CHAPTER En 1000  DISTRIBUTED ENERGY RESOURCES INTERCONNECTION PROCEDURES

 

PART En 1001  SCOPE

 

          En 1001.01  Scope.  These interconnection procedures are applicable to all applications for distributed energy resources seeking to interconnect to a New Hampshire utility.  Such distributed energy resources shall comply with RSA 362-A:9, X and XII.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1002  DEFINITIONS

 

          En 1002.01  “Affected system operator (ASO)” means the independent system operator for the New England region, otherwise known as ISO New England, and operators of other affected electric distribution systems (EDS).

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.02  “Affected system” means any distribution or transmission electric power system other than the utility electric power system (EPS), for which the stability, reliability, or operating characteristics might be significantly affected by the proposed facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.03  “Applicant” means the entity listed on the application for interconnection to the utility EDS who serves as the general point of contact for the application and otherwise assumes responsibility for the application through issuance of the interconnection agreement (IA).  The applicant can be the utility’s customer of record or a third-party owner, operator, or developer of a facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.04  “Application” means a request to have a proposed facility interconnect to a utility EDS, or a request to modify an interconnected facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.05  “Authorization to interconnect” means an official written notification provided by the utility to the interconnecting customer, authorizing the applicant to activate and operate the facility subject to the terms of the interconnection agreement or conditional approval of the interconnection agreement, as applicable.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.06  “Automatic sectionalizing device” means an interrupting device, such as a line recloser, that can automatically re-energize a line.  A fuse is not an automatic sectionalizing device.  If there are no line reclosers upstream of the facility, then the substation circuit breaker is the next automatic sectionalizing device.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.07  “Area network” means a specific area of the EDS fed by multiple, parallel distribution facilities in a meshed configuration with single directional power flow enforced by network protectors.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.08  “Business day” means Monday through Friday excluding state-recognized holidays.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.09  “Certified” means a piece of equipment has been tested in accordance with the applicable requirements of IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 and IEEE Std 1547.1™-2020, “IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces” dated 5/21/2020, by any nationally recognized testing laboratory (NRTL) recognized by the United States Occupational Safety and Health Administration to test and certify equipment pursuant to the applicable standard and the equipment has been labeled and is publicly listed by such NRTL at the time of the interconnection application.  Compliance with Supplement SB found in UL 1741 “Inverters, Converters, Controllers and Interconnection System Equipment for Use with Distributed Energy Resources” dated 4/22/2025 ensures compliance with IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 and IEEE Std 1547.1™-2020, “IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces” dated 5/21/2020.  There might be additional or separate certifications available for specific pieces of equipment.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.10  “Certificate of completion” means the form required as proof that the applicant-facility has been constructed to satisfy all applicable codes, standards, and requirements necessary for the facility to interconnect to the EDS and reviewed and signed off on by the relevant authority having jurisdiction.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.11  “Commission” means the New Hampshire public utilities commission.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.12  “Common study area” means a discrete portion of the company EPS where the operation of multiple interconnecting customers’ facilities may have cumulative impacts.  The company needs to determine if interconnection applications fall within a common study area.  A common study area can include, but is not limited to, an area that:

 

                  (a)  Is fed from a common substation, or

 

                  (b)  Is bounded by a circuit.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.13  “Common system modification” means any system modification that is required for more than one interconnecting customer’s facility as determined by the company.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.14  “Customer” means the person or entity that receives or is entitled to receive service through the utility’s electric distribution system (EDS) or is a retail customer of the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.15  “Department” means the New Hampshire department of energy.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.16  “Detailed study” means the final phase of engineering study, if necessary, conducted by the utility to determine necessary system modifications to its EDS, resulting in project cost estimates and a construction schedule for such modifications that will be required for the facility to interconnect to the EDS.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.17  “Distributed energy resources (DER)” means distributed generation and distributed storage.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.18  “Distributed generation (DG)” means “distributed generation” as defined in RSA 374-F:2, VIII.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.19  “Electric distribution system (EDS)” means the equipment operated and maintained by a utility to deliver electric service to end-users, including and without limitation transmission and distribution lines, substations, transformers, spot networks, and area networks.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.20  “Exempt modification” means a modification to an application or facility that does not increase the export capacity of the facility, relocate the point of interconnection (POI), or otherwise qualify as a material modification.  These include, but are not limited to:

 

          (a)  A change of ownership of a facility;

 

          (b)  A change or replacement of generating equipment, including inverters and transformers, that is a like-kind substitution in size, ratings, impedances, efficiencies, or capabilities of the equipment;

 

          (c)  Replacement of existing inverters with inverters that conform to more recent standards after the state has adopted their use, as long as the export capacity does not increase;

 

          (d)  Any change to equipment on the direct current (DC) side of the applicant’s equipment, including DC coupled storage;

 

          (e)  Any change to relays or reclosers that do not alter trip settings;

 

          (f)  Modification to the grounding configuration that remains in compliance with utility standards;

 

          (g)  A change where the inverter dynamic simulation performance is equivalent to the existing inverter; and

 

          (h)  A reduction in the size of the facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.21  “Existing DER” means a DER that is interconnected with the utility EDS and operating in parallel with the EDS.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.22  “Export capacity” means the maximum nameplate rating of a facility in alternating current (AC), except where the export capacity is limited by any of the methods identified in En 1013.03, the export capacity is the net capacity as limited through the use of such methods not including inadvertent export.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.23  “Facility” means a DER or proposed DER that is located on the customer’s side of the point of common coupling.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.24  “Fault current” means electrical current that flows through a circuit and is produced by an electrical fault, such as phase to ground, double-phase to ground, 3-phase to ground, phase-to-phase, and 3-phase.  A fault current is often several times larger in magnitude than the current that normally flows through a circuit.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.25  “Group” means 2 or more applicant-facilities by the same or different interconnecting customers in a common study area to be studied simultaneously with agreement of all group member-applicants.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.26  “Group study” means a single study that can be performed at the same time for a group, instead of each interconnection application undergoing such study separately either sequentially or in parallel as determined by the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.27  “Group window” means the period during which an applicant can elect to participate in a group.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.28  “Institute of Electrical and Electronics Engineers (IEEE)” means the Institute of Electrical and Electronics Engineers.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.29  “Inadvertent export” means the unintentional and unexpected export of active power from the facility to the utility EDS, exceeding a specified magnitude and for a limited duration pursuant to En 1013, generally due to load following behavior.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.30  “Inadvertent import” means the unintentional and unexpected import of active power from the utility EDS to the facility, exceeding a specified magnitude and for a limited duration pursuant to En 1013. Inadvertent import includes power flow conditions resulting from a fault condition on the utility EDS.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.31  “In-service date” means the date on which system modifications, if applicable, are complete and the facility is interconnected to the EDS and has been granted PTO from the utility, even if the facility is not actively operating by that date.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.32  “Interconnecting customer” means the entity that owns either a proposed facility that is the subject of an application or an existing DER with legal authority to enter into agreements regarding the construction, modification, and operation of the facility or existing DER.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.33  “Interconnection agreement (IA)” means the standard agreement establishing the terms of connecting an applicant’s facility to the utility EDS and entered into by the interconnecting customer and the utility.  The agreement also includes terms and conditions, attachments describing the facility, system modifications, payment terms, and construction schedule, if applicable, and any subsequent amendments or supplements to which the utility and interconnecting customer agree.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.34  “Interconnection equipment package” means a group of components connecting a facility with an EDS, and includes all interface equipment including switchgear, protective devices, inverters, or other interface devices.  An interconnection equipment package can include an integrated generator or electric source.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.35  “Interconnection facilities” means the electrical wires, switches, and related equipment that are required, in addition to the facilities required to provide electric distribution service to a customer, to allow interconnection.  Interconnection facilities can be located on either side of the point of common coupling as appropriate to their purpose and design.  Interconnection facilities can be integrated to a facility or provided separately.  Interconnection facilities can be owned by either the interconnection customer or the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.36  “ISO New England, Inc. (ISO-NE)” means the independent system operator established in accordance with the New England Power Pool agreement and applicable Federal Energy Regulatory Commission approvals, which is responsible for managing the bulk power generation and transmission systems in New England.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.37  “Line section” means that portion of the utility’s EDS connected to a facility bounded by automatic sectionalizing devices or the end of the distribution line.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.38  “Material modification” means a facility modification that is determined by the utility to be an electrically relevant change to the POI, or any modification that requires the utility to reperform a SIS, group study, detailed study, or a substantive simplified process or fast track technical screen for the facility proposed to be modified or any facility behind it in the queue.  Material modification does not include an exempt modification.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.39  “Member impact modification” means a modification to an application, applicant-facility, or existing DER that results in delays to a group study or the implementation of system modifications following a group study or increases the total cost of a group study or the common system modifications.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.40  “Nameplate rating” means the total of maximum continuous power output capacity listed by the manufacturer of all of a facility’s constituent generating or storage units, regardless of whether it is limited by any of the methods in En 1013.03.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.41  “Permission to operate (PTO)” means authorization by the utility to the applicant to commence generation and export power or operate in parallel with the EDS.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.42  “Point of common coupling (PCC)” means the point where the interconnecting customer’s local electric power system connects to the utility EDS, such as the electric power revenue meter or utility’s service transformer.  The PCC shall be specified in the IA.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.43  “Point of interconnection (POI)” means the point where the interconnection facilities connect with the utility’s EDS.  This could or could not be coincident with the PCC.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.44  “Power control system (PCS)” means systems or devices which electronically limit or control steady state currents to a programmable limit.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.45  “Pre-application report” means a non-binding report of certain information provided to the applicant by the utility prior to submission of the application pursuant to En 1006.02.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.46  “Protective function” means the equipment, hardware, and software in a facility, whether discrete or integrated with other functions, whose purpose is to protect against conditions that, if left uncorrected, could result in harm to personnel, damage to equipment, loss of safety or reliability, or the facility’s operation outside pre-established parameters required by the IA.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.47  “Queue” means the sequential list of applications maintained by each utility pursuant to En 1004.03.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.48  “Reference point of applicability (RPA)” means a point suggested by an applicant from where a proposed facility should be studied.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.49  “Screen” means criterium by which the utility will determine if a proposed facility’s installation will adversely impact the utility EDS in the simplified and fast track processes pursuant to En 1007 and En 1008.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.50  “Spot network” means a section of an electric delivery system that uses 2 or more inter-tied transformers to supply an electrical network circuit.  A spot network is generally used to supply power to a single utility customer or to a small group of utility customers and has the same meaning as the term is used in IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power System Interfaces” dated 4/6/2018.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.51  “System impact study (SIS)” means an engineering planning study performed by the utility to determine the impact of the facility on the utility EDS and any necessary system modifications to safely and reliably interconnect the facility to the EDS.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.52  “System impact study agreement (SISA)” means the agreement between the applicant and utility detailing the scope, terms, and cost of the SIS and estimated schedule of completion with progress milestones.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.53  “Technical interconnection requirements (TIR)” means public documents, often utility-specific, which include requirements for interconnection, interoperability, DER capabilities, and their utilization settings, and grid integration.  Grid integration includes, but is not limited to, protection coordination, and telemetry.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1002.54  “Utility” means the company that owns and operates the distribution facilities delivering electricity to the customer’s premises and subject to the jurisdiction of the department and the commission.  For the purpose of this chapter, the term utility does not include a rural electric cooperative for which a certificate of deregulation is on file with the commission.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1003  ORDER OF REVIEW

 

          En 1003.01  Optional Pre-Application Report.  Prior to submitting an application, a potential applicant shall have the option to request a pre-application report from the utility pursuant to En 1006.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1003.02  Interconnection Review.  There shall be 3 interconnection review paths which are the simplified process, fast track process, and standard process.  Within the simplified process and fast track process there shall be options to undertake supplemental review and an applicant options meeting prior to entering standard process.  Any applicant may elect to be placed in standard process or to move into standard process during application processing.  The utility shall process the applications in the order of their queue position as established pursuant to En 1004.03 unless the application is part of a group study pursuant to En 1012.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1003.03  Interconnection Review Paths.

