance with
(b), above, available to the department upon request; and
(h) Upon the request of the department
after the conclusion of any approved training, submit a course roster to the
department noting:
(1) Name and date(s) of the
course; and
(2) The name, certificate
number, and exam grade for each attendee.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1814.07
Training Provider and Training
Course Application Processing and Issuance Criteria.
(a)
The department shall review and process applications for training
providers and training courses in accordance with RSA 541-A:29, Env-A 200, and
Env-C 200, as applicable.
(b)
Within 30 days of receipt of the application, the department shall
notify the applicant of any errors or omissions and request any additional
documentation from the applicant needed to complete an application submitted
pursuant to Env-A 1814.02, Env-A
1814.04, or Env-A 1814.08(b).
(c) If the department obtains credible
information indicating that a reason exists to suspend or revoke a training
provider approval, as specified in Env-A 1814.09(h) below, while an application
for training provider approval is pending, the department shall notify the
training provider of the information and offer an opportunity for the training
provider to respond to the information prior to a decision being made on the
application.
(d) A training provider shall respond within 15
working days to the department’s notification in (b) or (c), above.
(e) The department shall approve the application
if the application:
(1) Meets
the criteria specified in Env-A 1814.03 and Env-A 1814.05; and
(2) If applicable,
contains the information required by Env-A 1814.08(b).
(f)
The department shall deny any application if:
(1) The application does not
include the information required by Env-A 1814.02,
Env-A 1814.04, or Env-A 1814.08(b);
(2) The
applicant does not respond to the department’s request pursuant to (b) or (c),
above; or
(3) The department determines that:
a. A reason
exists to suspend or revoke a license or
certification as specified in Env-A 1814.09(h); and
b. Either:
1. The applicant acted with intent to deceive; or
2. The deficiency(ies) cannot be
corrected so as to conform to applicable requirements.
(g)
The department shall notify the applicant of its decision in
writing. If the application is denied,
the notice shall specify the reason(s) for denial and that the applicant has an
opportunity to appeal as specified in (h), below.
(h) If the applicant wishes to appeal the
decision, the applicant shall file such appeal following the procedures set
forth in Env-A 1814.10.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1814.08 Duration
and Renewal of Training Provider and Training Course Approvals.
(a)
Training provider and training course approval shall be effective for
one year from the date of issuance as indicated on the written approval.
(b)
If the training provider wishes to renew the approval, the training
provider shall:
(1) Submit a completed
application for renewal, on the “Application for Asbestos Training Provider and
Courses” form specified in Env-A 1814.02(a), no later than 30 days prior to the
expiration date of the current approval, including the information specified in
Env-A 1814.02 and Env-A 1814.04;
(2) Attach any additional
information and documentation required by this chapter, including a list of the
type of asbestos training courses offered in the past year with the number of
students that successfully completed the courses; and
(3) Apply for renewal no later
than 3 years after the expiration date of the previous approval.
(c) The department shall not accept a renewal
application from a previously approved training provider whose approval expired
more than 3 years prior to the date of the renewal application, but shall
inform the person that if approval is desired, a new application shall be
submitted pursuant to Env-A 1814.02 and Env-A 1804.04.
(d) The department shall
process a renewal application as specified in Env-A
1814.07.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1814.09 Suspension
and Revocation of Approval for a Training Provider.
(a) If the department obtains credible
information indicating that one or more reasons to
suspend or revoke a training provider approval as specified in (h), below,
exists, the department shall notify the training provider in writing of:
(1) The
department’s intended action;
(2) The
reason(s) for the intended action; and
(3) The
date by which the training provider shall file a
written request for an adjudicative hearing if the training provider wishes to
contest the proposed action, which date shall be 15 working days from the date
of the department’s notice.
(b) If the department receives a written request
for an adjudicative hearing in accordance with (a)(3), above, the department
shall proceed in accordance with RSA 541-A:31 and Env-C 200 as applicable to
adjudicative proceedings.
(c) If the department does not receive a written request for
an adjudicative hearing in accordance with (a)(3), above, the approval shall be
deemed suspended or revoked, as specified in the notice issued pursuant to (a),
above, as of the 16th working day from the date of the department’s
notice.
(d) The department shall suspend a training provider approval if the department determines
that one or more reason(s), as specified in (h),
below, to suspend or revoke a training provider approval exists
but that:
(1) The training provider did not act with intent
to deceive; and
(2) The deficiency(ies)
can be corrected so as to conform to applicable
requirements.
(e) If the department suspends a training provider approval, the department shall:
(1) Notify the training provider in writing of
the specific deficiency(ies);
(2) Specify a reasonable time to correct the
deficiency(ies), which shall be determined based on
the number and nature of the deficiency(ies); and
(3) Inform the training provider in the written
notice that if the deficiencies are not corrected within the specified time,
the approval shall be revoked.
(f) The department shall revoke a training
provider approval if the department determines that one or more reason(s), as specified in (h), below, to suspend or revoke
a training provider approval exists and that:
(1) The training provider acted with intent to
deceive; or
(2) The deficiency(ies)
cannot be corrected so as to conform to applicable
requirements.
(g) If the department revokes a training provider
approval, the department shall notify the training provider in writing of the
revocation and the reason(s) therefor.
(h) The department shall suspend or revoke a
training provider approval if the training provider:
(1) Is not
conducting training that meets the requirements of Env-A
1814.02 or Env-A 1814.03;
(2) Has failed to comply with Env-A 1814.06;
(3) Misrepresents the extent of a training
course’s approval by a state or the EPA;
(4)
Falsified approval records, instructor qualifications, or other approval
information;
(5) Submits materially false or
fraudulent information on an application; or
(6) Meets any of the criteria
specified in Env-C 209.02 or Env-C 209.03.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1814.10 Appeal. A training provider aggrieved by a department
decision made pursuant to Env-A 1814.07, to deny an application, or Env‑A
1814.09, to revoke an approval, who wishes to
appeal the decision shall appeal to the air resources council, within 30 days
of the department’s decision, in accordance with RSA 21-O:14 and the rules
adopted by that council, Ec-Air 200.
Source. (See
Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for
Env-A 1800) #14104, eff
11-1-24, EXPIRES: 11-1-34
PART Env-A 1815 LICENSING AND CERTIFICATION FOR ASBESTOS ABATEMENT AND SCHOOL ASBESTOS PLANNING
Env-A 1815.01 Applicability.
(a) Pursuant to RSA 141-E:10 and RSA 141-E:11,
the rules in this part shall apply to any asbestos abatement entity, employee,
or individual that engages in any asbestos abatement or school asbestos
planning activities.
(b) Pursuant to the AHERA regulations promulgated by the EPA, individuals who conduct asbestos inspections of
schools, or provide services as an asbestos management planner or asbestos
abatement project designer to schools, shall apply to the department for
certification as either an asbestos inspector, asbestos management planner, or
asbestos abatement project designer.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.02 Exemptions.
(a) Any individual,
other than a maintenance worker, who performs
only minor asbestos abatement shall be exempt from the requirement to obtain an
asbestos abatement entity license in
accordance with Env-A 1816.01, provided that such individual:
(1) Has a current asbestos abatement supervisor
or worker certification issued pursuant to Env-A
1816.02 or Env-A 1816.03; and
(2) Complies with Env-A
1812.01 through Env-A 1812.03.
(b) A maintenance
worker who works in one or more buildings that
contain ACM shall be exempt
from licensing requirements for asbestos abatement entities and certification
requirements for asbestos abatement supervisors and asbestos abatement workers
provided that the maintenance worker:
(1) Receives 16 hours of initial training as described
in 40 CFR 763.92(a)(1) and (2);
(2) Receives 4 hours of refresher training annually, which refresher courses shall include changes in
federal and state regulations, developments in state-of-the-art procedures, and
a review of key aspects of the initial training course; and
(3) Performs only operations, maintenance, and repair
activities that are small-scale and short-duration.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.03 Initial
Application Procedures and Issuance Criteria.
(a) An employee or
individual seeking an initial certification or an asbestos abatement entity
seeking an initial license for asbestos abatement or school asbestos planning
shall submit a complete application to the department by mail, hand delivery,
or electronic means including the following:
(1) The information
specified in Env-A 1815.04 and Env-A
1816.01 through Env-A 1816.06, as applicable;
(2) The signature and certification required by
Env-A 1815.06;
(3) If
the applicant is an employee or individual, one clear,
color photograph, taken within the last 5 years, of
the applicant’s full face, meeting passport photograph requirements, including
the name of the applicant;
(4) If the applicant is an employee or
individual, a copy of each
dated training certificate which shows the applicant’s training to be
current and in accordance with Env-A 1815.13 at the
time of application;
(5) If the applicant is an asbestos abatement
entity, a copy of the training certificate held by each responsible
person who fulfills the licensing requirement specified in Env-A
1816.01(c)(11); and
(6) The appropriate
application fee as set forth in Env-A 1815.09.
(b) An applicant may
submit a combination application for asbestos inspector, asbestos
management planner, and asbestos abatement project designer, provided the
applicant fulfills the application requirements for each discipline for which
application is being made and applies for the certifications at the same
time. Any applications received
separately from the same applicant shall be treated as separate applications.
(c) The department
shall review and process applications in accordance with RSA 541-A:29, Env-A
200 and Env-C 200, as applicable.
(d) Within 30 days of receipt of the
application, the department shall notify the applicant of any errors or
omissions and request any additional documentation from the applicant needed to
complete an application submitted pursuant to (a), above.
(e) If the department
obtains credible information indicating that a reason exists to suspend or
revoke a license or certification as specified in Env-A 1815.10(g), while an
application for a license or certification in pending, the department shall
notify the applicant of the information and offer an opportunity for the
applicant to respond to the information prior to a decision being made on the
application.
(f)
An applicant shall respond within 15 working days to the department’s
notification in (d) or (e), above.
(g) The department
shall approve an application and issue an initial license or certification for
any of the individual disciplines specified in Env-A
1816.01 through Env-A 1816.06, provided the applicant
meets the requirements specified in (a), above.
(h) The department shall deny an application if:
(1) The application does not include the
information required by (a), above;
(2) The
applicant does not respond to the department’s request pursuant to (d) or (e),
above; or
(3) The
department determines that:
a. A reason exists to suspend or revoke a license or certification as
specified in Env-A 1815.10(g); and
b. Either:
1. The applicant acted with intent to deceive;
or
2. The
deficiency(ies) cannot be corrected so as to conform to applicable requirements.
(i) The department
shall notify the applicant of its decision in writing. If the application is denied, the notice
shall specify the reason(s) for the denial and that the applicant has an
opportunity to appeal as specified in (j), below.
(j) If the applicant wishes to appeal the
decision, the applicant shall file such appeal following the procedures set
forth in Env-A 1815.11.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.04 Information
Required for All Applications. Each applicant shall
supply the following information on or as an attachment to the application form specified in Env-A 1816.01
through Env-A 1816.06, as applicable:
(a) The name, mailing
address, telephone number, telephone type, and email address of the applicant;
(b) Date of birth of the applicant, if an individual;
(c) If applicable, a list of alternate names,
acronyms, or other identifiers by which the applicant is or has been known by,
or uses, or has used, to conduct business or perform work;
(d) Whether the
application is initial or renewal;
(e) Whether the applicant has been issued an
asbestos-related license or certification for asbestos abatement work within
the previous 5 years by any other state or federal agency;
(f) If applicable, a copy of each
asbestos-related license or certification issued, unless previously submitted;
(g) Whether any state or federal agency has taken
any of the following with regard to environmental,
health, or safety requirements against the applicant within the previous 10 years;
(1) Enforcement action; or
(2) Action related to a license, certification, or application for a license or
certification, such as suspension, revocation, or denial, against the applicant
or its responsible persons; and
(h) If applicable, a copy of each state or
federal enforcement action or action related to a license, certification, or
application for a license or certification, such as suspension, revocation, or
denial, and explanation of the status of such
actions, unless previously submitted.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1815.05 Optional
Information for Applications.
