CHAPTER En 1800  ADMINISTRATION OF NEW HAMPSHIRE ENERGY CONSERVATION CODE

 

PART En 1801  APPLICABILITY

 

          En 1801.01  Purpose.  En 1800 governs the procedures for submission to the department and the department’s review of the residential energy code compliance form for projects in municipalities that do not have an adopted code enforcement mechanism in accordance with RSA 155-A:10-a.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1801.02  Scope.  En 1800 shall apply to all new residential buildings and additions or alterations to existing residential buildings pursuant to RSA 155-A.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

PART En 1802  DEFINITIONS

 

          En 1802.01  “Applicant” means the owner, or owner’s agent submitting an application to the department for verification of design compliance with the energy code.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1802.02  “Application” means the “New Hampshire Residential Energy Code Application” effective July 3, 2024 pursuant to RSA 155-A:10‑a found at https://mm.nh.gov/files/uploads/fmo/remote-docs/nh-energy-codes-form-iecc-2018.pdf

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1802.03  “State building code review board” (BCRB) means the state building code review board pursuant to RSA 155-A.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1802.04  “Department” means the New Hampshire department of energy.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1802.05  “Energy code” means the “New Hampshire building code” or “state building code” as defined by RSA 155-A:1, IV.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1802.06  “Residential building,” as referenced in RSA 155-A New Hampshire building code, means:

 

          (a)  Any detached one- or 2-family dwelling;

 

          (b)  Any other dwelling as defined and prescribed by the New Hampshire building code.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

PART En 1803  APPLICATION REQUIREMENTS

 

          En 1803.01  Submission of Applications.

 

          (a)  Each applicant shall complete and submit an application.

 

          (b)  Each applicant shall include with each application for review of a residential building for compliance with the energy code, the following:

 

                  (1)  A completed, signed electronic copy of the application available on the BCRB website; and

 

                  (2)  A certification by the applicant, as follows:

 

                          “I hereby certify that all the information contained in this application is true and correct, and construction shall comply in all respects with the New Hampshire Building Code.”

 

          (c)  Applicants may submit applications to the department by electronic mail to energycodes@energy.nh.gov.

 

          (d)  For purposes of RSA 155-A:10-a, any application submitted shall not be deemed complete until all components of the application as required at En 1803.01(b) have been received by the department.  The failure of an applicant to respond to an inquiry by the department within 10 business days of such inquiry shall render the application rejected.

 

          (e)  If an applicant makes a substantive revision to an application, including but not limited to a revision to a design specification, after the application has been submitted to the department, the applicant shall date and initial in ink or electronically the revision made to the application.

 

          (f)  The date of the submitted revision, as described in En 1803.01(e) above, shall constitute a new receipt date for the application.

 

          (g)  An owner of a residential building for which plans and specifications have been approved by an architect or engineer pursuant to RSA 155-A shall submit them to the department as prescribed by the BCRB.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

PART En 1804  METHODS OF COMPLIANCE

 

          En 1804.01  Energy Code Compliance.

 

          (a)  In accordance with RSA 155-A:10-a, applicants who intend to construct new or alter existing residential buildings in municipalities without an adopted code enforcement mechanism, shall submit a completed application to the department on behalf of the BCRB for verification that the proposed applicable project meets the energy code requirements.

 

          (b)  An applicant shall demonstrate that a proposed residential building subject to the requirements of the energy code meets or exceeds the minimum construction standards of the energy code pursuant to RSA 155-A.

 

          (c)  No project shall be considered approved pursuant to En 1800 and RSA 155-A without the issuance of a verification letter by the department.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

          En 1804.02  Department Responsibilities.  The department shall review the application and shall:

 

          (a)  Determine whether the applicant has demonstrated, pursuant to RSA 155-A, that the design of the residential building complies with the energy code; and

 

          (b)  If the department determines compliance with the energy code, the department shall issue a verification letter to the municipality pursuant to RSA 155-A:10-a with a copy to the applicant.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

PART En 1805 REQUEST FOR RECONSIDERATION

 

          En 1805.01  Process after Department Denial of Application.

 

          (a)  When the department denies an application, it shall notify the applicant of its finding and the procedures outlined in En 1805.01.

 

          (b)  Any applicant whose application has been initially denied by the department may request an informal reconsideration conference with the department within 30 days of the date of the department’s notice of denial.

 

          (c)  The department shall hold an informal conference requested pursuant to En 1805.01(b) above.

 

          (d)  Following the informal conference referred to in En 1805.01(c) above, the department shall:

 

                  (1)  Issue a written decision which shall:

 

                          a.  Affirm, reverse, or modify the decision on the application; and

 

                          b.  Summarize the results of the informal conference and the basis for the decision; and

 

                  (2)  Provide a copy of the written decision, referred to in En 1805.01(d)(1) above, to the applicant.

 

          (e)  If, following the informal conference referred to in En 1805.01(c) above, the department determines compliance with the energy code, the department shall issue a verification letter to the municipality pursuant to RSA 155-A:10-a with a copy to the applicant.

 

Source.  #14381, eff 9-22-25, EXPIRES: 9-22-35

 

APPENDIX A

 

Rule

Statute

En 1801.01– En 1805.01

RSA 12-P:5, IV; RSA 155-A:10-a