 

          (a)  The simplified process shall be for certified inverter-based facilities that have a nameplate rating of 50 kilowatts (kW) or less and an export capacity of 25 kW or less.  If the facility’s export capacity is not limited, the nameplate rating shall not exceed 25 kW.

 

          (b)  The fast track process shall be for facilities that have an export capacity of up to one megawatt (MW).

 

          (c)  The standard process shall be for all other facilities that do not qualify for, or pass through, the simplified process or fast track process.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1004  APPLICATION SUBMISSION AND PROCESSING

 

          En 1004.01  Submission.  All applicants shall be required to pay an application fee consistent with the application fees adopted by the commission and located in each utility’s retail distribution tariff.  The applicant shall submit the application to the utility along with the applicable application fee, regardless of whether the facility plans to net meter.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1004.02  Completeness Review.  The utility shall record the date and time of the application’s receipt.  The utility shall notify the applicant within 3 business days that the application has been received.  Within 10 business days of receipt, the utility shall notify the applicant whether the application is complete.  If the application is incomplete, the utility shall provide the applicant with a list of all information that the applicant needs to provide to complete the initial application.  The applicant shall provide the requested information within 10 business days for the simplified and fast track processes and 20 business days for the standard process, or the application shall be deemed withdrawn.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1004.03  The Queue.  The utility shall assign the application a queue position once it is deemed complete pursuant to En 1004.02.  The utility shall maintain a queue for all facilities evaluated under the standard process, which may be sortable by geographic region, for example feeder or substation.  The queue shall be publicly available on the utility’s website, shall be updated at least monthly, and shall contain the following information:

 

          (a)  Project ID number;

 

          (b)  Nameplate rating in kW;

 

          (c)  Export capacity in kW;

 

          (d)  Primary fuel type, for example solar, wind, or bio-gas, if applicable;

 

          (e)  Energy storage rating in kW, or not applicable;

 

          (f)  Energy storage capacity in kWh, or not applicable;

 

          (g)  Energy storage coupling either AC, DC, or not applicable;

 

          (h)  Town or city;

 

          (i)  Substation;

 

          (j)  Feeder;

 

          (k)  Status, for example whether active, withdrawn, or interconnected;

 

          (l)  Name of group study, if applicable;

 

          (m)  Date application deemed complete;

 

          (n)  Date of execution of SISA;

 

          (o)  Date of notification of SIS, if readily available;

 

          (p)  Date of notification of detailed study results and construction estimates, if applicable and readily available;

 

          (q)  Identifier of ASO group, if applicable;

 

          (r)  Date final IA is issued to applicant;

 

          (s)  Date IA is fully executed by the signature of both parties; and

 

          (t)  Date of grant of permission to operate.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1004.04  Modifications to a Proposed Facility or an Existing DER.

 

          (a)  At any time after an application is deemed complete, including after the receipt of fast track, supplemental review, group study, SIS, or detailed study results, the applicant or the utility may identify modifications to the proposed facility.  Existing DERs may also propose modifications.  The applicant for a proposed facility or interconnecting customer, for an existing DER, shall submit to the utility, in writing according to each utility’s processes, all proposed modifications to the facility.  The utility shall not unilaterally apply any modification to an application or facility.

 

          (b)  Within 10 business days of receipt of a proposed modification, the utility shall notify the applicant whether the proposed modification constitutes an exempt modification, member impact modification, or material modification as outlined below:

 

                  (1)  If the proposed modification is determined by the utility to be an exempt modification, then the utility shall notify the applicant in writing that the modification has been accepted and that the applicant shall retain its eligibility for interconnection, including its place in the queue;

 

                  (2)  If the application proposed to be modified is part of a group study, and the proposed modification is determined to be a member impact modification, written approval shall be required from all other applicants in the group and the utility as follows:

 

                          a.  The applicant shall submit written approval from all other applicants in the group within 10 business days of notification from the utility that the modification is a member impact modification;

 

                          b.  Within 20 business days of receipt of written authorization from all other applicants in the group, the utility shall provide the applicant with estimated costs, timelines, and requirements for revising the group study process;

 

                          c.  Within 10 business days of notification from the utility related to estimated costs, timelines, and requirements for revising the group study process, the applicant shall submit written approval from all other applicants in the group and pay the utility pursuant to the term of the group study agreement.  If the applicant does not provide such approval and payment, the proposed modification shall be deemed withdrawn;

 

                          d.  Within the timeline specified in (b)(2)b. above in this section, the utility shall provide the applicant with a description of the utility’s analysis, conclusions, and the reasoning supporting those conclusions; and

 

                          e.  Within 10 business days of receipt of the results from the updated group study, the applicant shall notify the utility of its election to proceed with the modification and provide written approval of the modification from all other applicants in the group.  If the applicant does not provide its written approval, the proposed modification, shall be deemed withdrawn;

 

                  (3)  If the proposed modification is determined to be a material modification, the utility shall notify the applicant in writing that the applicant shall provide the utility with its decision in writing by either withdrawing the proposed modification, or by notifying the utility that it wishes to proceed with the modification;

 

                  (4)  The applicant shall provide its decision within 10 business days after the material modification determination notification, which shall note the due date for a response from the applicant.  If the applicant does not provide its decision by the date provided in the notification, the proposed modification shall be deemed withdrawn by the applicant, the application shall remain unchanged and retain its queue position; and

 

                  (5)  If the applicant notifies the utility that it wishes to proceed with the modification within the timeframe indicated in (b)(4) above in this section then the utility shall add the modification to the application and place the application at the end of the queue.

 

          (c)  Any change to the application or proposed facility not previously agreed upon by both the applicant and the utility shall be prohibited and shall result in the application being eligible for removal from the queue.

 

             (d)  Each utility shall provide a process for interconnecting customers to propose changes to existing DERs.  Applications for modifications to existing DERs, whether changes to the existing facility itself or the addition of an energy storage device, shall follow this process.  Proposed changes that are determined to be an exempt modification shall not require processing through the queue.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1004.05  Site Control.  Documentation of site control shall be submitted with the application.  Site control may be demonstrated by providing documentation of any of the following:

 

          (a)  Proof of ownership of, a leasehold interest in, or a right to develop the applicant’s property for the purpose of constructing a facility;

 

          (b)  A copy of or proof of a fully executed option to purchase or acquire a leasehold interest in the facility site for such purpose;

 

          (c)  A copy of a fully executed agreement demonstrating exclusivity or other business relationship between the applicant and the entity having the authority to grant the applicant the right to possess or occupy the facility site for such purpose; or

 

          (d)  A Federal Energy Regulatory Commission (FERC) license in good standing for hydroelectric generating facilities demonstrating that the applicant has authority to act on behalf of the facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1004.06  Continued Review.  If an application does not qualify for interconnection under one review path, but the applicant decides to continue with review under another review path within 10 business days of receipt of utility denial of elected review path, the applicant shall retain its original queue position.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1004.07  Standard Forms.  Each utility shall submit templates or models of its current IA, SISA, group study agreement, group study consent form, detailed study agreement, and application to the department no more than once a year by March 15.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1005  APPLICABLE STANDARDS

 

          En 1005.01  Applicable Standards.  The applicant and DER shall comply with the utility’s TIR as defined in En 1002.53 and the standards identified in this section, as applicable, unless waived by the utility.  If the utility’s published technical interconnection standards specify a more recent industry standard, then the industry standard cited in the utility’s technical interconnection standards shall prevail.  Applicable standards include the following:

 

          (a)  IEEE Std 1547-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B;

 

          (b)  IEEE Std 1547.1™-2020, “IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces” dated 5/21/20 as available in Appendix B;

 

          (c)  ANSI C84.1-2020, “Electric Power Systems and Equipment-Voltage Ratings (60 Hertz)” dated 3/10/2020 as available in Appendix B;

 

          (d)  IEEE Std 1547.2™-2023, “IEEE Application Guide for IEEE Std 1547™-2018, IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 5/20/2024 as available in Appendix B;

 

          (e)  IEEE Std 1547.3™-2023, “IEEE Guide for Cybersecurity of Distributed Energy Resources Interconnected with Electric Power Systems” dated 12/11/2023 as available in Appendix B;

 

          (f)  IEEE Std 1547.7™-2013, “IEEE Guide for Conducting Distribution Impact Studies for Distributed Resource Interconnection” dated 2/28/2014 as available in Appendix B;

 

          (g)  IEEE Std 519™-2022, “IEEE Standard for Harmonic Control in Electric Power Systems” dated 8/5/2022 as available in Appendix B;

 

          (h)  IEEE Std 1453™-2022, “IEEE Standard for Measurement and Limits of Voltage Fluctuations and Associated Light Flicker on AC Power Systems” dated 2/27/2023 as available in Appendix B;

 

          (i)  IEEE Std C37.90.2™-2024, “IEEE Standard for Relays, Relay Systems, and Control Devices used for Protection and Control of Electric Power Apparatus-Radiated Electromagnetic Interference Withstand Capability Requirements and Tests” dated 1/31/2025 as available in Appendix B;

 

          (j)  IEEE C37.95™-2014, “IEEE Guide for Protective Relaying of Utility-Consumer Interconnections” dated 5/5/2014 as available in Appendix B;

 

          (k)  IEEE Std C50.13™-2014, “IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous Generators Rated 10 MVA and Above” dated 5/9/2014 as available in Appendix B;

 

          (l)  IEEE Std C62.92.1™-2016, “IEEE Guide for the Application of Neutral Grounding in Electric Utility Systems-Part I: Introduction” dated 3/31/2017 as available in Appendix B;

 

          (m)  IEEE Std C62.92.2™-2017, “IEEE Guide for the Application of Neutral Grounding in Electric Utility Systems, Part II-Synchronous Generator Systems” dated 5/19/2017 as available in Appendix B;

 

          (n)  IEEE Std C62.92.6™-2017, “IEEE Guide for Application of Neutral Grounding in Electrical Utility Systems, Part VI-Systems Supplied by Current-Regulated Sources” dated 12/22/2017 as available in Appendix B;

 

          (o)  UL 1741, “Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources” dated 4/22/2025 as available in Appendix B;

 

          (p)  Certification Requirement Decision for Power Control Systems, March 8, 2019, Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources found in UL 1741, “Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources” dated 4/22/2025 as available in Appendix B; and