(a) Any applicant for an asbestos abatement
entity license under this part that has business liability insurance or is
bonded, or both, for work done under the license may submit proof of such
insurance or bond, or both, with the application.
(b) If proof of insurance or bond, or both, is
submitted with the application and the application is approved, the department
shall note that the licensee has represented that work done under the license
is covered by insurance or a bond, or both, as applicable.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1815.06
Signature and Certification Required for Applications.
(a) Pursuant to (b) below the applications shall be signed and dated by:
(1) The applicant;
or
(2) A responsible person who fulfills the
licensing requirement specified in Env-A 1816.01(c)(11).
(b)
The signature of the applicant, or responsible person,
shall constitute certification that:
(1) The applicant or responsible person has read,
and understands, the New Hampshire asbestos
management and control rules, Env-A 1800;
(2) The application has been prepared in
conformity with Env-A 1800; and
(3) All information contained in the
application, including any supplements attached, is true, complete, and not
misleading to the best of the knowledge and belief of the signer.
(c)
For an asbestos abatement entity application, each responsible person who
fulfills the licensing requirement specified in Env-A 1816.01(c)(11), shall
sign the application to acknowledge that the responsible person is aware that
the application is being filed and that they are being listed as the
responsible person involved with decisions regarding the license and related
matters.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.07 Requests
for Replacement License or Certification.
(a) The department shall provide a replacement
license or certification for a license or certification that has been lost,
destroyed, or stolen, provided the license or certification holder submits a
request to the department by mail, hand delivery, or electronic means, on the
“Request for Replacement License or Certification” form NHDES-A-01-027 dated
January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-027 or via the
department’s website at www.des.nh.gov,
that is:
(1) Signed by the license or certification holder
certifying that all information contained in the request is true, complete, and
not misleading to the best of the knowledge and belief of the signer; and
(2) Accompanied by the appropriate application
fee as set forth in Env-A 1815.09(b)(8).
(b) The license or certification holder shall
include the following on or attached to the form required by (a), above:
(1) The type of license or certification to be replaced;
(2) The license or certification holder’s first
name, middle initial, and last name;
(3) The license or certification holder’s date of
birth;
(4) Number of the license
or certification to be replaced;
(5) Mailing address to which the replacement
license or certification will be mailed;
(6) The reason for the requested replacement,
such as lost, destroyed, stolen, or other, with an explanation; and
(7) The license or certification holder’s
signature, printed name, and date.
(c) If the license or certification holder finds
a license or certification that has been replaced pursuant to (a), above, the
license or certificate holder shall return the original license or
certification to the department.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1815.08 Renewal
Application Requirements and Issuance Criteria.
(a) A license or certification holder shall
submit to the department by mail, hand delivery, or electronic means, the
following on or as an attachment to a form specified
in Env-A 1816.01 through Env-A
1816.06, as applicable and include:
(1) All
of the information required by Env-A 1815.03(a) and Env-A
1816.01 through Env-A 1816.06, as applicable to the
license or certification for which application is being made;
(2)
Documentation that annual refresher courses as required by Env-A 1815.13 are current at the time renewal is sought; and
(3) The
appropriate application fee as set forth in Env-A 1815.09.
(b) The department shall review and process the
application in accordance with RSA 541-A:29, Env-A 200, and Env-C 200, as
applicable.
(c)
Within 30 days of receipt of the application, the department shall
notify the applicant of any errors or omissions and request any additional
documentation from the applicant needed to complete an application submitted
pursuant to (a), above.
(d) If the department obtains credible
information indicating that a reason, as specified in Env-A 1815.10(g), exists
to suspend or revoke a license or certification, while an application for a
license or certification is pending, the department shall notify the applicant
of the information and offer an opportunity for the applicant to respond to the
information prior to a decision being made on the application.
(e) An applicant shall respond within 15 working
days to the department’s notification in (c) or (d), above.
(f) The department shall approve an application
for a license or certification for any of the individual disciplines described
in Env-A 1816.01 through Env-A
1816.06, provided the applicant meets the requirements specified in (a), above.
(g) The department shall deny an application if:
(1) The
application does not include the information required by (a), above;
(2) The
applicant does not respond to the department’s request pursuant to (c) or (d),
above; or
(3) The
department determines that:
a. A reason exists to suspend or revoke a license or certification as
specified in Env-A 1815.10(g); and
b. Either:
1. The applicant acted with intent to deceive;
or
2. The
deficiency(ies) cannot be corrected so as to conform to applicable requirements.
(h) The department shall notify the applicant of
its decision in writing. If the
application is denied, the notice shall specify the reason(s) for the denial
and that the applicant has an opportunity to appeal as specified in (i), below.
(i) If the applicant
wishes to appeal the decision, the applicant shall file such appeal following
the procedures set forth in Env-A 1815.11.
(j) Any person holding a license or certification
that expired more than 3 years prior to the date an application is filed shall
submit an initial application pursuant to Env-A
1815.03 in lieu of an application, pursuant to this section.
(k) An applicant may apply for a combination
certification only if the application is for the same certifications the
applicant originally received. An
applicant requesting any changes in the certifications shall submit initial
applications pursuant to Env-A 1815.03 in lieu of an
application pursuant to this section.
(l) The license or certification holder shall submit an application as specified in (a), above, to the
department, no more than 90 days prior to the expiration date of the current
license or certification.
(m) The department shall not accept an
application pursuant to this section received more than 90 days prior to the
expiration date of the current license or certification.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.09 Application
Fees.
(a) A non-refundable application fee shall
accompany each license or certification application.
(b) The non-refundable application fees for each
category of license and certification shall be as follows:
(1) For
an asbestos abatement entity:
a. An initial fee for each application as
follows:
1. For
applications submitted in calendar year 2026, $1,400; and
2. For
applications submitted in calendar year 2027 and subsequent years, $2,000;
b. A
renewal fee for each application as follows:
1. For
applications submitted in calendar year 2026, $1,100; and
2. For
applications submitted in calendar year 2027 and subsequent years, $1,500;
(2) For an asbestos abatement site supervisor, a fee
for each application as follows:
a. For
applications submitted in calendar year 2026, $300; and
b. For
applications submitted in calendar year 2027 and subsequent years, $400;
(3) For
an asbestos abatement worker, a fee for each application as
follows:
a. For
applications submitted in calendar year 2026, $75; and
b. For
applications submitted in calendar year 2027 and subsequent years, $100;
(4) For
an asbestos inspector, a fee for each application as
follows:
a. For
applications submitted in calendar year 2026, $300; and
b. For
applications submitted in calendar year 2027 and subsequent years, $400;
(5) For
an asbestos management planner, a fee for each application as
follows:
a. For
applications submitted in calendar year 2026, $300; and
b. For
applications submitted in calendar year 2027 and subsequent years, $400;
(6) For
an asbestos abatement project designer, a fee for each application as follows:
a. For
applications submitted in calendar year 2026, $300; and
b. For
applications submitted in calendar year 2027 and subsequent years, $400;
(7) For
an application for a combination certification, as specified in Env-A
1815.03(b), a fee as follows:
a. For
applications submitted in calendar year 2026, $300 for the first application
and $75 for each additional application submitted at the same time; and
b. For
applications submitted in in calendar year 2027 and subsequent years, $400 for
the first application and $100 for each additional application submitted at the
same time; and
(8) For
replacement of a license or certification, no fee for the first replacement and
a fee of $20 for each subsequent replacement.
(c) The fees specified in (b) above,
shall apply based on the date of submittal of the application.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1815.10 License
and Certification Suspension and Revocation.
(a) If the department
obtains credible information indicating that one or more reasons to suspend or
revoke an asbestos abatement license or certification as specified in (g),
below, exists, the department shall notify the holder of the license or
certification in writing of:
(1) The
department’s intended action;
(2) The
reason(s) for the intended action;
(3) For
a suspension, the items specified in (e), below: and
(4) The
date by which the holder of the license or certification shall file a written
request for an adjudicative hearing if the holder wishes to contest the
proposed action, which date shall be 15 working days from the date of the
department’s notice.
(b)
If the department receives a written request
for an adjudicative hearing in accordance with (a)(4), above, the department
shall proceed in accordance with RSA 541-A:31 and Env-C 200 as applicable to
adjudicative proceedings.
(c) If the department does not receive a written
request for an adjudicative hearing in accordance with (a)(4), above, the
license or certification shall be deemed suspended or revoked, as specified in
the notice issued pursuant to (a), above, as of the 16th working day
from the date of the department’s notice.
(d) The department shall suspend a license or
certification if the department determines that one or more reason(s),
as specified in (g), below, to suspend or revoke a license or certification
exists but that:
(1) The
license or certification holder did not act with intent to deceive; and
(2) The
deficiency(ies) can be corrected so
as to conform to applicable requirements.
(e) If the department suspends a license or
certification, the department shall:
(1)
Notify the license or certification holder in writing of the specific
deficiency(ies);
(2)
Specify a reasonable time to correct the deficiency(ies),
which shall be determined based on the number and nature of the deficiency(ies); and
(3)
Inform the license or certification holder in the written notice that if
the deficiencies are not corrected within the specified time, the license or
certification shall be revoked.
(f) The department shall revoke a license or
certification if the department determines that one or more reason(s),
as specified in (g), below, to suspend or revoke a license or certification
exists and that:
(1) The
license or certification holder acted with intent to deceive; or
(2) The
deficiency(ies) cannot be corrected so as to conform to applicable requirements.
(g) The department shall suspend or revoke a
license or certification if:
(1) The license holder or certification holder
has a performance history including violations of any state or federal
environmental, health, and safety requirements, as follows:
a. That relates to the type of work for which a
license or certification is sought under this chapter; and
b. That causes the department to conclude that
the license or certificate holder will not be able to comply with these rules
or poses a threat to workers or the public;
(2) The license holder or certification holder
has submitted materially false or fraudulent information on an application;
(3) The license holder or
certification holder has failed to submit any required information or
documentation with the application;
(4) The license holder or certification holder
has demonstrated an inability to comply with any applicable federal or state
requirement for asbestos abatement;
(5) The license or certification holder performs
work requiring licensure or certification during asbestos abatement without
having applied for and been issued the appropriate license or certification;
(6) The license or certification holder performs
work pursuant to Env-A 1808 or Env-A
1810 requiring licensure or certification without being in physical possession
of an initial and current license or certification;
(7) The license or certification holder allows
for the duplication or use of the license or certification by another entity or
person;
(8) The certification holder obtains training
from a training provider that does not have approval to offer training for the
applicable discipline from either the EPA or a state;
(9) The license or certification holder meets any
of the criteria specified in Env-C 209.02 or Env-C 209.03;
(10) A license holder allows work to be performed
pursuant to Env-A 1808 or Env-A
1810, by an employee or individual not having a current training certificate or
not being in physical possession of a current training certificate;
(11) A certification holder performs work pursuant
to Env-A 1808 or Env-A 1810
without having a current training certificate or without being in physical
possession of a current training certificate; or
(12) A license holder fails to comply with Env-A
1816.01(a)(2) or any of the requirements of Env-A 1816.01(c).
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.11 Appeal. An applicant,
license holder, or certification holder aggrieved by a department decision made
pursuant to Env-A 1815.03, to deny an initial application, Env-A 1815.08, to
deny a renewal application, or Env-A 1815.10 to revoke a license or
certification, who wishes to appeal the decision shall appeal to the air
resources council, within 30 days of the department’s decision, in accordance
with RSA 21-O:14 and the rules adopted by that council, Ec-Air
200.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.12 Expiration. Each license and certification issued under
this chapter shall expire one year from the date of issuance, unless the
license or certification is revoked prior to that date.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.13 Training Requirements
(a) Except as provided in Env-A
1815.14, the following individuals shall complete an initial accredited or
approved training course for the applicable discipline prior to applying for
certification:
(1) Individuals who have not previously completed
an initial training course;
(2) Individuals holding a
certification that has been suspended or revoked pursuant to this part, unless
the suspension or revocation is overturned on appeal;
(3) Individuals trying to obtain
a training certificate who have failed to obtain a score of 70 percent or
greater on the required written examination, three consecutive times; and
(4) Individuals whose training certificate has
been expired for more than 12 months.