 

          (q)  UL 3141 “UL LLC Outline of Investigation for Power Control Systems” dated 10/9/2024 as available in Appendix B.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1005.02  Utility TIRs.  Each utility shall publish and maintain TIRs.  The utilities shall convene a TIR working group quarterly that includes participation from interested stakeholders to ensure technical standards are regularly maintained, updated, and consistent with good utility practice.  The TIR working group shall be comprised of 6 members with 3 members representing utilities and 3 members representing companies engaged in the development and installation of DERs in New Hampshire.  The TIR working group shall have 2 co-chairs with one representing utility members and one representing industry members.  The utilities shall provide notice of changes to the TIR working group.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1005.03  Index of technical standards.  Each utility shall publish and maintain a complete index of all technical standards and requirements pursuant to En 1000 with references to each of the standards and requirements in a place of prominence and easy accessibility on each utility’s website.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1006  PRE-APPLICATION REPORT

 

          En 1006.01  Pre-Application Report Request.  Applicants who elect to submit a pre-application report to the utility as permitted by En 1003.01 shall include in their request the following information:

 

          (a)  Contact information to include name, address, phone number, and email address;

 

          (b)  A proposed POI that includes the latitude and longitude, site map, street address, utility equipment number, for example pole number, meter number, account number, or some combination of the above sufficient to clearly identify the location of the proposed POI;

 

          (c)  Facility type, for example solar, wind, combined heat and power, storage, or solar-plus-storage;

 

          (d)  Nameplate rating and export capacity, if different;

 

          (e)  Single- or 3-phase configuration;

 

          (f)  Whether the facility is stand-alone or will service onsite load;

 

          (g)  Whether new service is requested; and

 

          (h)  Non-refundable processing fee to the utility as approved by the commission.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1006.02  Pre-Application Report.

 

          (a)  Within 10 business days of receipt of a completed pre-application report request, the utility shall provide a pre-application report to the applicant.  The pre-application report shall include the following information, if available:

 

                  (1)  Circuit voltage at the substation;

 

                  (2)  Circuit name;

 

                  (3)  Circuit voltage at the proposed facility;

 

                  (4)  Substation name;

 

                  (5)  Substation transformer rating;

 

                  (6)  Whether or not 3-phase power is available at the site or distance from 3-phase service;

 

                  (7)  Aggregate existing export capacity (MW) interconnected to the substation, area bus, transformer bank, and distribution circuit expected to serve proposed site;

 

                  (8)  Aggregate queued export capacity (MW) proposing to interconnect to the substation, area bus, transformer bank, and distribution circuit expected to serve proposed site;

 

                  (9)  Whether zero sequence voltage (3V0) protection is deployed or scheduled for deployment on the circuit or substation;

 

                  (10)  Whether the proposed facility is located on an area, spot, or radial network;

 

                  (11)  Identification of feeders within 1/4 mile of the proposed interconnection site through a snapshot of geographic information system (GIS) map or other means;

 

                  (12)  For the nearest available feeder, the circuit rating and approximate circuit length from the proposed facility to the substation;

 

                  (13)  Whether an ASO has informed the utility that an ASO study is required, or the utility is aware of an ongoing ASO study for the proposed facility interconnection location;

 

                  (14)  Total capacity (MW) of substation, area bus, transformer bank, and distribution circuit expected to serve proposed site, based on the thermal ratings of the utility’s electric delivery system;

 

                  (15)  Available capacity (MW) of substation, area bus, transformer bank, and distribution circuit expected to serve proposed site, based on the thermal ratings of the utility’s EDS.  Available capacity is the total capacity less the sum of existing and queued export capacity, accounting for all load served by existing and queued facilities;

 

                  (16)  Relevant line section(s) and substation actual or estimated peak load and minimum load data;

 

                  (17)  Number and rating of protective devices and number and type of voltage regulating devices between the proposed site and the substation or area bus;

 

                  (18)  Limiting conductor rating from proposed POI to distribution substation;

 

                  (19)  Based on proposed POI, existing or known constraints such as, but not limited to, electrical dependencies at that location, short circuit interrupting capacity issues, power quality or stability issues on the circuit, capacity constraints, or secondary networks; and

 

                  (20)  Any other information the utility deems relevant to the applicant.

 

          (b)  The pre-application report shall include language to inform the applicant that:

 

                  (1)  The existence of available capacity in no way implies that an interconnection up to this level may be completed without impacts because there are many variables studied as part of the interconnection review process;

 

                  (2)  The utility EDS is dynamic and subject to change; and

 

                  (3)  Data provided in the pre-application report might become outdated and not useful at the time of submission of the complete application.

 

          (c)  The pre-application report shall only include pre-existing data.  A pre-application report request shall not obligate the utility to conduct a study or other analysis of the proposed project if data is not available.  If the utility cannot complete all or some of a pre-application report due to lack of available data, the utility shall provide the potential applicant with a pre-application report that includes the information that is available and identify the information that is unavailable.

 

          (d)  Notwithstanding any of the provisions of this section, the utility shall provide pre-application report data that represents the best available information at the time of submission.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1007  SIMPLIFIED PROCESS REVIEW

 

          En 1007.01  Eligibility.  Simplified process review shall be available to any certified inverter-based facility that has a nameplate rating that does not exceed 50 kW and has an export capacity of 25 kW or less.  If the facility’s export capacity is not limited, the nameplate rating shall not exceed 25 kW.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.02  Application.  An applicant shall submit an application with the fee pursuant to En 1004.01, which shall be sent electronically pursuant to each utility’s instructions.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.03  Simplified Process Screen.  The utility shall evaluate the application to ensure the equipment is certified to current standards and the utility’s EDS is able to accommodate the facility.  The utility shall utilize the following screens as applicable to each facility review:

 

          (a)  For certified equipment screens, the applicant-facility shall utilize an inverter certified to Supplement SB as found in UL 1741, “Standard for Inverters, Converters, Controllers with Interconnection System Equipment for Use with Distributed Energy Resources” dated 4/22/2025 as available in Appendix B;

 

          (b)  For minimum load screen for interconnection of a facility to a radial distribution circuit, the facility’s export capacity, aggregated with the export capacity of all other existing DERs on a line section, shall not exceed 100 percent of the line section’s relevant minimum load as most recently measured at the substation or calculated for the line section.  If the utility does not have relevant minimum load data, 25 percent of the peak feeder load shall be used instead;

 

          (c)  For shared secondary screens, if the facility is to be interconnected on a single-phase shared secondary, then the aggregate generation capacity on the shared secondary, including the facility’s export capacity, shall not exceed 25 kVA;

 

          (d)  For service imbalance screens, if the facility is single-phase and is to be interconnected on a transformer center tap neutral of a 240-volt service, its addition shall not create an imbalance between the 2 sides of the 240-volt service of more than 20 percent of the nameplate rating of the service transformer; and

 

          (e)  For network screens for interconnection of a facility within a spot network or area network, the export capacity shall be 15 kW or less, and the aggregate nameplate rating including the facility’s nameplate rating shall not exceed one fifteenth of the spot network or area network’s relevant minimum load.  Alternately, if the utility does not have minimum load data for the spot or area network, the utility shall select any of the following methods to determine anticipated minimum load:

 

                  (1)  Five percent of the spot network or area network’s maximum load in the previous year;

 

                  (2)  The utility’s estimate, if provided in writing to the applicant along with an explanation why the utility cannot calculate or measure minimum load; or

 

                  (3)  If there is no existing meter or the existing metering in place cannot be used to determine the minimum load, then a meter capable of recording minimum loads shall be installed at the applicant’s expense as follows:

 

                          a.  In such cases, the utility shall install an appropriate meter to measure 3 months of continuous customer load capturing the annual minimum load.  The maximum time the utility-approved monitoring equipment shall be used to measure the minimum load is 9 months from the point of the time the analysis was commenced; and

 

                          b.  The utility shall remove the meter at the applicant’s expense if the applicant requests its removal provided the interval meter is not required to bill the rate on which the customer shall take service when the facility is interconnected.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.04  Time to Process Screens.  Within 15 business days after the utility notifies the applicant that the application is complete, the utility shall notify the applicant whether the facility meets all the applicable simplified process screens.  If the applicant is proposing to interconnect within a spot network or area network and an interval meter is required pursuant to En 1007.03(e)(3), the utility shall notify the applicant whether the facility meets all the applicable simplified process screens within 60 business days after the utility notifies the applicant that the application is complete.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.05  Screens Failure.

 

          (a)  Despite the failure of one or more screens, the utility may authorize an applicant or facility to interconnect to the EDS provided such interconnection does not compromise the safe and reliable operation of the EDS.

 

          (b)  If the utility determines that the facility cannot interconnect based on screen results, the utility shall provide the applicant with the screen results detailing the specific screens that the application failed, including the technical reason for failure.  The screen results shall include information about the specific system threshold or limitation causing the application to fail the screen, and the utility shall discuss the applicant’s options to interconnect based on current circumstances.  Upon review of the screen results, the utility shall allow the applicant to undergo supplemental review, in accordance with En 1009.  The applicant shall notify the utility of its selection to proceed to further study within 10 business days or the application shall be deemed withdrawn.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.06  Approval.

 

          (a)  If the application passes the screens, the application shall be approved, and the utility shall provide the applicant with a written notice of approval to install within 15 business days of deeming the application complete.

 

          (b)  If the facility requires no system modifications to the EDS, the utility shall provide the applicant with PTO following receipt of certificate of completion and closing paperwork pursuant to En 1004.

 

          (c)  If the facility requires any EDS modifications, the utility shall provide written conditional approval to interconnect, along with an itemized, non-binding good faith cost estimate and construction schedule for such upgrades, to the applicant within 15 business days of providing the screening results.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.07  Time for Commencing Operation.  Unless extended by mutual agreement of the parties, within 12 months of fully executing the IA or 12 months from the completion of any necessary EDS modifications, whichever is later, the applicant shall commence operation of the facility subject to satisfying En 1007.08 and En 1007.09.  The applicant shall provide the utility with notice of the completion of construction of the facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.08  Final Utility Review and Metering.

 

          (a)  If the utility determines that a review of the facility or changes to the applicant’s meter are necessary, the utility shall complete this work within 10 business days of receiving the complete facility as-built documentation from the applicant.  If the facility passes the review, the utility shall provide written notice of the passage within 3 business days.

 

          (b)  If the facility initially fails a utility review, the utility shall offer to reinspect the facility at the applicant’s expense at a time mutually agreeable to both the utility and the applicant.  If the utility determines that the facility fails the review, including the discovery of unapproved changes to the facility, the utility shall provide the applicant with a written explanation detailing the reasons for the failure and any standards violated within 3 business days.