(b) Individuals with a training certificate that
has been expired for 12 months or less before the date
an application is submitted pursuant to Env-A 1815.08,
shall complete the annual refresher accredited or approved training course
requirements for the applicable discipline prior to applying for certification.
(c) All initial and refresher training courses
shall meet the requirements for the applicable discipline as set forth in the
MAP.
(d) Each employee or individual
to whom a certification has been issued pursuant to this part shall maintain a
current training certificate while the certification is in effect.
(e) Each employee or individual
performing work pursuant to Env-A 1808 or Env-A 1810, in New Hampshire,
except as exempted under Env-A 1815.02, shall provide on-site, at a conspicuous
location where site conditions do not require personal protective equipment be
worn by those present, the certification issued by the department and the
initial and current training certificates issued to that individual.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1815.14 Reciprocity.
(a) In accordance with RSA 141-E:11, asbestos
abatement supervisors, asbestos abatement workers, asbestos inspectors,
asbestos management planners, and asbestos abatement project designers who have
been granted certification by other states, or the EPA, shall be granted
reciprocity as to the required training requirements specified in Env-A 1815.13
by the state of New Hampshire, provided the
training requirements of said state(s) are effectively equivalent to the
provisions of this part and Env-A 1816 for the individual discipline
certification for which application is being made.
(b) The applicant for reciprocity shall:
(1) Apply in accordance with Env-A
1815.03 or Env-A 1815.08, as applicable; and
(2) Fulfill all requirements in Env-A 1816.01 through Env-A 1816.06, as
specified for the individual discipline certification for which application is
being made.
(c) The department shall review
and process the application in accordance with RSA 541-A:29, Env-A 200, and
Env-C 200.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1816 SPECIFIC
LICENSING AND CERTIFICATION REQUIREMENTS FOR INDIVIDUAL DISCIPLINES
Env-A 1816.01 Asbestos
Abatement Entity Licensing Requirements.
(a) An asbestos abatement entity shall not engage
in any asbestos abatement in New Hampshire without first:
(1)
Being licensed to do so under the provisions of this chapter, unless it
is exempt as specified in Env-A 1815.02; and
(2)
Being registered and in good standing to do business as required by the
New Hampshire secretary of state.
(b) In addition to the items required to be
submitted by Env-A 1815.03(a) or Env-A 1815.08(a), as applicable, the applicant
for an initial or renewal asbestos abatement entity license shall complete and
submit to the department by mail, hand delivery, or electronic means the
following, on or with the “Asbestos Abatement Entity License”, form
NHDES-A-01-014 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-014 or via the
department’s website at www.des.nh.gov:
(1)
Physical address of the applicant;
(2)
Whether the applicant is an individual, sole proprietorship,
corporation, partnership, unincorporated association, or other type with a description;
(3)
Unless listed pursuant to (5) below, a list of the names, titles, and
mailing addresses of the responsible person(s) of the applicant, and all
individuals in management of the entity having primary responsibility for, and
control over, the asbestos abatement work of the applicant;
(4) A
list of all New Hampshire-certified asbestos abatement supervisors employed by
the applicant at the time of application, including the supervisor’s name,
certification number, and certification expiration date;
(5) For
each responsible person who fulfills the licensing
requirement specified in Env-A 1816.01(c)(11), the following information or
documentation for that person:
a. Name;
b. Title;
c. Mailing address;
d. Telephone number;
e. Principal duties; and
f. A
copy of a current asbestos supervisor training certificate;
(6) The
name, title, mailing address, telephone number, telephone type, and email
address of the person designated to be the principal contact for the applicant;
and
(7) A certificate of good standing issued by the
New Hampshire secretary of state.
(c) Each asbestos abatement entity to which the
department issues a license shall:
(1)
Have a current copy of this chapter available at all active asbestos
abatement worksites;
(2)
Retain, in paper or electronic format, for 30 years all business and
personnel records for each asbestos abatement which has been performed by the
entity in New Hampshire;
(3) Notify the department within 30 days of any
change in personnel employed by the entity as New Hampshire-certified asbestos abatement supervisors;
(4) Ensure that an asbestos abatement supervisor who is
certified in accordance with Env-A 1816.02 and whose
training is current is present on-site whenever any asbestos abatement activity
is being carried out in New Hampshire;
(5)
Require all employees and contract workers engaged in asbestos abatement
activities in New Hampshire to be certified in accordance with the provisions
of this chapter and to have a current training certificate;
(6)
Submit documentation of all employee training upon request of the department;
(7)
Notify the department within 30 days of any change in the names or
addresses of any responsible person(s) who work(s) for
the licensed entity and fulfill the requirement
specified in (11), below;
(8)
Maintain an accurate list of the name of each
individual entering and exiting an established
asbestos abatement containment area;
(9)
Maintain a list of asbestos abatement performed in New Hampshire by the
licensed entity, which includes the following:
a. The start and completion
dates of the asbestos abatement;
b. Address of the asbestos abatement;
c. Name
of the owner or operator;
d. Name
of
and telephone number for a contact person for the asbestos abatement; and
e. Name
of each supervisor who worked on the asbestos abatement;
(10)
Maintain good standing with the New Hampshire secretary of state; and
(11)
Have at least one responsible person listed pursuant to (b)(3), above,
who is:
a. Actively involved with
decisions regarding the license and related matters; and
b. Maintains a current
training certificate as an asbestos abatement supervisor.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1816.02 Asbestos
Abatement Supervisor Certification Requirements.
(a) Except as specified in Env-A
1815.02, no individual shall engage in any on-site supervision of asbestos
abatement workers during asbestos abatement in New Hampshire without first
being certified as an asbestos abatement supervisor under the provisions of
this chapter.
(b) The applicant for an initial asbestos
abatement supervisor certification shall meet the following criteria within the
3 years prior to submitting an application:
(1)
Held a valid certification issued by any state, which has not been
suspended or revoked, as an asbestos abatement worker or supervisor, for a
minimum of one year; and
(2)
Have experience performing major asbestos abatement activities in a
containment area for a minimum of 640 hours or 80 days of at least 8 hours per
day.
(c) In addition to the items required to be
submitted by Env-A 1815.03(a) or Env-A 1815.08(a), as applicable, the applicant
for initial or renewal asbestos abatement supervisor certification shall
complete and submit to the department by mail, hand delivery, or electronic
means the following on or with the “Asbestos Abatement Supervisor
Certification”, form NHDES-A-01-010 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-010 or via the
department’s website at www.des.nh.gov:
(1) The
name, mailing address, email address,
telephone type, and telephone number of the applicant’s employer; and
(2) For
an initial application, a list of asbestos abatement performed by the applicant that demonstrates that the applicant possesses the
minimum experience specified in (b)(2), above, and includes the following for
each asbestos abatement:
a. The
date(s) and hours during which the applicant performed major asbestos abatement
activities in the containment area;
b. The
address of the asbestos abatement;
c. The
name of the owner or operator;
d. The
name of and a telephone number for the contact person for the asbestos
abatement; and
e. The
name of the site supervisor(s).
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1816.03 Asbestos
Abatement Worker Certification Requirements.
(a) Except as exempted by Env-A
1815.02, no individual shall perform as an asbestos abatement worker in New
Hampshire without first being certified as an asbestos abatement worker under
the provisions of this chapter.
(b) In addition to the items required to be
submitted by Env-A 1815.03(a) or Env-A 1815.08(a), as applicable, the applicant
for an initial or renewal asbestos abatement worker certification shall:
(1)
Complete and submit to the department by mail, hand delivery, or
electronic means, the information, on “Asbestos Abatement Worker
Certification”, form NHDES-A-01-011 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-011 or via the department’s website at www.des.nh.gov; and
(2)
Include the name, mailing address,
email address, telephone type, and telephone number of the applicant’s
employer.
(c) The applicant may specify on the form that
the company mailing address be used rather than the applicant’s mailing
address, for all application related correspondence from the department.
Source. (See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for Env-A 1800) #14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1816.04 Asbestos
Inspector Certification Requirements.
(a) No individual shall perform any asbestos
inspections, pursuant to Env-A 1804.01, in New
Hampshire without first being certified as an asbestos inspector under the
provisions of this chapter.
(b) The applicant for an initial asbestos
inspector certification shall meet one of the following minimum criteria:
(1)
Have 6 months of experience in one of the following occupations:
a.
Project planning;
b. Management;
c. Engineering;
d. Construction;
e. Architecture;
f.
Industrial hygiene; or
g.
Occupational health;
(2) Have 2 months of field experience under
the supervision of a certified asbestos inspector or management planner; or
(3) Have an associate degree or certification of
completion of a 2-year program as specified in Env-A 1816.05(b)(1).
(c) In addition to the items required to be
submitted by Env-A 1815.03(a) or Env-A 1815.08(a), as applicable, the applicant
for an initial or renewal asbestos inspector certification shall submit to the
department by mail, hand delivery, or electronic means, the following:
(1) A
completed “Asbestos Inspector, Management Planner and/or Project Designer
Certification”, form NHDES-A-01-009 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-009 or via the
department’s website at www.des.nh.gov;
(2)
Whether the application is for certification as an inspector, project
designer, or management planner;
(3) For
an initial application, submit the following:
a. A
list of employment history, including employer’s name, dates of employment,
type of occupation, and job duties demonstrating that the applicant possesses
the minimum experience specified in (b)(1), above;
b. A
list of field work completed, demonstrating that the applicant possesses the
minimum field experience specified in (b)(2), above, including:
1.
Project date(s);
2.
Project owner name;
3.
Project contact name and phone number;
4.
Supervisor name, certification state, and certificate number; and
5.
Description of project and work performed; or
c. A
copy of each degree conferred on the applicant demonstrating that the applicant
possesses the minimum education specified in (b)(3), above; and
(4) The name, mailing address, email address,
telephone type, and telephone number of the applicant’s current employer.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1816.05 Asbestos
Management Planner Requirements.
(a) No individual shall function as an asbestos
management planner for schools in New Hampshire without first being certified
as an asbestos management planner under the provisions of this chapter.
(b) The applicant for an initial asbestos
management planner certification shall meet the following minimum criteria:
(1)
Have an associate degree or certificate of completion of a 2-year
program in:
a.
Project planning;
b. Management;
c. Environmental sciences;
d. Engineering;
e. Construction;
f. Architecture;
g. Industrial hygiene;
h. Occupational health, or
i. A related scientific field; and
(2)
Have 6 months of experience in asbestos abatement, including experience
in asbestos management.
(c) In addition to the items required to be
submitted by Env-A 1815.03(a) or Env-A 1815.08(a), as applicable, the applicant
for an initial or renewal asbestos management planner certification shall
submit to the department by mail, hand delivery, or electronic means, the
following:
(1) A
completed “Asbestos Inspector, Management Planner and/or Project Designer
Certification”, form NHDES-A-01-009 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-009 or via the
department’s website at www.des.nh.gov; and
(2) Whether the application is for certification
as an inspector, project designer, or management planner;
(3) For
an initial application, submit the following:
a. A
copy of each degree conferred on the applicant demonstrating that the applicant
possesses the minimum education specified in (b)(1), above; and
b. A
list of employment history including employer’s name, dates of employment, type
of occupation, and job duties demonstrating that the applicant possesses the
minimum experience specified in (b)(2), above; and
(4) The
name, mailing address, email address,
telephone type, and telephone number of the applicant’s employer.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1816.06 Asbestos
Abatement Project Designer Requirements.
(a) No individual
shall function as an asbestos project designer for schools in New Hampshire
without first being certified as an asbestos abatement project designer under
the provisions of this chapter.
(b) The applicant for an initial asbestos
abatement project designer certification shall meet one of the following
criteria:
(1) At
least 12 months of experience in asbestos abatement and a bachelor's degree in
industrial hygiene, occupational health, environmental science, biological
science, physical science, or a closely related field;
(2) At least 12 months of experience in asbestos
abatement and registration as a registered architect or registered engineer; or
(3) At
least 2 years’ experience in asbestos abatement including experience in
asbestos abatement design.