 

          (c)  If the utility determines no inspection or changes to the applicant’s meter are necessary, it shall notify the applicant within 3 business days of receiving the notice of the completion of construction.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1007.09  Operation.  The utility shall provide PTO and the facility may begin operating provided that:

 

             (a)  The applicant has received conditional approval to interconnect;

 

          (b)  The utility has received proof of the respective electric code official’s approval including a signed certificate of completion or other inspector-code official provided documentation;

 

          (c)  The applicant successfully completed the witness test if required by the utility pursuant to En 1011.11; and

 

          (d)  The applicant has received written notice that the facility passed any review required by the utility or received notice that no review is required.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1008  FAST TRACK PROCESS REVIEW

 

          En 1008.01  Eligibility.  Fast track review shall be available to any facility that has an export capacity that does not exceed 1 MW.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.02  Application.  An applicant shall submit a complete application with the fee pursuant to En 1004.01, which shall be sent electronically pursuant to each utility’s instructions.  Separate from and in addition to the application fee described in En 1004.01, the applicant shall submit a fee for fast track review.  The fast track review fee shall be utility specific and designed to recover all costs associated with the fast track review process, shall be based upon the applicant’s facility export capacity, and may consist of a fixed fee in whole or in part.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.03  Required Screens.  The utility shall evaluate the application using the following screens:

 

          (a)  For minimum load screen for interconnection of a DER to a radial distribution circuit, the DER’s export capacity, aggregated with the export capacity of all other DERs on a line section, shall not exceed 100 percent of the line section’s relevant minimum load as most recently measured at the substation or calculated for the line section.  If the utility does not have relevant minimum load data, 25 percent of the peak feeder load shall be used instead;

 

          (b)  For inadvertent export screen for interconnection of a proposed DER that can introduce inadvertent export, where the nameplate rating of the DER minus the export capacity is greater than 250 kW, the power change equal to the nameplate rating minus the export capacity, the change in voltage at the point on the medium voltage (primary) level nearest the POI shall not exceed 3 percent.  Voltage change will be estimated applying the following formula:

 

 

Formula

(RSOURCE × ∆𝑷) – (XSOURCE × ∆𝑸)

V2

Where:

∆𝑷 = (DER apparent power Nameplate Rating – Export Capacity) × PF,

∆𝑸 = (DER apparent power Nameplate Rating – Export Capacity) × ,

RSOURCE is the grid resistance, XSOURCE is the grid reactance,

V is the grid voltage, PF is the power factor

 

          (c)  For fault current contribution screen, the DER, aggregated with other generation on the distribution circuit, shall not contribute more than 10 percent to the distribution circuit’s maximum fault current at the point on the primary nearest the proposed POI;

 

          (d)  For short circuit interrupting capability screen, the DER, aggregated with other generation on the distribution circuit, shall not cause any distribution protective devices and equipment, including but not limited to substation breakers, fuse cutouts, and line reclosers, or utility customer equipment on the system, to exceed 90 percent of the short circuit interrupting capability, nor is the interconnection proposed for a circuit that already exceeds 90 percent of the short circuit interrupting capability;

 

          (e)  The line configuration screen shall include a review of the type of electrical service provided to the interconnecting customer, including line configuration and the transformer connection to limit the potential for creating over-voltages on the utility’s EDS due to a loss of ground during the operating time of any anti-islanding function.  The DER shall comply with the applicable type of interconnection, based on Table 1008 below:

 

Table 1008: Line Configuration for DER Interconnection

 

Primary Distribution Line Configuration

Type of Interconnection to Primary Distribution Line

Results/Criteria

 

3-phase, 3-wire

3-phase or

single-phase, phase-to-phase

 

Pass Screen

 

3-phase, 4-wire

3-phase or

single-phase, line-to-neutral

 

Pass Screen

 

             (f)  For shared secondary transformer screens, if the facility is to be interconnected on a single-phase shared secondary, then the aggregate export capacity on the shared secondary, including the facility’s export capacity, shall not exceed 25 kVA.  The utility shall consider voltage control capabilities of the facility to determine if such controls can alleviate the voltage concern identified by this screen;

 

          (g)  For service imbalance screens, if the DER is single-phase and is to be interconnected on a transformer center tap neutral of a 240-volt service, its addition shall not create an imbalance between the 2 sides of the 240-volt service of more than 20 percent of nameplate rating of the service transformer;

 

          (h)  For transient stability screens, the DER’s nameplate rating, in aggregate with other generation interconnected to the distribution low-voltage side of the substation transformer feeding the distribution circuit where the DER proposes to interconnect shall not:

 

                  (1)  Exceed 10 MW in an area where there are known or posted transient stability limitations to generating units located in the general electrical vicinity for example 3 or 4 transmission voltage level busses from the POI; and

 

                  (2)  Have interdependencies, known to the utility, with earlier queued interconnection requests, that would necessitate further study;

 

          (i)  For stiffness screens, the ratio of the utility short circuit current at the PCC to the proposed DER’s nameplate rated current shall not be less than 25;

 

          (j)  For transmission screens, the DER’s PCC shall not be on a transmission line;

 

          (k)  For network screens for interconnection of a DER within a spot network or area network, the aggregate nameplate rating including the DER’s nameplate rating shall not exceed 50 percent of the spot network or area network’s relevant minimum load.  Alternately, if the utility does not have minimum load data for the spot or area network, the utility may select any of the following methods to determine anticipated minimum load:

 

                  (1)  Five percent of the spot network or area network’s maximum load in the previous year;

 

                  (2)  The applicant’s good faith estimate, if provided; or

 

                  (3)  The utility’s estimate if provided in writing to the applicant along with the reasons why the utility considered the other methods to estimate minimum load inadequate; and

 

          (l)  For effective grounding screens, the proposed facility in aggregation with other generation in the vicinity of the proposed POI shall not exceed the utility’s threshold for requiring effective grounding established in the utility’s current TIR.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.04  Time to Process Screens.  Within 25 business days after the utility notifies the applicant that the application is complete, the utility shall notify the applicant whether the facility meets all of the applicable fast track screens.  The utility’s 25 business day notification shall not include time when the application is on hold pending information to be provided by the applicant or other hold requested by the applicant and approved by the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.05  Screens Failure.  Despite the failure of one or more screens, the utility, at its sole discretion, shall approve the interconnection provided such approval is consistent with safety and reliability.  The utility shall provide the applicant with the screen results in the event of failure of any screens identifying which of the specific screens the application failed, the technical reason for failure, and the specific system threshold or limitation causing the application to fail the screen.  The utility shall provide the applicant with the option to either undergo supplemental review, in accordance with En 1009, or proceed under the standard process beginning with the SIS pursuant to En 1011.06.  Upon receipt of the screening results, the applicant shall notify the utility of its selection within 10 business days or the application shall be deemed withdrawn.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.06  Approval.  If the applicant passes the screens, the application shall be approved, and the utility shall provide the applicant with an executable IA within the following timeframes:

 

          (a)   If the facility requires no EDS modifications by the utility, the utility shall provide the IA to the applicant at the same time that the utility provides the fast track or supplemental review results; or

 

          (b)  If the facility requires EDS modifications, the utility shall provide the IA, along with an itemized, non-binding cost estimate and construction schedule for such upgrades, to the applicant within 15 business days after the fast track or supplemental review results.  If the cost to generate the non-binding estimate exceeds $2,500, the utility shall invoice the applicant for the cost of the estimate.  The applicant shall remit payment to proceed within 10 business days of receipt of the invoice or the application shall be deemed withdrawn.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.07  Reference Point of Applicability Review.  This process shall occur concurrently with fast track screening pursuant to En 1008.04:

 

          (a)  If it is determined that the RPA is appropriate, the utility shall notify the applicant when it provides the screen results and proceed according to En 1008.04; and

 

          (b)  If the utility determines that the RPA is inappropriate, the following shall occur:

 

                  (1)  The utility shall notify the applicant and with the notification include an explanation as to why it requires correction;

 

                  (2)  Upon receipt of notification from the utility the applicant shall provide the utility with a corrected application with the proper RPA within 5 business days of notification;

 

                  (3)  The utility shall review the corrected application with the proper RPA within 5 business days of receipt;

 

                  (4)  If the proper RPA is provided, the utility will proceed according to En 1008.04; and

 

                  (5)  If the applicant does not provide the appropriate location or request an extension of time within the deadline, the application shall be deemed withdrawn.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.08  IA Execution.

 

          (a)  An applicant that receives an IA shall have 15 business days to execute the agreement and return it to the utility along with any required payment due upon execution of the IA.

 

          (b)  Failure to submit an executed IA with the necessary payment shall result in withdrawal of the application from the queue upon the utility notifying the applicant unless the applicant and the utility mutually agree to extend the deadline pursuant to En 1014.02.

 

          (c)  Within 24 months from an applicant’s execution of an IA or 6 months of completion of any EDS modifications, whichever is later, the facility shall commence operation unless the applicant and utility agree to an extension.  The applicant shall provide the utility with notice of the completion of construction of the facility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1008.09  Final Utility Review and Metering.  If the utility determines that a review of the facility or changes to the applicant’s meter are necessary, the following shall occur:

 

          (a)  The utility shall review the facility or change the applicant’s meter within 10 business days of receiving the complete facility as-built documentation from the applicant;

 

          (b)  If the facility passes the review, the utility shall provide written notice of such outcome to the applicant within 3 business days;

 

          (c)  If the facility initially fails a utility review, the utility shall offer to conduct the inspection again at the applicant’s expense at a time mutually agreeable to both the utility and the applicant;

 

          (d)  If the utility determines that the facility fails the review described in (c) above in this section, including the discovery of unapproved changes to the facility, the utility shall provide the applicant with a written explanation detailing the reasons for the failure and any standards violated within 3 business days; and

 

          (e)  If the utility determines no review or changes to the applicant’s meter are necessary based on its review described in (a) above in this section, it shall notify the applicant within 3 business days of receiving the notice of the completion of construction.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

             En 1008.10  Operation.  An applicant may begin operating if:

 

          (a)  There is an IA in effect;

 

          (b)  The utility has received proof of the respective electric code official’s approval including a signed certificate of competition or other inspector-code official provided documentation;

 

          (c)  The applicant successfully completed the witness test if required by the utility pursuant to En 1011.11; and

 

          (d)  The applicant has received written notice that the facility passed any review required by the utility or received notice that no review is required.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1009  SUPPLEMENTAL REVIEW

 

          En 1009.01  Supplemental Review.  If the applicant agrees to undergo supplemental review, it shall notify the utility and submit a fee for supplemental review in accordance with the timeline specified in En 1007.05 or En 1008.05.  The supplemental review fee shall be utility specific and designed to recover all costs associated with the supplemental review process, shall be based upon the applicant’s facility export capacity, and may consist of a fixed fee in whole or in part.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

             En 1009.02  Utility Response to Supplemental Review.  Within 20 business days of an applicant’s election to undergo supplemental review and payment of the fee, the utility shall perform supplemental review using the screens set forth below in En 1009.03, notify the applicant of the results, and include with the notification a written report of the analysis and data underlying the utility’s determinations under the screens, including information about the specific system threshold or limitation causing the result.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1009.03  Screens.  The utility shall evaluate the application using the following screens as applicable:

 

          (a)  The utility shall apply the minimum load screen analysis as follows:

 

                  (1)  Where 12 months of line section minimum load data, including onsite load but not station service load served by the proposed facility, are available, can be calculated, estimated from existing data, or determined from a power flow model, the facility’s export capacity aggregated with all other generation capable of exporting energy on the line section is less than 100 percent of the relevant minimum load for all line sections bounded by automatic sectionalizing devices upstream of the proposed facility;