(c) In addition to the items required to be
submitted by Env-A 1815.03(a) or Env-A 1815.08(a), as applicable, the applicant
for an initial or renewal asbestos abatement project designer certification
shall submit to the department by mail, hand delivery, or electronic means, the
following:
(1) A completed “Asbestos Inspector, Management
Planner and/or Project Designer Application”, form NHDES-A-01-009 dated January
1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-009
or via the department’s website at www.des.nh.gov ;
(2) Whether the application is for certification
as an inspector, project designer, or management planner;
(3) For an initial application, submit the
following documentation
that the applicant possesses one of the criteria specified in (b), above:
a.
Documentation that the applicant possesses the minimum experience and
education, specified in (b)(1) as follows:
1. A
list of asbestos abatement employment history, including employer’s name, dates
of employment, and job duties; and
2. A
copy of each degree conferred on the applicant;
b.
Documentation that the applicant possesses the minimum experience and
professional accreditation specified in (b)(2), above, as follows:
1. A
list of employment history including employer’s name, dates of employment, type
of occupation, and job duties; and
2. A
copy of the applicant’s registration as an architect or engineer; or
c. A
list of asbestos abatement employment history including employer’s name, dates
of employment, and job duties demonstrating that the applicant possesses the
experience specified in (b)(3), above; and
(4) The
name, mailing address, email address,
telephone type, and telephone number of the applicant’s employer.
Source. (See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for Env-A 1800) #14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
PART Env-A 1817 LICENSING
ASBESTOS DISPOSAL SITE CONTRACTORS, EMPLOYERS, AND INDIVIDUALS
Env-A 1817.01 Purpose. The purpose of this part is to implement the
provisions of RSA 141-E:10 that require contractors, employers including
self-employed individuals, and other individuals who disturb asbestos at
asbestos disposal sites (ADS) to be licensed.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.02 Applicability. Except as specified in Env-A
1817.03, any contractor, employer, or individual who disturbs asbestos at an
(ADS) shall hold a valid license issued pursuant to this part.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.03 ADS
License Exemptions. The following
individuals who disturb asbestos at an ADS shall not be required to hold a
license issued pursuant to this part:
(a) Individuals identified in RSA 141-E:10, I(a),
namely, individuals certified pursuant to Env-A 1818
who perform the work for a contractor, employer, or other individual holding a
valid license issued pursuant to this part;
(b) The homeowner of a single-family,
owner-occupied property who, on said property only, personally performs the
work, subject to the following conditions:
(1) The owner shall be trained and certified
pursuant to Env-A 1818; and
(2) The work shall be done in a manner that
prevents the release of asbestos fibers and in accordance with other federal,
state, and local requirements, including the requirements identified in Env-A 1801.01(b);
(c) Entities and individuals undertaking a
small-scale, short-duration disturbance of asbestos at an ADS, subject to the
following conditions:
(1) The entity or individual shall not be under
license suspension or revocation pursuant to these rules;
(2) The quantity of material disturbed shall not
exceed one cubic foot;
(3) The area of disturbance shall not exceed 3
square feet;
(4) The work shall be completed within 2 hours of
being initiated;
(5) The entity or individual shall ensure that
the local health officer is notified before the work commences and that the
local health officer and the department are provided
access to the work site for inspection;
(6) The work shall be done in a
manner that prevents
the release of asbestos fibers and in accordance with other federal, state, and
local requirements, including the requirements identified in Env-A 1801.01(b);
and
(7) The
work shall not be part of a larger project that is being segmented into
small-scale, short-duration tasks; and
(d) Entities and individuals removing non-friable
asbestos only from the ground surface to a container for disposal, subject to
the following conditions:
(1) The
activity shall not involve excavation below the ground surface;
(2) The activity shall not involve contact
with friable asbestos or asbestos that exhibits
friable characteristics; and
(3) The work shall be done in a manner that
prevents the release of asbestos fibers and in accordance with other federal,
state, and local requirements, including the requirements identified in Env-A
1801.01(b).
Source. (See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for Env-A 1800) #14104, eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.04 Application
for ADS License.
(a) Each contractor, employer, and individual
seeking a license to disturb asbestos at an ADS shall submit a completed
application to the department by mail, hand delivery, or electronic means, on a
form specified in Env-A 1817.05, that:
(1) Contains the information specified in Env-A 1817.05;
(2) Is signed and dated as specified in (c)
through (e), below, by the applicant and each responsible person who fulfills the licensing
requirement specified in Env-A 1817.10(b); and
(3) Is
accompanied by a non-refundable application fee as follows:
a. For applications submitted in
calendar year 2026, $350; and
b. For applications submitted in
calendar year 2027 and subsequent years, $500.
(b) The license holder shall submit
an application as specified in (a), above, to the department no more
than 90 days prior to the expiration date of the license.
(c) Pursuant to (d), below, the application shall
be signed and dated by:
(1) The applicant, if an individual; or
(2) A
responsible person who fulfills the licensing requirement specified in Env-A
1817.10(b), as applicable, if the applicant is an employer or contractor.
(d) The signature of the applicant, or
responsible person, shall constitute certification that:
(1) The
applicant or responsible person has read, and understands, the New Hampshire
asbestos management and control rules, Env-A 1800;
(2) The
application has been prepared in conformity with Env-A
1800; and
(3) All
information contained in the application, including any supplements attached,
is true, complete, and not misleading to the best of the knowledge and belief
of the signer.
(e) Each responsible person who
fulfills the licensing requirement specified in Env-A 1817.10(b) shall sign the
application to acknowledge that the responsible person is aware that the
application is being filed and that they are being listed as the responsible person involved with
decisions regarding the license and related matters.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1817.05 Information
Required for ADS License Applications.
The applicant for an ADS license shall complete and submit the “Asbestos
Disposal Site Contractor License”, form NHDES-A-01-015 dated January 1, 2026,
available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-015 or via the
department’s website at www.des.nh.gov, the
following information:
(a) The applicant’s name, mailing address,
physical address, e-mail address, telephone type, and telephone number;
(b) If applicable, a list of alternate names,
acronyms, or other identifiers by which the applicant is, or has been, known by
or uses, or has used to conduct business or perform work;
(c) Whether the application is initial or a renewal;
(d) Whether the applicant is an individual,
corporation, partnership, firm, association, sole proprietorship, political
subdivision, or other kind of association or organization;
(e) If the applicant is an individual, the
applicant’s date of birth;
(f) If the applicant is an employer or
contractor, then for each of its responsible persons not listed pursuant to (h)
below, having primary responsibility for, and control over, the asbestos
abatement work of the applicant, the individual’s:
(1) Name;
(2)
Title; and
(3)
Mailing address;
(g) The name, title, mailing address, email address,
telephone type, and telephone number of the individual affiliated with and
designated by the applicant to be contacted regarding the application;
(h) For each responsible person who fulfills the licensing requirement
specified in Env-A 1817.10(b), the following additional information or
documentation about each such individual:
(1) Name;
(2)
Title and principal duties;
(3)
Telephone number; and
(4)
Current New Hampshire asbestos disposal site worker certification number;
(i) Whether any state or federal agency has taken any of the
following with regard to environmental, health, or
safety requirements against the applicant within the previous 10 years:
(1)
Enforcement action; or
(2)
Action related to license, certification, or application for a license
or certification, such as suspension, revocation, or denial, against the
applicant or its responsible persons;
(j) If applicable, a copy of each of the
following state or federal action(s) against the applicant within the last 10
years unless previously submitted, including its responsible persons, with regard to environmental, health, or safety activities,
and the current status of each such action:
(1)
Enforcement action;
(2)
Action related to a license or certification, such as suspension or
revocation; or
(3)
Action related to an application for a license or certification, such as
denial;
(k) A copy of the list, specified in Env-A
1817.10(f), of all individuals currently employed or otherwise associated with
the applicant who, under the authority of the applicant's license, if issued,
will perform work relating to the disturbance of asbestos at an ADS;
(l) If the applicant is not an individual, a
certificate of good standing from the New Hampshire secretary of state;
(m) Whether the applicant has been issued an
asbestos-related license or certification for asbestos abatement work within
the previous five years by any other state or federal agency;
(n) If applicable, a copy of each
asbestos-related license or certification issued, unless previously submitted;
and
(o) Date and sign the application as specified in
Env-A 1817.04.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1817.06 Optional
Information for ADS License Applications.
(a) Any applicant for licensure under this part
that has business liability insurance or is bonded, or both, for work done
under the license may submit proof of such insurance or bond, or both, with the
application.
(b) If proof of insurance or bond, or both, is
submitted with the application and the application is approved, the department
shall note that the licensee has represented that work done under the license
or certification is covered by insurance or a bond, or both, as applicable.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.07 Review
and Issuance Criteria for ADS License.
(a) The department shall review and process
applications in accordance with RSA 541-A:29, Env-A 200, and Env-C 200.
(b)
Within 30 days of receipt of the application, the department shall
notify the applicant of any errors or omissions and request any additional
documentation from the applicant needed to complete an application submitted
pursuant to Env-A 1817.04.
(c) If the department obtains credible
information indicating that a reason exists to suspend or revoke a license, as
specified in Env-A 1817.08(g), while an application for an ADS license is
pending, the department shall notify the applicant of the information and offer
an opportunity for the applicant to respond to the information prior to a
decision being made on the application.
(d) An applicant shall respond within 15 working
days to the department’s notification in (b) or (c), above.
(e) The department shall approve an application
for an ADS license provided the applicant meets the requirements for licensure
specified in Env-A 1817.04
(f) The department shall deny an application for
an ADS license if the applicant:
(1) Submits incomplete information in the
application, and has not corrected the omission despite being requested by the
department pursuant to (b), above;
(2) Does not submit the items specified in Env-A 1817.04;
(3) Does not meet the obligations of license
holders specified in Env-A 1817.10;
(4) Holds a license or certification that is
currently under suspension where all terms and conditions of the suspension
have not been fully satisfied, or that has been revoked pursuant to this
chapter; or
(5) Does not respond to the department’s request
pursuant to (b) or (c), above.
(g) The department shall notify the applicant of
its decision in writing. If the
application is denied, the notice shall specify the reason(s) for the denial
and that the applicant has an opportunity to appeal as specified in (h), below.
(h) If the applicant wishes to appeal the
decision, the applicant shall file such appeal following the procedures set
forth in Env-A 1817.09.
(i)
If the department approves an application, pursuant to (e) above, the
department shall issue a license as follows:
(1) Is in writing for the type of work the
applicant is qualified to perform;
(2) Is dated and signed by the commissioner or
the commissioner's designee;
(3) Is valid for a period of 12 months from the
date of issuance;
(4) Includes the name and address of the applicant;
(5) Includes such terms and conditions as
necessary to protect public health, safety, and the environment;
(6) Bears a unique identification number; and
(7) Is non-transferable.
(j) Issuance of a license shall not relieve the
license holder, including its responsible persons, of the obligation to comply
with any other federal, state, or local requirements, including any other
obligation for obtaining licenses, permits, training, or other approvals for
the work to be performed.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.08 ADS
License Suspension and Revocation.
(a) If the department obtains credible
information indicating one or more reasons to revoke or suspend an ADS license,
as specified in (g) below, the department shall notify the holder of the
license, in writing, of the following:
(1) The
department’s intended action;
(2) The
reason(s) for the intended action;
(3) For
a suspension, the items specified in (f), below; and
(4) The
date by which the holder of the license shall file a written request for an
adjudicative hearing, which date shall
be 15 working days from the date of the department’s notice, if the holder
wishes to contest the proposed action.
(b) If the department receives a written request
for an adjudicative hearing, in accordance with (a)(4) above, the department
shall proceed in accordance with RSA 541-A:31 and Env-C 200, as applicable to
adjudicative proceedings.
(c) If the department does not receive a written
request for an adjudicative hearing, in accordance with (a)(4) above, the
license or certification shall be suspended or revoked, as specified in the
notice issued pursuant to (a) above, as of the 16th working day from
the date of the department’s notice.