 

                  (2)  If the minimum load data is not available, or cannot be calculated or estimated, the facility’s export capacity aggregated with all other generation capable of exporting energy on the line section is less than 30 percent of the peak load for all line sections bounded by automatic sectionalizing devices upstream of the proposed facility;

 

                  (3)  Load that is co-located with load-following, non-exporting, or export-limited generation shall be appropriately accounted for; and

 

                  (4)  The utility shall not consider as part of the aggregate export capacity for purposes of this screen facility export capacity, including combined heat and power (CHP) facility capacity, known to be already reflected in the minimum load data;

 

          (b)  The utility shall apply the voltage and power quality screen.  In instances where the facility limits export pursuant to En 1013, the export capacity instead of nameplate rating shall be utilized including power flow simulations.  When combined with existing generation on the same line section, the aggregate impact shall be evaluated to ensure compliance with voltage and power quality standards:

 

                  (1)  The voltage regulation on the line section shall be maintained in compliance with relevant requirements under all system conditions;

 

                  (2)  The voltage fluctuation shall be within acceptable limits as defined by IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B; and

 

                  (3)  The harmonic levels shall comply with limits at the RPA pursuant to the IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018, as available in Appendix B;

 

          (c)  The utility shall apply the supplemental grounding screen if the facility failed the effective grounding screen pursuant to En 1008.03(l).  The supplemental grounding screen shall be applied as follows:

 

                  (1)  For facilities with a rotating machine, effective grounding shall be maintained; or

 

                  (2)  For facilities with a three-phase inverter, the utility shall apply the following criteria to evaluate whether the DER is effectively grounded:

 

                          a.  The line-to-neutral connected load on the feeder or line section is greater than 33 percent of peak load on the feeder or line section;

 

                          b.  If using a supplemental grounding software tool:

 

                                  i.  The tool determines that supplemental grounding is not required to maintain effective grounding;

 

                                  ii.  If the tool determines that supplemental grounding is required, the applicant shall agree to modify the facility to include supplemental grounding; and

 

                          c.  If using a detailed hosting capacity analysis that incorporates evaluation of temporary overvoltage risk for inverters, the nameplate rating of the facility is below the available hosting capacity at the POI;

 

          (d)  The utility shall apply the safety and reliability screen.  The location of the proposed facility and the aggregate export capacity on the line section shall not create impacts to safety or reliability that cannot be adequately addressed without standard process review.  If the facility limits export pursuant to En 1013, the export capacity shall be included in any analysis including power flow simulations, except when assessing fault current contribution.  To assess fault current contribution, the rated fault current shall be used; and

 

          (e)  When making a determination concerning the impacts to safety and reliability in applying the screen in (d) above in this section, the utility shall consider the following factors which shall include but not be limited to:

 

                  (1)  Whether the line section has significant minimum loading levels dominated by a small number of customers, for example several large commercial customers;

 

                  (2)  Whether there is an even or uneven distribution of loading along the feeder;

 

                  (3)  Whether the proposed facility is located in close proximity to the substation, for example < 2.5 electrical circuit miles, and whether the distribution line from the substation to the POI is composed of large conductor or feeder section, for example 600A class cable;

 

                  (4)  Whether the proposed facility incorporates a time delay function to prevent reconnection of the facility to the system until system voltage and frequency are within normal limits for a prescribed time;

 

                  (5)  Whether operational flexibility is reduced by the proposed facility, such that transfer of the line section(s) of the facility to a neighboring distribution circuit or substation might trigger overloads or voltage issues; and

 

                  (6)  Whether the proposed DER utilizes certified anti-islanding functions and equipment.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1009.04  Passage of the Supplemental Screens.  If the proposed interconnection passes the supplemental screens, the utility shall approve the application and provide the applicant an executable IA pursuant to the procedure set forth in En 1008.06.  After receiving an IA executed by the utility, the applicant shall proceed under the terms of the applicable level of review under which the application was initially studied.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1010  APPLICANT OPTIONS MEETING

 

          En 1010.01  Applicant Options Meeting.

 

          (a)  If the utility determines that an application that has gone through the simplified process, the fast track process, or supplemental review requires review using the standard process, the utility shall provide the applicant the option of proceeding to standard process review or of participating in an applicant options meeting with the utility to review the screening analysis and related results and possible application modifications to determine what further study is needed for the facility to proceed with interconnection to the EDS.

 

          (b)  The applicant shall request either an applicant options meeting or notify the utility that it shall proceed with the standard process within 10 business days of receipt of screen results or the application shall be deemed withdrawn.  If the applicant requests an applicant options meeting, the utility shall offer to convene the meeting at a mutually agreeable time within 15 business days of the applicant’s request.

 

          (c)  After the applicant options meeting, the applicant may choose within 10 business days to either amend the application or proceed with the standard process pursuant to the following process:

 

                  (1)  If the applicant chooses to amend the application to address the specific failed screens, the applicant shall have one opportunity to submit an updated application including all necessary redesigns that address screen failures within 10 business days;

 

                  (2)  If the applicant makes any material modifications that do not directly correct the screen failure(s), it shall result in the application losing its queue position and being placed at the end of the queue; or

 

                  (3)  If the applicant fails to either amend the application or proceed with the standard process within 10 business days of receiving the notification from the utility of the results of the evaluation described in (d) below in this section, the application shall be deemed withdrawn.

 

          (d)  Within 20 business days of receiving the updated application, the utility shall evaluate whether the redesign addresses the screen failure(s) and notify the applicant of the results of this evaluation.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1011  STANDARD PROCESS

 

          En 1011.01  Application.  An applicant shall submit an application with the fee pursuant to En 1004.01 electronically in compliance with the utility’s instructions.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.02  System Impact Study Agreement.  Separate from and in addition to the application fee pursuant to En 1004.01, all expected costs necessary for the utility to conduct necessary EDS study shall be set forth in a separate SISA between the utility and the applicant, issued by the utility, the payment of which shall be due in full prior to the commencement of work.  The utility shall make their best faith efforts to estimate the actual costs necessary to study the EDS for interconnection of the applicant’s proposed facility.  As set forth in the SISA, the applicant shall bear and be responsible for all costs to interconnect the facility to the system, including, without limitation, all necessary system modification costs.  Should any dollars remain from the SISA, they shall be included in the true up as a part of the final accounting described in En 1018.11.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.03  Scoping Meeting.

 

          (a)  The utility shall conduct an initial review that includes a scoping meeting with the applicant within 15 business days of determining that an application is complete.  The purpose of the scoping meeting shall be to discuss the application, the RPA, and review existing studies relevant to the application.

 

          (b)  The scoping meeting shall take place in person, by telephone, or electronically by a means mutually agreeable to the utility and applicant.

 

          (c)  At the scoping meeting, the utility shall provide pertinent information such as:

 

                  (1)  The available fault current at the proposed location;

 

                  (2)  The existing peak loading on the lines in the general vicinity of the proposed facility; and

 

                  (3)  The configuration of the distribution line at the proposed POI, and whether the proposed facility may be required to participate in an ASO study.

 

          (d)  The utility and the applicant shall bring to the meeting personnel, including system engineers, and other resources as might be reasonably required to accomplish the purpose of the meeting.

 

          (e)  By mutual agreement of the parties, the scoping meeting, SIS, or detailed study may be waived.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.04  Affected System Operator.

 

          (a)  The utility shall coordinate with the applicant, ASO, and any affected system owners if an ASO study is required.

 

          (b)  The utility shall not be responsible for the timing of an ASO study.

 

          (c)  Within 10 business days following receipt of complete information from the ASO, the utility shall provide the applicant with information related to the plan for conducting the ASO study, including the responsibilities of each party, the scope of the study, the expected timeline for completion, and the estimated cost.

 

          (d)  The applicant shall be directly responsible to the ASO and affected system owner for all costs of any additional studies required to evaluate the impact of the interconnection on the affected systems.

 

          (e)  The applicant shall be directly responsible for any resulting affected system costs, including, without limitation, modifications to the electric power system of the ASO or affected system owner and operation and maintenance costs.

 

          (f)  The utility may, in its sole discretion, elect to include the additional ASO study costs and affected system costs in the utility’s cost estimates.  If the utility elects to include these costs in its estimates, the utility shall specify the ASO study costs and the affected system costs in its estimates.  The applicant shall pay the utility for those costs, and the utility shall pay those costs to the ASO and affected system owner.

 

          (g)  The applicant shall be responsible for all actual affected system costs necessitated as a result of the ASO requirements, none of which shall be subject to any cost caps or limitations under this chapter.

 

          (h)  Within 5 business days of notice from the ASO that additional information or technical data about the facility is required for the ASO study, the utility shall notify the applicant.  The applicant shall provide the requested information to the utility or request additional time from the utility within 15 business days of the notification from the utility.  If the applicant fails to provide the requested information within the allowed time, the applicant shall have the opportunity to cure the failure ahead of the application being removed from its queue position pursuant to the required notification period established in 1014.02(c).  If the applicant does not cure the failure within the required notification period, the application shall be withdrawn unless the applicant and the utility mutually agree to extend the deadline.

 

          (i)  Within 5 business days of notice from the ASO of any ASO study costs, the utility shall notify the applicant.  The applicant shall provide payment within 15 business days of the notification from the utility.  If the applicant fails to provide payment within the allowed time, the applicant shall have the opportunity to cure the failure ahead of the application being removed from its queue position pursuant to the required notification period established in 1014.02(c).  If the applicant does not cure the failure within the required notification period, the application shall be withdrawn unless the applicant and the utility mutually agree to extend the deadline.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.05  Group Study Process.

 

          (a)  The utility may evaluate the application in a group study if any of the following criteria are met:

 

                  (1)  Interconnection of the facility will require upgrading the substation transformer;

 

                  (2)  Interconnection of the facility requires common system modifications; or

 

                  (3)  The applicant requests a group study and the utility approves the request.

 

          (b)  The utility shall not delay or deny a request for a group study based solely on the requirement that a group member application participate in an ASO study.

 

          (c)  If an ASO study is required, the applicant may elect to proceed with the group study pursuant to En 1012.  If the applicant elects to proceed with the group study prior to the completion of the ASO study and the results of the ASO study require the utility to amend the applicant’s group study, the utility shall provide an amended group study agreement with a cost estimate and expected timeline to complete the updated group study.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.06  System Impact Study.

 

          (a)  If an ASO study is required, the applicant may elect to proceed with the SIS pursuant to this section.  If the applicant elects to proceed with the SIS prior to the completion of the ASO study, and the ASO study results necessitate revisions to the SIS, the utility shall issue an amended SISA incorporating updated cost estimates and a revised schedule for the completion of the amended SIS.  The utility shall complete the amended SIS in accordance with (g) below in this section.

 

          (b)  For applicants participating in a group study, the group study shall satisfy the requirement for a SIS.  A separate SIS shall not be required.

 

          (c)  If the parties do not waive the SIS, within 10 business days of the completion of the scoping meeting, or 10 business days after completion of the application or the final step in the simplified process or fast track process if scoping meeting is waived, the utility shall provide the applicant with a standard form SISA, including a good faith estimate of the cost and time to undertake the SIS.  The applicant shall return the signed SISA within 20 business days, or the application shall be deemed withdrawn.