(d) The department shall revoke a license if the
department determines that one or more reasons exist to suspend or revoke the
ADS license, as provided by (g) below, and;
(1) The
underlying problem(s) cannot be corrected or eliminated; or
(2) The
license holder knowingly or intentionally created the underlying problem(s).
(e) The department shall suspend an ADS license
if the department determines that one or more reasons exist to suspend or
revoke the license, as provided by (g) below; and
(1)
Given time to do so, the license holder can correct or eliminate the
underlying problem(s); and
(2) The
license holder did not knowingly or intentionally create the underlying
problem(s).
(f) If the department suspends an ADS license,
the department shall:
(1)
Notify the license holder in writing of the specific deficiency(ies);
(2)
Specify a reasonable time to correct the deficiency(ies),
which shall be determined based on the number and nature of the deficiency(ies); and
(3) Inform the license holder in the written
notice that if the deficiency(ies) are not corrected
within the specified time, the license or certification shall be revoked.
(g) The department shall suspend or revoke an ADS
if the license holder:
(1)
Submitted false or misleading material information in an application;
(2)
Violated the safe work practices prescribed in state and federal
asbestos regulations;
(3)
Failed to comply with an order of abatement issued pursuant to RSA
141-E:14;
(4)
Meets any of the criteria for suspending or revoking an ADS license
application specified in Env-C 209.03;
(5)
Failed to comply with these rules or the terms and conditions of the
license, in accordance with Env-A 1817.10; or
(6) Has
a performance history, including violations by the license holder or its
responsible persons of any state or federal environmental, health, or safety
requirement that relates to the type of work for which licensure is sought,
that causes the department to conclude that the license holder will not be able
to comply with these rules or poses a risk to workers or the public.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.09 Appeal.
An applicant or license holder aggrieved by a department decision made
pursuant to Env-A 1817.07, to deny an application, or Env-A 1817.08, to revoke
a license, who wishes to appeal the decision shall appeal to the air resources
council, within 30 days of the department’s decision, in accordance with RSA
21-O:14 and the rules adopted by the council, Ec-Air
200.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1817.10 Obligations
of ADS License Holders.
(a) License holders shall be registered and in
good standing to do business in New Hampshire, as required by New Hampshire law
and the New Hampshire secretary of state.
(b) License holders shall have at least one
responsible person who is actively involved with decisions regarding the
license and related matters and is certified pursuant to Env-A
1818.
(c) License holders shall not undertake any work
under the authority of the license unless:
(1) The
work is actively supervised at all times by at least
one individual who is certified as an experienced worker pursuant to Env-A 1818 and meets the requirements of a competent person as
specified in 29 CFR 1926.1101 or an on-site supervisor as specified in 29 CFR
1910.120, or both;
(2) The
work is performed by individuals who hold a valid certificate issued pursuant
to Env-A 1819 and are competent to perform the work;
(3) At
the work site, the number of workers who are certified as workers-in-training
pursuant to Env-A 1818 does not exceed 5 times the
number of workers who are certified as experienced workers pursuant to Env-A 1818;
(4) The
license or a certified copy thereof is posted at a conspicuous location at the
work site where site conditions do not require personal protective equipment to
be worn by those present;
(5) The
certificates, or copies thereof, of all workers present at the work site are
available for inspection by the department and the local health officer at a
conspicuous location at the work site where site conditions do not require
personal protective equipment to be worn by those present; and
(6) A
current copy of Env-A 1801, Env-A 1802, Env-A 1817, Env-A 1818, Env-A 1819,
Appendix C, and Appendix D is available for reference by workers at a
conspicuous location at the work site where site conditions do not require
personal protective equipment to be worn by those present.
(d) License holders shall maintain business and
personnel records in conformance with federal requirements, including but not
limited to:
(1) 29 CFR 1926.1101(n);
(2) 29 CFR 1910.1001(m); and
(3) 29 CFR 1910.1020.
(e) License holder(s) shall maintain a list of
ADS projects conducted by the license holder since the date the expiring
license was issued, including for each project the:
a. Site
location;
b. Name of the property owner;
c. Project start date;
d. Project status;
e. Project contact person and telephone number;
and
f. Project site supervisor.
(f) License holders shall maintain a list of all
individuals currently employed or otherwise associated with the applicant who,
under the authority of the applicant’s license, if issued, will perform work
relating to the disturbance of asbestos at an ADS, including the following
information about each individual:
(1) Name;
(2) Position title;
(3)
Mailing address:
(4)
Telephone number;
(5) If
the individual is certified pursuant to Env-A 1818,
the certification number and expiration date;
(6) If
the individual is not certified pursuant to Env-A
1818, the date the application for certification was or will be made, and the
date training, in accordance with Env-A 1819, was or
will be obtained; and
(7)
Whether the individual meets the requirements of a competent person, as
specified in 29 CFR 1926.1101, or an on-site supervisor, as specified in 29 CFR
1910.120, or both.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1818 CERTIFICATION OF ASBESTOS DISPOSAL SITE
WORKERS
Env-A 1818.01 Purpose. The purpose of the rules in this part is to
implement RSA 141-E:11, I, which requires individuals who disturb asbestos at
an ADS to be trained and certified.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1818.02 Applicability. Except as specified in Env-A
1818.03, any individual who disturbs asbestos at an ADS shall hold a valid
certification issued pursuant to this part.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A
1818.03 ADS Certification Exemptions.
(a) An individual shall not be required to hold a
valid certification issued pursuant to this part in order to
undertake a small-scale, short-duration disturbance of asbestos at an ADS,
subject to the following conditions:
(1) The
individual shall not be under license or certification suspension or revocation
pursuant to these rules;
(2) The
quantity of material disturbed shall not exceed one cubic foot;
(3) The
area of disturbance shall not exceed 3 square feet;
(4) The work shall be completed within 2 hours of
being initiated;
(5) The individual performing the work shall
assure that the local health officer is notified before the work commences and
that the local health officer and the department are provided
access to the work site for inspection;
(6) The work shall be done in a manner that prevents the
release of asbestos fibers and in accordance with other federal, state, and
local requirements, including those identified in Env-A 1801.01(b); and
(7) The
work shall not be part of a larger project that is being segmented into
small-scale, short-duration tasks.
(b) An individual shall not be required to hold a
valid certification issued pursuant to this part in order to remove non-friable asbestos only from the ground
surface to a container for disposal, subject to the following conditions:
(1) The
activity shall not involve excavation below the ground surface;
(2) The
activity shall not involve contact with friable asbestos or asbestos that exhibits friable characteristics; and
(3) The work shall be done in a manner that
prevents the release of asbestos fibers and in accordance with other federal,
state, and local requirements, including those identified in Env-A 1801.01(b).
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1818.04 Application
for Initial ADS Certification.
(a) The following individuals seeking initial
certification to disturb asbestos at an ADS shall apply as specified in (b)
below:
(1) An
experienced ADS worker or worker-in-training applying for the first time;
(2) Individuals seeking re-certification to
disturb asbestos at an ADS more than 3 years after their most recent
certification has expired; and
(3) Individuals seeking re-certification to
disturb asbestos at an ADS after their most recent certification has been
revoked.
(b) The individual seeking initial certification
shall complete and submit to the department by mail, hand delivery, or
electronic means an “Asbestos Disposal Site Worker/Worker-in-Training
Certification”, form NHDES-A-01-012 dated January 1, 2026, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-012 or via the
department’s website at www.des.nh.gov.
(c) The applicant shall include the following on
the form specified in (b) above:
(1) The
applicant’s name, mailing address, telephone number, telephone type, email
address, and date of birth;
(2) The
name, address, email address, telephone type, and telephone number of each
entity or individual licensed, or to be licensed pursuant to Env-A 1817, with whom the applicant is currently employed or
otherwise associated for the performance of work
involving the disturbance of asbestos at asbestos disposal sites;
(3)
Whether any state or federal agency is taking or has taken any
enforcement action or action related to a license, certification, or
application for a license or certification, such as suspension, revocation, or denial,
against the applicant or its responsible persons with regard
to environmental, health, or safety requirements within the previous 10 years;
(4) If
applicable, a copy of each state or federal enforcement action or other action
against the applicant, unless previously submitted, and the current status of each such action;
(5) Whether the applicant is seeking
certification as an experienced worker or a worker-in-training, based on the
criteria provided in Env-A 1818.09(b);
(6) One
clear, color photograph, taken within the last 5 years,
of the applicant’s full face, meeting passport photograph requirements
including the name of the applicant;
(7)
Written documentation showing that the applicant meets the certification
requirements specified in Env-A 1818.09, including:
a. For
an initial application, a copy of the record required by Env-A 1819.04(c);
b. A
statement by the applicant attesting that the applicant has met the
requirements of Env-A 1818.09(a);
and
c. For
an application for an initial experienced worker, a work experience record,
signed by the work supervisor(s), documenting a minimum of 40 hours that the
applicant has engaged successfully in the disturbance of asbestos at an ADS
pursuant to the requirements in Env-A 1818.09(c);
(8) If
applicable, a list of alternate names, acronyms, or other identifiers by which
the applicant is, or has been, known by, or uses, or has used, to perform work;
(9)
Whether the applicant has been issued an asbestos-related license or
certification for asbestos abatement work within the previous 5 years by any
other state or federal agency;
(10) If applicable, a copy of each
asbestos-related license or certification issued, unless previously submitted;
and
(11)
Whether the application is initial or a renewal.
(d) The applicant shall date and sign the
application certifying that:
(1) The applicant has read, and understands, the
New Hampshire asbestos management and control rules, Env-A 1800;
(2) The application has been prepared in
conformity with Env-A 1800; and
(3) All information contained in the application,
including any supplements attached, is true, complete, and not misleading to
the best of the knowledge and belief of the signer.
(e) The applicant shall submit a non-refundable
application fee with each application as follows:
(1) For
applications submitted in calendar year 2026, $75; and
(2) For
applications submitted in calendar year 2027 and subsequent years, $100.
(f) The applicant may specify on the form that
the company mailing address be used rather than the applicant’s mailing
address, for all application related correspondence from the department.
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1818.05 Review
and Issuance Criteria for ADS Certification.
(a)
The department shall review and process applications in accordance with
RSA 541-A:29, Env-A 200, and Env-C 200, as applicable.
(b)
Within 30 days of receipt of the application, the department shall
notify the applicant of any errors or omissions and request any additional
documentation from the applicant needed to complete an application submitted
pursuant to Env-A 1818.04.
(c) If the department
obtains credible information indicating that a reason exists to suspend or
revoke a certification, as specified in Env-A 1818.06(g), while an application
for an ADS certification is pending, the department shall notify the applicant
of the information and offer an opportunity for the applicant to respond to the
information prior to a decision being made on the application.
(d) An applicant shall
respond within 15 working days to the department’s notification in (b) or (c),
above.
(e) The department shall approve an application
for an ADS certification if the applicant or certificate holder meets the
requirements for certification specified in Env-A
1818.04 or Env-A 1818.07, as applicable, and Env-A 1818.09.
(f)
The department shall deny an application if:
(1) The applicant submits incomplete
information in the application and does not correct the omission despite being
requested pursuant to (b), above;
(2) The
applicant does not submit any of the information required by Env-A 1818.04 or Env-A 1818.07, as applicable;
(3) The
applicant does not meet the requirements for certification specified in Env-A 1818.09;
(4) The applicant holds a license or
certification that is currently under suspension where all terms and conditions
of the suspension have not been fully satisfied, or that has been revoked and
not overturned on appeal, pursuant to this chapter; or
(5) The
applicant does not respond to the department’s request pursuant to (b) or (c),
above.
(g) The department shall notify
the applicant of its decision in writing.
If the application is denied, the notice shall specify the reason(s) for
the denial and that the applicant has an opportunity to appeal as specified in
(h), below.
(h) If the applicant wishes to appeal the
decision, the applicant shall file such appeal following the procedures set
forth in Env-A 1818.08.
(i)
If the department approves an application pursuant to (e) above, the
department shall issue a certification that:
(1) Is in writing for the type of work the
applicant is qualified to perform, including whether the certification holder
is an experienced worker or a worker-in-training, based on the experience
requirements specified in Env-A 1818.09(c).
(2) Is dated and signed by the commissioner or
the commissioner's designee;
(3) Is valid for a period of 12 months from the
date of issuance;
(4) Includes the name, address and photograph of
the applicant;
(5) Includes such terms and
conditions necessary to protect public health, safety, and the environment;
(6) Bears a unique identification number; and
(7) Is non-transferable.
(j) Issuance of a certification shall not
eliminate any obligation of the certification holder to comply with any other
federal, state, or local requirements for the performance of the work,
including any obligation to obtain additional training and certifications,
licenses, permits, or other approvals.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1818.06 Suspension
and Revocation of ADS Certification.
(a) If the department obtains credible
information indicating that one or more reasons to
suspend or revoke an ADS certification, as specified in (g) below,
exists, the department shall notify the certification holder, in
writing, of the following:
(1) The
department’s intended action;
(2) The
reason(s) for the intended action;
(3) For
a suspension, the items specified in (f), below; and
(4) The
date, 15 working days from the date of the department’s notice, by which the
certification holder shall file a written request for an adjudicative hearing
if the holder wishes to contest the proposed action.
(b) If the department receives a written request
for an adjudicative hearing in accordance with (a)(4), above, the department
shall proceed in accordance with RSA 541-A:31 and Env-C 200, as applicable to
adjudicative proceedings.
(c) If the department does not receive a written
request for an adjudicative hearing in accordance with (a)(4), above, the
certification shall be suspended or revoked, as specified in the notice issued
pursuant to (a), above, as of the 16th working day from the date of
the department’s notice.
(d)
The department shall revoke a certification if the department determines that
one or more reasons exists to suspend or revoke
the certification, as provided by (g), below, and:
(1) The
underlying problem(s) cannot be corrected or eliminated; or
(2) The
underlying problem(s) were created by the certificate holder knowingly or
intentionally.
(e) The department shall suspend a certification
if the department determines that one or more reasons exist to suspend or
revoke the certification, as provided by (g), below, and:
(1)
Given time to do so, the certification holder can correct or eliminate
the underlying problem(s); and
(2) The
underlying problem(s) were not created knowingly or intentionally by the
certification holder.
(f) If the department suspends a certification,
the department shall:
(1)
Notify the certification holder in writing of the specific deficiency(ies);
(2)
Specify a reasonable time to correct the deficiency(ies),
which shall be determined based on the number and nature of the deficiency(ies); and
(3)
Inform the certification holder in the written notice that if the
deficiencies are not corrected within the specific time, the certification
shall be revoked.
(g) The department shall suspend or revoke an ADS
certification if the certification holder:
(1) Submitted false or misleading material
information in an application;
(2)
Cheated on the examination;
(3) Violated the safe work practices prescribed in
state and federal asbestos regulations;
(4)
Failed to comply with an order of abatement issued pursuant to RSA
141-E:14;
(5)
Meets any of the criteria for suspending or revoking a certification
specified in Env-C 209.03;
(6)
Failed to comply with these rules or the terms and conditions of the
certification; or
(7) Has
a performance history, including violations of any state or federal
environmental, health, or safety requirement that relates to the type of work
for which certification is sought, that causes the department to conclude that
the certification holder will not be able to comply with these rules or poses a
threat to workers or the public.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1818.07 ADS
Certification Renewal.
(a) A certification holder whose certification
has not yet expired or has been expired for less than 3 years, shall submit to
the department, on or with the form, as required by Env-A
1818.05, obtained from the department, the following information:
(1) All
application information required in Env-A 1818.04(c);
(2) The
certification number and issue date of the applicant’s expiring or expired certification;
(3) A
list of asbestos disposal site projects that the certification holder has
worked on since the date the expiring or expired certification was issued,
including:
a. The
site location;
b. The
name of the property owner;
c. The name, address, and
telephone number of the license holder for whom the certification holder
performed the work;
d. The name, address, and telephone number of
the project site supervisor;
e. The date the project commenced and the date
the project was completed; and
f. The nature of the work performed;
(4) A statement by the applicant attesting that
the annual refresher training requirements specified in Env-A
1819.05 have been satisfied;
(5) A
non-refundable application fee for each application as follows:
a. For
applications submitted in calendar year 2026, $75; and
b. For
applications submitted in calendar year 2027 and each year thereafter, $100;
and
(6) A
statement by the applicant attesting that all of the
requirements specified in Env-A 1818.09(c) have been met.
(b) The applicant shall sign and date the
application as specified in Env-A 1818.04(d).
(c) The applicant shall submit
an application, as specified in (a) and (b) above, to the department no
more than 90 days prior to the expiration date of the certification.
(d) The department shall review and process
applications in accordance with Env-A 1818.05.
(e) The department shall not approve an
application with an expiring certification that is under suspension until the
applicant fully satisfies all terms and conditions of the suspension, in
accordance with Env-A 1818.06(f).
Source. (See Revision Note #1, Revision Note #2, and
Revision Note #3 at chapter heading for Env-A 1800)
#14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36
Env-A 1818.08 Appeal.
An applicant or certification holder aggrieved by a department decision made
pursuant to Env-A 1818.05, to deny an initial application, Env-A 1818.06, to
deny a renewal application, or Env-A 1818.07, to revoke a certification, who
wishes to appeal the decision, shall appeal to the air resources council,
within 30 days of the department’s decision, in accordance with RSA 21-O:14 and
the rules adopted by that council, Ec-Air 200.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1818.09 Requirements
for ADS Certification.
(a) No individual shall be granted an ADS
certification pursuant to this part, unless the individual has:
(1)
Completed training in accordance with Env-A 1819;
(2) Read or reviewed Env-Sw
2100; and
(3)
Scored 70 percent or better on an examination in accordance with Env-A
1819.03(c).
(b) The department shall certify an individual as
either an experienced worker or a worker-in-training, as specified in (c)
through (e), below.
(c) To qualify as an experienced worker, an
individual shall have successfully performed at least 40 hours of work
involving the disturbance of asbestos at asbestos disposal sites as specified
in (d), below.
(d) The department shall
consider work experience to be as follows:
(1) The
individual shall have performed the work under the supervision of an individual
who is certified as an experienced worker pursuant to these rules and who meets
the requirements of either a competent person as defined in 29 CFR 1926.1101 or
an on-site supervisor as defined in 29 CFR 1910.120, or both; and
(2) One
or a
combination of the following may be substituted for up to 10 hours of the
asbestos disposal site work experience required by (c), above:
a. Ten hours or less of work experience at a
hazardous waste site under the supervision of a competent person as specified
in 29 CFR 1901.120; or
b. Ten hours or less of work experience on
asbestos abatement as an asbestos abatement worker or an asbestos abatement
supervisor under the authority of a licensed asbestos abatement entity as
specified in Env-A 1816.02 or Env-A
1816.03.
(e) Any individual who
has not yet met the experienced worker requirements specified in (c), above,
shall be a worker-in-training.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1818.10
Limitations. Individuals
certified pursuant to this part shall be authorized to disturb asbestos at an
ADS only when the activities are authorized by an entity or individual licensed
pursuant to Env-A 1818, unless the work is
license-exempt work pursuant to Env-A 1818.03.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A
1819 Training requirements for Asbestos
Disposal Site Workers
Env-A 1819.01 Purpose.
(a) The purpose of this part is to establish the scope of
training required to obtain and renew a certification pursuant to Env-A 1818.
(b)
The training described in this part is intended to supplement, and not to
replace or wholly satisfy, federal training requirements for working with
asbestos, including, as applicable:
(1) 29 CFR 1926.1101;
(2) 29 CFR 1910.120; and
(3) 40 CFR 763.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1819.02 Applicability. The rules in this part shall apply to all
individuals seeking certification pursuant to Env-A
1812.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1819.03 Training
Requirements for ADS Workers.
(a) The following individuals shall be trained
pursuant to the basic training program requirements in Env-A
1819.04 prior to applying for certification pursuant to Env-A
1818:
(1)
Individuals not previously certified pursuant to Env-A 1818;
(2)
Individuals holding a certification issued pursuant to Env-A 1818 that has been expired for over 3 years before the
date an application for renewal is submitted pursuant to Env-A 1818;
(3)
Individuals holding a certification that has been suspended or revoked
pursuant to this chapter, and the suspension or revocation has not been
overturned on appeal; and
(4)
Individuals trying to obtain a training certificate who have failed the
post-training examination, as provided in Env-A
1819.06, 3 consecutive times.
(b) The following individuals shall satisfy the
annual refresher training requirements in Env-A
1819.05 prior to applying for certification renewal pursuant to Env-A 1818:
(1)
Individuals holding an expiring certification issued pursuant to Env-A 1818; and
(2)
Individuals holding a certification issued pursuant to Env-A 1818 that has been expired for 3 years or less before the
date an application for renewal is submitted pursuant to Env-A
1818.
(c) After training pursuant to either (a) or (b),
above, is completed, and within 6 months prior to filing an application to
obtain or renew certification, the trainee shall take and pass an examination
as specified by Env-A 1819.06.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1819.04 Basic
ADS Worker Training Program.
(a) An ADS worker shall obtain basic training
from an accredited or approved training provider, in accordance with Env-A 1814.04, or an employer through a program, or combination
of programs, that covers no less than the following topics:
(1)
Asbestos identification, specifically including the identification of
asbestos at asbestos disposal sites located in New Hampshire;
(2)
History, characteristics, and location of asbestos disposal sites in New Hampshire;
(3)
Human health effects due to asbestos exposure, including the
relationship to smoking and contact information for smoking cessation;
(4)
Relevant federal, state, and local regulations, including Env-Sw 2100;
(5)
Personal protective equipment;
(6)
Medical monitoring;
(7) State of the art work
practices for disturbing asbestos at asbestos disposal sites, including:
a. Site characterization;
b. Site control and site security;
c. Neighborhood protection;
d. Air monitoring and asbestos fiber control;
e. Cut and fill techniques;
f. Bulk containment, transportation, and
disposal of asbestos waste;
g. Decontamination procedures for personnel and equipment;
h. Site closure requirements and clearance
determinations pursuant to Env-Sw 2100;
i. Sampling techniques; and
j.
Managing site emergencies; and
(8)
Best management practices for maintaining closed sites and protecting
public health.
(b) The basic training program shall be taught
using a combination of lecture, interactive presentation, and hands-on
activity.
(c)
The person or entity providing basic training pursuant to (a), above, shall
create and provide to the ADS worker a written record showing that the ADS
worker attended and completed basic training, including the date(s) of training
and the name and signature of the person providing the training.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1819.05 Annual
ADS Worker Refresher Training.
(a) Annual refresher training shall be
self-administered by the certification holder.
(b) Annual refresher training shall include the
following:
(1)
Review of written materials and other information obtained during basic training;
(2)
Review of Env-Sw 2100; and
(3) Review of current and relevant federal,
state, and local regulations, including these rules.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1819.06 Post-Training
Examinations for ADS Workers.
(a) The department shall administer examinations
required pursuant to this part.
(b) The department shall schedule examinations on a monthly basis during regular business hours at a time
convenient to both the applicant and the department.
(c) The department shall design examinations to
test the trainee’s understanding of:
(1) The
information covered by the basic training program;
(2)
Env-Sw 2100; and
(3) Current and relevant federal, state, and
local regulations.
(d) The department shall administer the
examination orally to any individual who so requests
an oral examination due to a reading difficulty.
(e) The department shall include 50 questions in
an initial exam and 25 questions for a renewal examination.
(f) The department shall allow each examinee one
hour to complete the exam.
(g) The department shall allow for additional
time to complete the exam if an examinee submits a written request prior to the
exam date specifying the reason for needing additional time to complete the
exam.
(h) A passing score on the examination shall be
70 percent or greater.
(i) To obtain a
passing score, an individual shall be allowed to retake the required
examination up to 3 times before having to re-attend basic training.