 

          (d)  A SIS for a facility shall include a review of the facility’s adherence to IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B.  For facility components that are certified, the utility shall not charge the applicant for review of those components in isolation.

 

          (e)  Each utility shall include in its SISA a description of the various elements of a SIS it shall undertake pursuant to this section, which may include but is not limited to:

 

                  (1)  Load-flow study;

 

                  (2)  Short-circuit study;

 

                  (3)  Circuit protection and coordination study;

 

                  (4)  Impact on system operation;

 

                  (5)  Stability study and the conditions that would justify including this element in the SIS; and

 

                  (6)  Voltage-collapse study and the conditions that would justify including this element in the SIS.

 

          (f)  The SIS shall consider the proposed facility’s design and operating characteristics and study the facility according to how the facility is proposed to be operated.  If the facility limits export or import pursuant to En 1013, the SIS shall use export capacity or import capacity instead of nameplate rating, except when assessing fault current contribution.

 

          (g)  The utility shall commence the SIS once an applicant submits an executed SISA and required payment for the SIS.  The SIS shall be completed within 55 business days of the applicant’s submission of the SISA and payment, unless the applicant and utility mutually agree to a different completion term.  The utility shall true up all SISA payments to reflect final, actual costs of the SIS once those costs are known.  The utility shall provide an SIS report that includes a description of the utility’s analysis, conclusions, and the reasoning supporting those conclusions.

 

          (h)  After the results of the SIS are delivered, if an applicant requests a meeting to discuss results within 10 business days, the utility shall conduct a results meeting with the applicant within 15 business days of providing the results to the applicant.  The results meeting shall take place in person, by telephone, or virtually.  The utility and the applicant shall bring to the results meeting personnel, including system engineers, and other resources as might be reasonably required to accomplish the purpose of the meeting.

 

          (i)  Within 10 business days after the results meeting or the applicant’s decision to waive the results meeting, the applicant shall notify the utility of its decision to proceed with the IA, if applicable, request a modification permitted pursuant to En 1004.04, or withdraw the application.  Failure of the applicant to notify the utility of its decision or request a modification shall result in the withdrawal of the application.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.07  Detailed Study.

 

          (a)  If the utility determines that necessary modifications to the utility’s EDS are substantial, the SIS report shall include a high-level estimate of the system modification costs and an estimate of the cost of an optional detailed study.  The optional detailed study shall provide granular costs of any EDS modifications necessary to interconnect the applicant’s proposed facility.

 

          (b)  If the applicant elects to participate in a group study pursuant to En 1012, the utility shall waive the detailed study.

 

          (c)  If the utility determines that EDS modifications required to accommodate the facility are not substantial, the SIS shall identify the scope and cost of the EDS modifications defined in the SIS results, and no detailed study shall be required.

 

          (d)  If the applicant elects to proceed with the detailed study, within 10 business days of the issuance of the SIS report, the utility shall provide a detailed study agreement, including a good faith estimate of the cost and time to complete the detailed study.

 

          (e)  The utility shall execute the detailed study once the applicant completes the detailed study agreement and submits payment.  The detailed study shall include a granular list of necessary EDS modifications, estimated milestones for completion of modifications, and a non-binding, itemized cost estimate detailing equipment, labor, operation and maintenance, contingencies, and other costs.

 

          (f)  The utility shall complete the detailed study within 30 business days of execution of the detailed study agreement and receipt of study payment if no substation upgrades are required.  If substation upgrades are required, the timeline for detailed study shall be established by mutual agreement.

 

          (g)  After the results of the detailed study are delivered, if an applicant requests a meeting to discuss the results within 10 business days, the utility shall conduct a results meeting with the applicant within 15 business days of providing the results to the applicant.  The results meeting shall take place in person, by telephone, or virtually.  The utility and the applicant shall bring to the results meeting personnel, including system engineers, and other resources as might be reasonably required to accomplish the purpose of the meeting.

 

          (h)  Within 10 business days after the results meeting or the applicant’s decision to waive the results meeting, the applicant shall notify the utility of its decision to proceed with the IA, if applicable, or request a modification  pursuant to En 1004.04, or withdraw the application.  Failure of the applicant to notify the utility of its decision or request a modification shall result in the withdrawal of the application.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.08  Interconnection Agreement

 

          (a)  Within 15 business days of completion of the last study or the meeting to discuss study results, whichever is later, the utility shall provide the applicant with a signed IA using the current standard agreement, which shall incorporate the milestones for completing EDS modifications, if any, from the detailed study.  The IA shall include a good faith, non-binding estimate of all costs associated with interconnection of the applicant’s proposed facility to the utility EDS including an itemized quote including contingencies.

 

          (b)  Within 15 business days of the receipt of the IA, the applicant shall either execute or provide comments on the IA and return it to the utility.  The utility shall have 15 business days to respond to any applicant IA comments.  Upon the applicant’s receipt of the utility’s responses, the applicant and utility shall attempt to resolve any issues identified by the applicant.  The applicant shall either execute the IA within 15 business days of the receipt of comments by the utility, or the applicant may initiate informal dispute resolution efforts pursuant to En 1016, or withdraw its IA at any time.

 

          (c)  Payment of 25 percent of the utility’s good faith, non-binding estimate shall be due within 45 business days of applicant signature of the IA with the remaining 75 percent due within 90 business days of applicant signature of the IA.  Nothing in this provision shall prevent the parties from establishing mutually agreed upon payment terms or the applicant making payment sooner than 45 business days to maintain queue position.

 

          (d)  If the applicant’s system modification costs exceed $500,000 or the estimated construction schedule for system modifications exceeds 2 years from the signed IA, the applicant shall be eligible for a payment plan.  This plan shall be included with the IA and shall include a payment and construction schedule with milestones for both the utility and the applicant that correlates to the schedule for payments with design, procurement, and construction of the EDS modifications.

 

          (e)  If the applicant fails to pay the utility within the timelines defined in (c) and (d) above in this section, the IA shall be deemed withdrawn, subject to the notice requirement of En 1014.02.

 

          (f)  Upon execution of the IA, the applicant shall notify the utility of the anticipated date the facility shall commence operations.  Unless the utility agrees to a later date or requires more time for necessary modifications to its EDS, the applicant shall identify an anticipated in-service date that is within 24 months of the applicant’s execution of the IA.  The utility and the applicant may mutually agree to an extension of this time if needed beyond the 24-month time period.

 

          (g)  The applicant shall notify the utility if there is any change in the anticipated in-service date of interconnected operations of the facility.

 

          (h)  The IA milestone schedule for system modifications shall commence upon the utility’s receipt of the applicant’s initial 25 percent payment.  The utility shall make its best efforts to adhere to the IA milestone schedule provided in the IA or detailed study.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.09  Witness Test Plan.  The applicant shall provide the utility with proposed witness test procedures and plans that comply with IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B and all requisite supporting documentation at least 30 business days before the anticipated in-service date.  Within 10 business days from receipt of the witness test plan, the utility shall notify the applicant whether the witness test plan complies with applicable industry and utility standards and if it complies, then the utility shall approve the witness test plan.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.10  Completeness and Compliance Review.  The utility shall review the completed facility as built for compliance with all applicable utility requirements and shall have the option to attend any required commissioning tests pursuant to the currently effective version of IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B.  The utility shall conduct the as-built review within 10 business days of receiving the notice of the anticipated in-service date at a time mutually agreeable to the interconnecting customer and utility.  If the facility passes the inspection, the utility shall provide written notice of such approval within 3 business days.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.11  Witness Test.

 

          (a)  Once the as-built review has been passed and the witness test plan has been approved, the utility shall schedule the witness test within 10 business days at a time mutually agreeable to the interconnecting customer and utility.

 

          (b)  If the facility initially fails the witness test, the utility shall offer to repeat the test at the interconnecting customer’s expense at a time mutually agreeable to the interconnecting customer and utility and repeat the test as many times as is necessary until the facility passes the witness test.

 

          (c)  If the utility determines that the facility fails the inspection, the utility shall provide a written explanation detailing the reasons and any standards violated.  Provided that any required commissioning tests are satisfactory, the utility shall grant PTO once the facility passes the witness test and all other requirements of the IA are satisfied.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1011.12  Operation.  Upon the utility’s receipt of proof of the electric code official’s approval, an interconnecting customer may begin interconnected operation of a facility, provided there is an IA in effect, the facility has passed any facility review and witness test that may be required by the utility, and the facility had received permission to operate.  Evidence of approval by an electric code official shall include a signed certificate of completion or other inspector-provided documentation.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1012  GROUP STUDY PROCESS

 

          En 1012.01  Eligibility.  An applicant shall be eligible to participate in a group study if the facility meets the criteria of En 1011.05 and once the application is deemed complete, or if the applicant and utility have not executed an IA and the utility determines that the facility is located in the common study area of another facility that has been assigned a later queue position and meets the criteria of En 1011.05.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.02  Group Study Notification.  If the applicant is eligible to participate in a group study, the utility shall notify the applicant within 20 business days after the utility notifies the applicant that the application is complete.  The utility shall notify the applicant of its eligibility to participate in a group study upon notification of eligibility to another applicant in the common study area.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.03  Group Window.  The utility shall identify all facilities eligible for inclusion in the group within 40 business days of the initial group study notification.  The utility may include additional facilities in the group after closing the group window with approval from the applicant and other applicants eligible for the group study.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.04  Public Availability.

 

          (a)  Once the utility has notified the applicant of eligibility to participate in a group study the utility shall publish on its website the following:

 

                  (1)  The name of the group;

 

                  (2)  The number of projects in the group;

 

                  (3)  The application identification and export capacity of each project in the group;

 

                  (4)  The relevant substation for the group, the deadline for group formation, and date of execution of group study agreement; and

 

                  (5)  Date of completion of group study.

 

          (b)  Any facility that is eligible for the group study shall be included on the utility’s website within 10 business days.  The utility shall update this information monthly.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.05  Scoping Meeting.

 

          (a)  The purpose of the scoping meeting shall be to discuss the application, the group, and review existing studies relevant to the application.  At the scoping meeting, the utility shall provide pertinent information such as aggregate export capacity of all other facilities in the common study area, thermal limits of the substation transformer and distribution feeders, quantity of applications and aggregate export capacity of the facilities in the group, whether a substation transformer will need to be upgraded, and whether there are any additional system modification anticipated.

 

          (b)  The utility shall conduct a scoping meeting with all group members with facilities in the common study area within 20 business days of the close of the group window.

 

          (c)  The scoping meeting shall take place in person, by telephone, or electronically by a means mutually agreeable to the parties.

 

          (d)  The utility and the applicant shall bring to the meeting personnel, including system engineers, and other resources as might be reasonably required to accomplish the purpose of the meeting.

 

          (e)  By mutual agreement of the parties, the scoping meeting may be waived.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.06  Group Study Election.  The applicant shall notify the utility of its election to participate in the group study within 10 business days of completion of the scoping meeting.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.07  Extended Group Study Election.

 

          (a)  The utility shall provide the applicant with an extended group study consent form within 12 business days of completion of the scoping meeting.

 

          (b)  The applicant shall provide an executed extended group study consent form within 10 business days of receiving the consent form from the utility.

 

          (c)  The applicant shall be eligible for an extended group study if all remaining facilities in the group submit an executed extended group study consent form to the utility.

 

          (d)  If the applicant is deemed eligible for an extended group study, the utility shall produce a non-binding estimate for the cost of system modifications.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.08  Group Study Agreement.  The utility shall provide the applicant with a group study agreement and an estimated cost for the group study within 25 business days of completion of the scoping meeting.  The applicant shall submit an executed group study agreement to the utility and pay the utility pursuant to the term of that agreement within 15 business days of receipt of such agreement.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.09  Group Study Fee.  Each applicant participating in a group study shall be responsible for its pro rata portion of the group study fee based on the export capacity of each applicant’s facility as a percentage of the total export capacity of all facilities in the group.  Should one or more individual applicants of a group withdraw from the group either during the group study or after the group study has been completed and as a result of any such withdrawal, the utility shall revise or modify the group study or restudy the group impact on the distribution system, each of the remaining applicants in the group shall be responsible for its pro rata portion of the cost to revise or modify the existing group study or restudy based on the export capacity of each applicant’s facility as a percentage of the total export capacity of all remaining facilities in the group.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.10  Timelines.

 

          (a)  For a group of DERs with no more than 3 applicants, an aggregated nameplate capacity of 10 MW or less, and estimated aggregate system modifications less than $1,500,000, the utility shall complete the group study within 100 business days of the applicants’ delivery of the executed group study agreements.

 

          (b)  For a group of DERs with no more than 5 applicants, an aggregated nameplate capacity of 25 MW or less, and estimated aggregate system modifications less than $1,500,000, the utility shall complete the group study within 125 business days of the applicants’ delivery of the executed group study agreements.

 

          (c)  For all other groups of DERs the utility shall complete the group study within 160 business days of the applicants’ delivery of the executed group study agreements.

 

          (d)  The utility shall be provided with an additional 60 business days to complete the group study if substation upgrades are required.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.11  Facility Operating Characteristics.  The group study shall take into account the proposed facilities’ design and operating characteristics and study the facilities according to how the facilities are proposed to be operated.  If the facilities limit export pursuant to En 1013, the group study shall use export capacity instead of nameplate rating, except when assessing fault current contribution.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.12  Group Study Results.  The group study results provided to the applicant shall include a description of the utility’s analysis, conclusions, and the reasoning supporting those conclusions and include a non-binding estimate of the cost of the system modifications.  The utility shall use its best efforts to ensure the estimate is within +/- 25 percent of final costs for a group study or +/- 15 percent of final costs for an extended group study.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.13  Group Study Results Meeting.  The utility shall conduct a meeting to discuss the group study results with the applicant and all other applicants with facilities in the common study area within 20 business days of providing the group study results to the applicant.  The group study results meeting shall:

 

          (a)  Take place in person, by telephone, or virtually;

 

          (b)  The utility and the applicant shall bring to the meeting personnel, including system engineers, and other resources as might be reasonably required to accomplish the purpose of the meeting; and

 

          (c)  By mutual agreement of the parties, the group study results meeting may be waived.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.14  Group Member Cost Responsibilities.  The applicant shall be responsible for the pro rata portion of the common system modifications identified in the group study based on export capacity of the facility and total export capacity of the group.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1012.15  IA, Inspection, and Operation.  Upon the completion of the group study:

 

          (a)  The utility shall issue an IA in accordance with En 1011.08;

 

          (b)  The applicant shall satisfy witness test procedures consistent with En 1011.09;

 

          (c)  The utility shall conduct an inspection consistent with En 1011.10 and 1011.11; and

 

          (d)  The facility shall begin operation in accordance with En 1011.12.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1013  LIMITED-EXPORT, LIMITED-IMPORT, AND NON-EXPORTING FACILITIES

 

          En 1013.01  Export Capacity.  If a facility uses any configuration or operating mode pursuant to En 1013.03 to limit the export or import of electrical power across the PCC, then the import capacity or export capacity shall be only the amount capable of being imported or exported, excluding any inadvertent export.  To prevent impacts on system safety and reliability, any inadvertent import and export from a facility shall comply with the limits identified in this section.  The export capacity or import capacity specified by the applicant in the application shall subsequently be included as a limitation in the IA.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1013.02  Control and Protection Settings.  An application proposing to use a configuration or operating mode to limit the export or import of electrical power across the PCC shall include proposed control or protection settings.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1013.03  Acceptable Methods.  Acceptable methods of export limitation or import limitation shall include:

 

          (a)  Limitation methods for non-exporting facilities as follows:

 

                  (1)  For reverse power protection (Device 32R), to limit export of power across the PCC, a reverse power protective function shall be implemented using a utility-grade protective relay.  The default setting for this protective function shall be 0.1 percent (export) of the service transformer’s nominal base nameplate rating, with a maximum 2.0 second time delay to limit inadvertent export;

 

                  (2)  For minimum power protection (Device 32F), to limit import or export of power across the PCC, a minimum import protective function shall be implemented using a utility-grade protective relay.  The default setting for this protective function shall be 5 percent (import) of the facility’s total nameplate rating, with a maximum 2.0 second time delay to limit inadvertent export; and

 

                  (3)  For the relative distributed energy resource rating option, the facility’s nameplate rating shall be sufficiently small relative to the host facility’s minimum load such that no additional protective functions are required to prevent export to the electric delivery system.  To qualify, the facility’s nameplate rating shall not exceed 50 percent of the applicant’s verifiable minimum host load over the preceding 12 months.  This option is not permitted for interconnections to area networks or spot networks;

 

          (b)  Limitation methods for limited-export or limited-import facilities as follows:

 

                  (1)  For directional power protection (Device 32), to limit export or import of power across the PCC, a directional power protective function shall be implemented using a utility-grade protective relay.  The default setting for this protective function shall be the export/import capacity value, with a maximum 2.0 second time delay to limit inadvertent export/import; and

 

                  (2)  For configured power rating, a reduced output rating utilizing the power rating configuration setting may be used to ensure the facility does not generate power beyond a certain value lower than the nameplate rating.  The configuration setting corresponds to the active or apparent power ratings in Table 28 of IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018, as available in Appendix B.  A local facility communication interface is not required to utilize the configuration setting as long as it can be set by other certified means.  The reduced power rating may be indicated by means of a nameplate rating replacement, or a supplemental adhesive de-rating tag to indicate the reduced power rating.  This method shall be certified in accordance with IEEE Std 1547.1™-2020, “IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces” dated 5/21/2020 as available in Appendix B.  Use of a configured power rating not applied to individual generator(s) shall require evaluation under mutually agreed upon means; and

 

          (c)  Limitation methods for non-exporting facilities, limited-export facilities, non-importing facilities, or limited-import facilities as follows:

 

                  (1)  For certified power control systems, a facility may use certified PCSs to limit export or import.  A facility utilizing this option shall use a PCS and an inverter certified per UL 1741, “Standard for Inverters, Converters, Controllers with Interconnection System Equipment for Use with Distributed Energy Resources” dated 4/22/2025 as available in Appendix B, by a NRTL with a maximum open loop response time of no more than 30 seconds to limit inadvertent export or inadvertent import.  This option shall not be available for interconnections to area networks or spot networks; and

 

                  (2)  For agreed-upon means, a facility may be designed with other control systems or protective functions to limit export, inadvertent export, import, or inadvertent import if mutual agreement is reached with the utility.  The limits may be based on technical limitations of the interconnection customer’s equipment or the electric delivery system equipment.  To ensure inadvertent export or inadvertent import remains within mutually agreed-upon limits, the interconnection customer may use an uncertified power control system, an internal transfer relay, energy management system, or other customer facility hardware or software if approved by the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1014  TIMELINES AND EXTENSIONS

 

          En 1014.01  Utility Deadlines.  The utility shall make reasonable efforts to meet all timelines set by the interconnection procedures.  If the utility cannot meet a timeline, the utility shall attempt to notify the applicant in writing in advance of the deadline but in any event no less than one business day after the missed deadline.  The notification shall explain the reason for the utility’s failure to meet the deadline and provide an estimate of when the step will be completed.  The utility shall keep the applicant updated of any changes in the expected completion date.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1014.02  Applicant Deadlines.

 

          (a)  An applicant may make a request to seek extension of a deadline of the interconnection procedures.  Such request shall be in writing.

 

          (b)  The utility shall grant an extension request if the applicant demonstrates sufficient justification for the additional extension and the extension duration is reasonable and does not unreasonably delay applications behind the applicant seeking the extension in the queue.

 

          (c)  For any missed deadline that would result in an application’s removal from its current queue position, the utility shall notify the applicant a minimum of 8 business days prior to the application being removed from its queue position.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1015  ONLINE APPLICATIONS AND ELECTRONIC SIGNATURES

 

          En 1015.01  Electronic Submission.  Each utility shall require electronic applications to be submitted via email or through other electronic means acceptable to the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1015.02  Utility Website Posting.  Each utility shall post this chapter to a well-identified page within the utility’s website.  The relevant website page shall include:

 

          (a)  This chapter in an electronically searchable format;

 

          (b)  The utility’s standard forms; and

 

          (c)  The utility’s point of contact for submission of applications including email address and phone number.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1015.03  Electronic Signatures for Interconnection Applications and Agreements.  Each utility shall allow electronic signatures to be used for interconnection applications and agreements.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1016  DISPUTE RESOLUTION

 

          En 1016.01  Informal Dispute Resolution Efforts Required.

 

          (a)  In the event of a dispute regarding any issue arising under this chapter, the utility and the applicant shall make a good faith effort to first resolve the dispute through informal means.

 

          (b)  If the efforts of informal dispute resolution are unsuccessful, the applicant may make a formal complaint with the department pursuant to RSA 365:1-4.

 

          (c)  Informal dispute resolution efforts shall not suspend, extend, or delay any timeframes or deadlines applicable to the application(s) at issue, except upon mutual agreement by the utility and the applicant(s).

 

          (d)  All timelines and deadlines shall remain in place and enforceable, including all consequences of violating the applicable timeline or deadline, which may be addressed in the informal dispute resolution process or brought as a formal complaint to the department.

 

          (e)  If a timeline or deadline is part of a good-faith dispute or will be materially impacted as a consequence of a good-faith dispute, the utility and the applicant shall make their best-faith efforts to accommodate modifications to the relevant timelines or deadlines.

 

          (f)  No application shall be deemed withdrawn or removed from the queue solely because of a missed deadline that is associated with or results from a good-faith dispute undergoing the process of this section.