(j) Within 15 working days of the exam, the
department shall send the examination score to the examinee in writing.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
PART Env-A 1820 WAIVERS FROM
LICENSE AND CERTIFICATION RULES
Env-A 1820.01 Purpose. The purpose of the rules in this part is to
establish procedures and criteria for granting waivers to accommodate
situations where strict adherence to a particular requirement would not be in
the best interest of the public.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1820.02 Procedures
for Requesting a Waiver of a Rule.
(a) Any person who is or would be directly
affected by the strict application of a rule in Env-A
1811, or Env-A 1815 through Env-A 1819 may request a waiver, as specified below.
(b) Each request for a rule waiver shall:
(1) Be
in writing; and
(2)
Include the information specified in Env-A
1820.03.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1820.03 Content
and Format of Waiver Requests.
(a) The person requesting the rule waiver shall
provide the following information:
(1) The
name, address, and telephone number of the person requesting the waiver;
(2)
Identification of the specific rule(s) from which the applicant is
seeking a waiver;
(3) The
period of time during which the applicant wishes the
waiver to be effective;
(4) A
description of the specific project(s) to which the waiver is intended to apply
or a statement that the requested waiver is intended to apply without regard to
a specific project(s);
(5) A
full explanation of why the waiver is necessary, including an explanation of
the economic and operational consequences of complying with the rule as written;
(6) A
full explanation, with supporting data, of the alternative(s), if any, that the
applicant proposes to use in lieu of complying with the rule;
(7) A
full explanation of how each of the alternatives proposed pursuant to (6)
above, is consistent with the purpose and intent of RSA 141-E and Env-A 1800, and is otherwise adequate to protect public health,
safety, and the environment; and
(8) A
list of all state and federal enforcement actions, both past and pending,
against the applicant, including responsible persons in its employ, with regard to environmental, health, or safety activities,
and the current status of each such enforcement
action.
(b) The applicant shall date and sign the request
for waiver certifying that:
(1) The applicant has read, and understands, the
New Hampshire asbestos management and control rules, Env-A 1800;
(2) The request has been prepared in conformity
with Env-A 1800; and
(3) All information contained in the request is
true, complete, and not misleading to the best of the knowledge and belief of
the signer.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1820.04 Criteria
for Granting a Waiver.
(a) Subject to (b), below, the department shall
grant a request for a rule waiver if:
(1)
Granting the request will not result in an adverse effect to public
health, public safety, the environment, or the natural resources of the state
of New Hampshire; and
(2) One
or more of the following conditions will be satisfied:
a.
Granting the request is consistent with the purpose and intent of the
rule being waived; or
b.
Strict compliance with the rule will provide no benefit to the public
and will cause an operational or economic hardship to
the applicant.
(b) No rule waiver shall be granted if the effect
of the waiver would be to waive or modify:
(1) A
federal or state statutory requirement, unless the statute specifically allows
for a waiver; or
(2) A
federal or state constitutional requirement.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Env-A 1820.05
Decisions.
(a) The department shall notify the person
requesting the waiver of the decision in writing.
(b) A notice of denial shall state clearly the
reason(s) for denial.
(c) A notice of approval shall include the terms
and conditions under which the waiver is granted, including the effective date
and expiration date, which shall be no later than one year from the date it is
granted.
Source.
(See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter
heading for Env-A 1800) #14104,
eff 11-1-24, EXPIRES: 11-1-34
Appendix A: State Statutes and Federal Regulations
Implemented
|
Rule
Number(s) |
State
Statute(s) Implemented |
Federal
Regulations Implemented |
|
Env-A 1801.01 |
RSA 141-E:1 |
|
|
Env-A 1801.02 |
RSA 141-E:3 |
40 CFR 61.140 and 61.145(a) |
|
Env-A 1801.03 – Env-A 1801.04 |
RSA 141-E:4, XVI(c) |
42 U.S.C. 7412 |
|
Env-A 1801.05 |
RSA 141-E:3, II and VI; RSA 141-E :4, II and XVI(a) |
42 U.S.C. 7412; 40 |
|
Env-A 1801.06 |
RSA 141-E:4 |
15
U.S.C. 2643(m); 40 |
|
Env-A 1802.01 - Env-A 1802.04 |
RSA 141-E:4 |
|
|
Env-A 1802.05 |
RSA 141-E:2, I |
|
|
Env-A 1802.06 |
RSA 141-E:2, II |
|
|
Env-A 1802.07 – Env-A 1802.11 |
RSA 141-E:4 |
|
|
Env-A 1802.12 |
RSA 141-E:4 |
40 CFR 763, subpart E, appendix D |
|
Env-A 1802.13 |
RSA 141-E:2, III |
|
|
Env-A 1802.14 – Env-A 1802.20 |
RSA 141-E:4 |
|
|
Env-A 1802.21 |
RSA 141-E:2, IV |
|
|
Env-A 1802.22 – Env-A 1802. 28 |
RSA 141-E:4 |
|
|
Env-A 1802.29 |
RSA 141-E:2, VI |
|
|
Env-A 1802.30 |
RSA 141-E:4 |
40 CFR 763, subpart E, appendix D |
|
Env-A 1802.31 – Env-A
1802.34 |
RSA 141-E:4 |
|
|
Env-A 1802.35 & Env-A
1802.37 |
RSA 141-E:4, I |
|
|
Env-A 1802.38 |
RSA 141-E:4 |
40 CFR 61.141, appendix D |
|
Env-A 1802.39 |
RSA 141-E:4 |
|
|
Env-A 1802.40 |
RSA 141-E:4 |
29 CFR 1926.1001(b), appendix D |
|
Env-A 1802.41 |
RSA 141-E:2, VII |
|
|
Env-A 1802.42 – Env-A
1802.45 |
RSA 141-E:4 |
|
|
Env-A 1802.46 |
RSA 141-E:2, VIII |
|
|
Env-A 1802.47 – Env-A
1802. 49 |
RSA 141-E:4 |
|
|
Env-A 1802.50 |
RSA 141-E:2, IX |
|
|
Env-A 1802.51 – Env-A
1802.56 |
RSA 141-E:4 |
|
|
Env-A 1803.01 – Env-A 1803.08 |
RSA 141-E:1, III; RSA 141-E:3, VIII and IX;
RSA 141-E:4, XVI |
|
|
Env-A 1804.01 |
RSA 141-E:3, X; RSA 141-E:4, XVI |
|
|
Env-A 1804.02 & Env-A 1804.03 |
RSA 141-E:3, VI and X;
RSA 141-E:4, VI |
|
|
Env-A 1804.04 |
RSA 141-E:3, X; RSA 141-E:4, XVI |
|
|
Env-A 1804.05 |
RSA 141-E:4, XIII; RSA 141-E:12, II |
|
|
Env-A 1805.01 – Env-A 1805.03 |
RSA 141-E:3, XI; RSA 141-E:4, XVI |
|
|
Env-A 1806.01 – Env-A 1806.06 |
RSA 141-E:3, XI |
40
CFR 61.145 |
|
Env-A 1806.07 |
RSA 141-E:3, XII; RSA 141-E:4, XVI(d); RSA
141-E:12, II |
|
|
Env-A 1806.08 |
RSA 141-E:3, XI |
40 CFR 61.145 |
|
Env-A 1806.09 |
RSA 141-E:3, X |
|
|
Env-A 1807 |
RSA 141-E:3, VIII;
RSA 141-E:4, II & XVI(a) |
|
|
Env-A 1808 |
RSA 141-E:3, VIII;
RSA 141-E:4, II & XVI(a) |
|
|
Env-A 1809 |
RSA 141-E:3, VIII; RSA 141-E:4, II &
XVI(a) |
|
|
Env-A 1810 |
RSA 141-E:3, VIII;
RSA 141-E:4, II & XVI(a) |
|
|
Env-A 1811.01 |
RSA 141-E:4, II(a)(3) |
42 U.S.C. 7412; 40 |
|
Env-A 1811.02 |
RSA 141-E |
15 U.S.C. 2643(m); 40 |
|
Env-A 1812 |
RSA 141-E:3, IX ; RSA 141-E :4, XVII |
40 CFR 61.145 and 61.150 |
|
Env-A 1813 |
RSA
141-E:8 & 13 |
|
|
Env-A 1814 |
RSA 141-E:4, II & VIII |
40 CFR 763, subpart E, Appendix C |
|
Env-A 1815.01 – Env-A 1815.08 |
RSA 141-E:3, II; RSA 141-E:4, II, VII & VIII; RSA 141-E:10-11 |
|
|
Env-A 1815.09 |
RSA 141-E:3, III; RSA 141-E:4, II, IX &
XI; RSA 141-E:12, I |
|
|
Env-A 1815.10 |
RSA 141-E:4, II&VIII, RSA 141-E:10-11 |
|
|
Env-A 1816 |
RSA
141-E:3, II; RSA 141-E:4, II, VII & VIII; RSA 141-E:10-11 |
|
|
Env-A 1817 |
RSA 141-E:3, I and XXI; RSA 141-E:4, XV; RSA 141-E:10 |
|
|
Env-A 1817.04 & Env-A 1817.05 |
RSA 141-E:3, I, III and XXI;
RSA 141-E:4, XV; RSA 141-E:10 |
|
|
Env-A 1817.10(c)(1) |
RSA 141-E:4, XV; RSA 141-E:10 |
29 CFR 1910.120, 29 CFR 1926.1101 |
|
Env-A 1817.10(d) |
RSA 141-E:4, XV; RSA 141-E:10 |
29 CFR 1910.1001 & 1910.1020; 29 CFR 1910.1101 |
|
Env-A 1818 |
RSA 141-E:3:II and XXI; RSA 141-E:4, XV; RSA 141-E:11 |
|
|
Env-A 1818.04 & Env-A 1818.07 |
RSA 141-E:3:II, III and XXI;
RSA 141-E:4, XV; RSA 141-E:11 |
|
|
Env-A 1818.08(d) |
RSA 141-E:4, XV; RSA 141-E:11 |
29 CFR 1910.120, 29 CFR 1926.1101 |
|
Env-A 1819 |
RSA 141-E:3, III; RSA 141-E:4, XV |
|
|
Env-A 1819.01(b) |
RSA 141-E:4, XV; RSA 141-E:11 |
29 CFR 1910.1001 & 1910.1020; 29 CFR 1910.1101 |
|
Env-A 1820 |
RSA 141-E:4, XII; RSA 541-A:22, IV |
|
Appendix B:
Information on Documents Incorporated by Reference
|
Rule (Env-A) |
Title, Date |
Obtain from: |
|
1808.06(g)(1) 1809.01(b)(1) 1813.03(b) |
Asbestos and Other Fibers
by PCM: Method 7400, Issue 3, Fifth Edition, June 14, 2019 |
National Institute of Occupational Safety and Health (NIOSH) Manual of Analytical Methods (NMAM) The material can be downloaded at no charge from: https://www.cdc.gov/niosh/nmam/pdf/7400.pdf |
Appendix
C: Statutory Definitions
125-C:2:
X. "Person," any individual,
partnership, firm or co-partnership, association, company, trust, corporation,
department, bureau, agency, private or municipal corporation, or any political
subdivision of the state, the United States or political subdivisions or
agencies thereof, or any other entity recognized by law as subject to rights
and duties.
141-E:2:
I. “Asbestos” means amosite, chrysotile,
crocidolite, or asbestiform tremolite, actinolite, or anthophyllite.
II. “Asbestos abatement” means any of the
following activities:
(a) The wrecking or removal of any
load-supporting structural member containing or covered by RACM, as defined in
paragraph VII;
(b) The encapsulation, coating,
binding, or resurfacing of structural members, walls, ceilings,
or other building surfaces, or ducts, pipes, boilers, tanks, reactors,
furnaces, or other vessels containing RACM for the purpose of minimizing the
potential for fiber release;
(c) The construction of airtight
enclosures by the use of impact resistant materials to
isolate surfaces coated or containing RACM;
(d) The removal or stripping of RACM
from structural members, walls, ceilings, or other building surfaces, or ducts,
pipes, boilers, tanks, reactors, furnaces, or other vessels; and
(e) The repair of RACM to minimize the
likelihood of fiber release from damaged areas. Repair may include, but shall
not be limited to, application of duct tape, rewettable
glass cloth, canvas, cement, or other suitable materials to seal exposed areas
where asbestos fibers may be released, or repair of damaged, previously
encapsulated, RACM with non-asbestos substitutes; and re-encapsulation or
repair of enclosures around RACM.
III. “Asbestos disposal site” means land
where asbestos waste exists, either in or on the ground, due to dumping
activities which ceased by July 10, 1981. The term includes inactive disposal
sites as defined by 40 CFR 61.141. The term does not include any disposal site
which is subject to the permitting requirements of RSA 149-M.
IV. “Contractor” means any partnership,
firm, association, corporation, or sole proprietorship which engages in
asbestos abatement activities and/or activities involving the disturbance of
asbestos at asbestos disposal sites.
VI. “Friable asbestos material” means any
material that contains more than one percent of asbestos by weight, area, or
volume and that can be crumbled, pulverized, or reduced to powder when dry by
hand pressure.
VII. “Regulated asbestos-containing
material” or “RACM” means:
(a) Friable asbestos-containing material;
(b) Category I non-friable
asbestos-containing material, as defined by 40 CFR 61.141, that has become friable;
(c) Category I non-friable
asbestos-containing material, as defined by 40 CFR 61.141, that will be or has
been subjected to sanding, grinding, sawing, or abrading; or
(d) Category II non-friable
asbestos-containing material, as defined by 40 CFR 61.141, that will likely
become or has become crumbled, pulverized, or reduced to powder by the forces
expected to act on the material in the course of
demolition or renovation operations.
VIII. “School asbestos abatement planning”
means any of the following activities:
(a) The inspection of school buildings
for asbestos-containing materials;
(b) The preparation of plans for
asbestos abatement in schools, pursuant to P.L. 99-519; or
(c) The design of asbestos abatement
projects for school buildings.
IX. “Structural member” means any beam,
ceiling, floor, or wall.
Appendix
D: Federal Definitions
40 CFR 61.141:
All terms that are used in this subpart and are not defined below are
given the same meaning as in the Act and in subpart A of this part.
Active waste disposal site
means any disposal site other than an inactive site.
Adequately wet means
sufficiently mix or penetrate with liquid to prevent
the release of particulates. If visible emissions are observed coming from
asbestos-containing material, then that material has not been adequately wetted. However, the absence of visible emissions is not
sufficient evidence of being adequately wet.
Asbestos-containing waste
materials means mill tailings or any waste that contains commercial
asbestos and is generated by a source subject to the provisions of this
subpart. This term includes filters from control devices, friable asbestos
waste material, and bags or other similar packaging contaminated with
commercial asbestos. As applied to demolition and renovation operations, this
term also includes regulated asbestos-containing material waste and materials
contaminated with asbestos including disposable equipment and clothing.
Asbestos mill means any
facility engaged in converting, or in any intermediate step in converting,
asbestos ore into commercial asbestos. Outside storage of asbestos material is
not considered a part of the asbestos mill.
Asbestos tailings means any solid waste that contains asbestos and is a
product of asbestos mining or milling operations.
Asbestos waste from control
devices means any waste material that contains asbestos and is collected by
a pollution control device.
Category I nonfriable
asbestos-containing material (ACM) means asbestos-containing packings,
gaskets, resilient floor covering, and asphalt roofing products containing more
than 1 percent asbestos as determined using the method specified in appendix E,
subpart E, 40 CFR part 763, section 1, Polarized Light Microscopy.
Category II nonfriable ACM
means any material, excluding Category I nonfriable ACM, containing more than 1
percent asbestos as determined using the methods specified in appendix E,
subpart E, 40 CFR part 763, section 1, Polarized Light Microscopy that, when
dry, cannot be crumbled, pulverized, or reduced to powder by hand pressure.
Commercial
asbestos means any material containing asbestos that is extracted from ore
and has value because of its asbestos content.
Cutting means to penetrate
with a sharp-edged instrument and includes sawing, but does not include
shearing, slicing, or punching.
Demolition means the wrecking
or taking out of any load-supporting structural member of a facility together
with any related handling operations or the intentional burning of any
facility.
Emergency renovation operation means a renovation
operation that was not planned but results from a sudden, unexpected event
that, if not immediately attended to, presents a safety or public health
hazard, is necessary to protect equipment from damage, or is necessary to avoid
imposing an unreasonable financial burden. This term includes operations
necessitated by nonroutine failures of equipment.
Fabricating means any
processing (e.g., cutting, sawing, drilling) of a manufactured product that
contains commercial asbestos, with the exception of
processing at temporary sites (field fabricating) for the construction or
restoration of facilities. In the case of friction products, fabricating
includes bonding, debonding, grinding, sawing, drilling, or other similar
operations performed as part of fabricating.
Facility component
means any part of a facility including equipment.
Friable asbestos material
means any material containing more than 1 percent asbestos as determined using
the method specified in appendix E, subpart E, 40 CFR part 763, section 1,
Polarized Light Microscopy, that, when dry, can be crumbled, pulverized, or
reduced to powder by hand pressure. If the asbestos content is less than 10
percent as determined by a method other than point counting by polarized light
microscopy (PLM), verify the asbestos content by point counting using PLM.
Fugitive source means any
source of emissions not controlled by an air pollution control device.
Glove bag
means a sealed compartment with attached inner gloves used for the handling of
asbestos-containing materials. Properly installed and used, glove bags provide
a small work area enclosure typically used for small-scale asbestos stripping
operations. Information on glove-bag installation, equipment and supplies, and
work practices is contained in the Occupational Safety and Health
Administration's (OSHA's) final rule on occupational exposure to asbestos
(appendix G to 29 CFR 1926.58).
Grinding means to reduce to powder or small fragments and includes
mechanical chipping or drilling.
In poor condition means the
binding of the material is losing its integrity as indicated by peeling,
cracking, or crumbling of the material.
Inactive waste disposal site
means any disposal site or portion of it where additional asbestos-containing
waste material has not been deposited within the past year.
Installation means any
building or structure or any group of buildings or structures at a single
demolition or renovation site that are under the control of the same owner or
operator (or owner or operator under common control).
Leak-tight means that solids
or liquids cannot escape or spill out. It also means dust-tight.
Malfunction means any sudden
and unavoidable failure of air pollution control equipment or process equipment
or of a process to operate in a normal or usual manner so that emissions of
asbestos are increased. Failures of equipment shall not be considered
malfunctions if they are caused in any way by poor maintenance, careless
operation, or any other preventable upset conditions, equipment breakdown, or
process failure.
Manufacturing means the
combining of commercial asbestos—or, in the case of woven friction products,
the combining of textiles containing commercial asbestos—with any other
material(s), including commercial asbestos, and the processing of this
combination into a product. Chlorine production is considered a part of
manufacturing.
Natural barrier means a
natural object that effectively precludes or deters access. Natural barriers
include physical obstacles such as cliffs, lakes or other large bodies of
water, deep and wide ravines, and mountains. Remoteness by itself is not a
natural barrier.
Nonfriable
asbestos-containing material means any material containing more than 1
percent asbestos as determined using the method specified in appendix E,
subpart E, 40 CFR part 763, section 1, Polarized Light Microscopy, that, when
dry, cannot be crumbled, pulverized, or reduced to powder by hand pressure.
Nonscheduled renovation operation
means a renovation operation necessitated by the routine failure of equipment,
which is expected to occur within a given period based on past operating
experience, but for which an exact date cannot be predicted.
Outside air means the air
outside buildings and structures, including, but not limited to, the air under
a bridge or in an open air ferry dock.
Owner or operator of a demolition
or renovation activity means any person who owns, leases, operates,
controls, or supervises the facility being demolished or renovated or any
person who owns, leases, operates, controls, or supervises the demolition or
renovation operation, or both.
Particulate asbestos material
means finely divided particles of asbestos or material containing asbestos.
Planned renovation operations
means a renovation operation, or a number of such
operations, in which some RACM will be removed or stripped within a given period of time and that can be predicted. Individual
nonscheduled operations are included if a number of
such operations can be predicted to occur during a given period
of time based on operating experience.
Renovation means altering a
facility or one or more facility components in any way, including the stripping
or removal of RACM from a facility component. Operations in which
load-supporting structural members are wrecked or taken out are demolitions.
Resilient floor covering means
asbestos-containing floor tile, including asphalt and vinyl floor tile, and
sheet vinyl floor covering containing more than 1 percent asbestos as
determined using polarized light microscopy according to the method specified
in appendix E, subpart E, 40 CFR part 763, section 1, Polarized Light
Microscopy.
Roadways means surfaces on
which vehicles travel. This term includes public and private highways, roads,
streets, parking areas, and driveways.
Strip means to take off RACM
from any part of a facility or facility components.
Structural member means any
load-supporting member of a facility, such as beams and load supporting walls;
or any nonload-supporting member, such as ceilings
and nonload-supporting walls.
Visible emissions means any emissions, which are visually detectable without
the aid of instruments, coming from RACM or asbestos-containing waste material,
or from any asbestos milling, manufacturing, or fabricating operation. This
does not include condensed, uncombined water vapor.
Waste generator means any
owner or operator of a source covered by this subpart whose act or process
produces asbestos-containing waste material.
Waste shipment record means
the shipping document, required to be originated and
signed by the waste generator, used to track and substantiate the disposition
of asbestos-containing waste material.
Working day means Monday
through Friday and includes holidays that fall on any of the days Monday
through Friday.
40 CFR 763, Subpart E, Appendix C:
I. A. 8.
“Small-scale, short-duration activities (SSSD)” are tasks such as, but
not limited to:
a.
Removal of asbestos-containing insulation on pipes.
b.
Removal of small quantities of asbestos-containing insulation on beams
or above ceilings.
c.
Replacement of an asbestos-containing gasket on a valve.
d.
Installation or removal of a small section of drywall.
e.
Installation of electrical
conduits through or proximate to asbestos-containing materials.
SSSD can be further defined by
the following considerations:
f.
Removal of small quantities of ACM only if required in the performance
of another maintenance activity not intended as asbestos abatement.
g. Removal of asbestos-containing thermal system
insulation not to exceed amounts greater than those
which can be contained in a single glove bag.
h.
Minor repairs to damaged thermal system insulation which do not require
removal.
i. Repairs to a piece of asbestos-containing
wallboard.
j.
Repairs, involving encapsulation, enclosure, or removal, to small
amounts of friable ACM only if required in the performance of emergency or
routine maintenance activity and not intended solely as asbestos abatement. Such work may not exceed amounts greater than
those which can be contained in a single prefabricated mini-enclosure. Such an enclosure shall conform spatially and
geometrically to the localized work area, in order to
perform its intended containment function.
40 CFR 763.83
Asbestos-containing building material (ACBM) means surfacing ACM, thermal
system insulation ACM, or miscellaneous
ACM that is found in or on interior structural members or other
parts of a school
building.
High-efficiency particulate
air (HEPA) refers to a filtering system capable of trapping
and retaining at least 99.97 percent of all monodispersed particles 0.3 µm in
diameter or larger.
School building means:
(1) Any structure suitable for use as a
classroom, including a school facility such as a laboratory, library,
school eating facility, or facility used for the preparation of food.
(2) Any
gymnasium or other facility which is specially designed for athletic or
recreational activities for an academic course in physical education.
(3) Any
other facility used for the instruction or housing of students or for the
administration of educational or research programs.
(4) Any maintenance, storage, or utility
facility, including any hallway, essential to the operation of any facility
described in this definition of “school building” under paragraphs (1), (2), or
(3).
(5) Any
portico or covered exterior hallway or walkway.
(6) Any
exterior portion of a mechanical system used to condition interior space.
29 CFR 1910.1001(b)
PACM means “presumed asbestos containing
material.”
29 CFR
1926.1101(b)
Amended water means water to which
surfactant (wetting agent) has been added to increase the ability of the liquid
to penetrate ACM.