 

          (g)  An applicant’s execution of an IA or payment for system modifications in accordance with applicable deadlines shall not preclude the applicant from disputing any system modification or associated cost required under the IA.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1016.02  Notice of Grievance.  When a dispute occurs that is not resolved through informal conversation, the party with the grievance shall notify the other party of the dispute in writing with a description of the nature of the dispute and relevant facts, the provisions of this chapter believed to be at issue, and desired outcome.  The receiving party shall acknowledge the notification, identify a representative with the authority to resolve the dispute, and commence good faith efforts to resolve the dispute within 10 business days.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1016.03  Grievance Resolution Process.  If a resolution is not reached in 10 business days from the date of the notice of dispute, the following shall be available:

 

          (a)  A party may request in writing to continue negotiations for an additional 25 business days;

 

          (b)  The applicant may file an informal complaint with the department’s consumer services division and request a conference to attempt to resolve the dispute; and

 

          (c)  Within 10 business days of a request for continued negotiations or within 10 business days of the conference referenced in (b) above in this section, the applicant and the utility shall each provide a written description of technical and regulatory details relevant to the dispute.  Nothing shall prevent the parties from continuing informal negotiations if a department-attended conference is requested.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1017  UTILITY REPORTING REQUIREMENT

 

          En 1017.01  Annual Report Reporting Period.  Each utility shall provide to the department an annual report by April 1 of each year.  The reporting period for all information required by this part shall be for the most recent past calendar year.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1017.02  Annual Report Required Information Contained in the Pre-Application Reports.  The annual report shall include the following data submitted as part of the pre-application reports:

 

          (a)  Total number of reports requested;

 

          (b)  Total number of reports in process;

 

          (c)  Total number of reports issued; and

 

          (d)  Average net utility processing times from receipt of request to issuance of report.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1017.03  Annual Report Required Information Regarding Interconnection Applications.  The annual report shall include the following data regarding interconnection applications:

 

          (a)  Total number of simplified process applications submitted in the reporting period as follows:

 

                  (1)  Total average processing time from complete application to contingent approval for applications completed in the reporting year;

 

                  (2)  Average net utility processing time from receipt of complete simplified process application to initial utility approval or contingent approval for applications completed in the reporting year; and

 

                  (3)  Average customer hold time for applications completed in the reporting year; and

 

          (b)  Total number of fast track process applications submitted in the reporting period as follows:

 

                  (1)  Total average processing time from complete application to contingent approval for applications completed in the reporting year;

 

                  (2)  Average net utility processing time from receipt of complete fast track process applications to provision of contingent approval for applications that received contingent approval during the reporting period; and

 

                  (3)  Average customer hold time for applications completed in the reporting year.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

PART En 1018  MISCELLANEOUS REQUIREMENTS

 

          En 1018.01  Approvals.  The applicant shall be responsible for construction of the facility and obtaining any necessary local code official approvals such as electrical and zoning approval.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.02  Commissioning Test.  The applicant shall conduct the commissioning test pursuant to the IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B, and comply with all manufacturer requirements when conducting the commissioning test.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.03  Utility Designee.  To assist applicants in the interconnection process, the utility shall designate an employee or office from which basic information on interconnections can be obtained.  Upon request, the utility shall provide interested applicants with all relevant forms, documents, and technical requirements for filing a complete application.  Upon an applicant’s request, the utility shall meet with an applicant at the utility’s offices, by telephone, or via video meeting prior to submission for up to one hour for simplified process applicants and 2 hours for other applicants.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.04  Additional Controls.  A utility shall not be permitted to require an applicant to install, at a cost to the applicant, any additional controls or perform additional tests beyond those included in the interconnection agreement to obtain approval to interconnect.  The utility shall be permitted, at a cost to the applicant, to require the installation of controls necessary for safety and reliability that the utility could not have known about at the time the interconnection agreement was executed.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.05  Insurance Thresholds.  A utility shall require an applicant to purchase insurance covering utility damages as follows:

 

          (a)  For non-inverter-based facilities, the following:

 

                          Insurance Thresholds For Non-Inverter-Based Facilities

 

Nameplate Rating > 5 MW

$5,000,000

1 MW < Nameplate Rating < 5 MW

$2,000,000

100 kW < Nameplate Rating < 1 MW

$1,000,000

10 kW < Nameplate Rating < 100 kW

$500,000

Nameplate Rating < 10 kW

Typical Homeowners

 

          (b)  For inverter-based facilities, the following:

 

                          Insurance Thresholds For Inverter-Based Facilities

 

Nameplate Rating > 5 MW

$2,000,000

MW < Nameplate Rating < 5 MW

$1,000,000

Nameplate Rating < 1 MW

No insurance

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.06  Additional Equipment.  Additional protection equipment not included with the interconnection equipment package may be required at the utility’s discretion as long as the operational performance of an applicant’s DER is not negatively impacted and the applicant is not charged for any equipment that provides protection that is already identified in the approved interconnection equipment.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.07  Metering.  Metering and monitoring shall be as set forth in En 300, utility tariffs, the IA, when applicable, and additional applicable utility resources.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.08  Telemetry.  Requirements for telemetry shall be consistent with the utility’s TIR as defined in En 1002.53.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.09  Operational Testing.  Once an interconnection has been approved under this chapter, a utility shall not require an interconnection customer to test its facility except that the utility may require any manufacturer-recommended testing and:

 

          (a)  For the fast track process, the utility may require periodic testing to verify adherence to the interconnection requirements.  The frequency of periodic testing shall be specified in the utility’s interconnection handbook or other appropriate documentation;

 

          (b)  For the standard process, all interconnection-related protective functions and associated batteries shall be periodically tested at intervals specified by the manufacturer, system integrator, or authority having jurisdiction over the interconnection.  Periodic test reports or a log for inspection shall be maintained; and

 

          (c)  For functional software or firmware changes, hardware changes, protection settings, or function changes, or changes to operating modes, the utility may require retesting to ensure the facility still meets the requirements of IEEE Std 1547™-2018, “IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces” dated 4/6/2018 as available in Appendix B.  When required, the updated facility configuration and testing results shall be documented and submitted to the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.10  Utility Right to Inspect.  A utility shall have the right to inspect an interconnecting customer’s facility before and after interconnection approval is granted during normal business hours with prior written notice provided to the interconnection customer no less than one week before the scheduled inspection.  In the event of an emergency, no such notice is necessary.  If the utility discovers an interconnecting customer’s facility is not in compliance with the operating requirements of the IA or applicable standards, and the non-compliance adversely affects the safety or reliability of the electric system, the utility may require disconnection of the interconnecting customer’s facility until the facility complies with the operating requirements of the IA or applicable standards.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.11  Cost Reconciliation.

 

          (a)  The utility shall, only upon request by the applicant, true up estimates for all, studies and EDS modifications for project applications with substantial modifications to reflect actual costs either through refunding or invoicing the applicant for the difference within 240 business days of PTO or of termination of the IA if the termination of the IA occurs prior to PTO.  Invoices provided to the applicant shall be accompanied by a final accounting report that provides a detailed breakdown of costs.  That cost breakdown shall match, at minimum, the level of detail of the estimate provided to the applicant.

 

          (b)  An applicant may request a final accounting report of any difference between:

 

                  (1)  The actual costs of the studies and upgrades; and

 

                  (2)  The applicant’s previous aggregate payments to the utility for studies and upgrades within 120 business days after PTO or within 120 business days of the termination of the IA if the termination of the IA occurs prior to PTO.

 

          (c)  Upon receipt of a request for a final accounting report from an applicant, the utility shall have 120 business days to provide the requested final accounting report to the applicant as follows:

 

                  (1)  If the funds spent or committed by the utility exceeds the applicant’s previous aggregate payments, the utility shall invoice the applicant, and the applicant shall provide full payment to the utility within 45 business days;

 

                  (2)  If the applicant’s previous aggregate payments exceed the funds spent or committed by the utility, the utility shall refund to the applicant an amount equal to the difference within 45 business days; and

 

                  (3)  Failure by the applicant to pay undisputed amounts within the required timeframe authorizes the utility to disconnect the facility from the EDS any time after the lapsed deadline.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.12  Voluntary Disconnection.  The interconnecting customer may disconnect the facility at any time without prior notice to the utility and may terminate the IA at any time with 10 days notice to the utility.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.13  Designated Representative.  An applicant may designate a representative to process an application on applicant’s behalf, and an interconnection customer may designate a representative to meet some or all of the interconnection customer’s responsibilities under the IA.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.14  Assignment.  Nothing in this chapter shall prohibit the interconnecting customer from assigning its ownership of the facility as well as all rights and obligations under the IA to a successor owner or occupant of the facility site.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 

          En 1018.15  Energy Storage.

 

          (a)  If the applicant is seeking approval for an energy storage device, that is co-located with load, other than station service load, pursuant to an application governed by this chapter, the utility shall not require a separate and additional request for new service for the interconnection of new or modified load.  The utility shall review the co-located energy storage device pursuant to the processes in this chapter and not pursuant to En 300.

 

          (b)  If the applicant is seeking approval for an energy storage device not co-located with load, other than station service load, the utility shall apply the interconnection requirements established in the utility TIR.

 

          (c)  Energy storage devices shall be screened or studied according to the proposed facility’s design and operating characteristics.  If the facility limits export or import pursuant to En 1013, screening or study of the device shall use export capacity or import capacity instead of nameplate rating, except when assessing fault current contribution.

 

Source.  #14657, eff 9-1-26, EXPIRES: 9-1-36

 


 

APPENDIX A

 

Rule(s)

Statute

En 1001

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1002

RSA 12-P:5, IV; RSA 362-A:1; RSA 362-A:9; RSA 374-F:2, VII-VIII; Laws 2024, ch. 287

En 1003

RSA 12-P:5, IV; Laws 2024, ch. 287

En 1004

RSA 12-P:5, IV; RSA 362-A:9; RSA 378:3; Laws 2024, ch. 287

En 1005 - En 1007

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1008.01 - En 1008.05

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1008.06

RSA 12-P:5, IV; RSA 362-A:9, X(a); RSA 362-A:9, XIII; Laws 2024, ch. 287

En 1008.07 - En 1008.10

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1009 - En 1010

RSA 12-P:5, IV; RSA 362-A:9, X(a); RSA 374:2; Laws 2024, ch. 287

En 1011.01

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1011.02

RSA 12-P:5, IV; RSA 362-A:9, X(a); RSA 362-A:9, XIII; Laws 2024, ch. 287

En 1011.03 – En 1012.08

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1012.09

RSA 12-P:5, IV; RSA 362-A:9, X(a); RSA 362-A:9, XIII; Laws 2024, ch. 287

En 1012.10 – En 1012.13

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1012.14

RSA 12-P:5, IV; RSA 362-A:9, X(a); RSA 362-A:9, XIII; Laws 2024, ch. 287

En 1013

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1014

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1015

RSA 12-P:5, IV; RSA 362-A:9, X(a); Laws 2024, ch. 287

En 1016

RSA 12-P:5, IV; RSA 365:1-4; Laws 2024, ch. 287

En 1017

RSA 12-P:5, IV; Laws 2024, ch. 287

En 1018

RSA 12-P:5, IV; RSA 362-A:9, XIII; RSA 362-A:1; Laws 2024, ch. 287

 


 

APPENDIX B: INCORPORATION BY REFERENCE INFORMATION

 

Rule

Title (date)

Source

En 1002.09,

En 1002.50,

En 1005.01(a),

En 1009.03(b)(2),

En 1009.03(b)(3),

En 1011.06(d),

En 1011.09,

En 1011.10,

En 1013.03(b)(2),

En 1018.02,

En 1018.09(c)

IEEE Std 1547™-2018 - IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power System Interfaces, dated 4/6/2018

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-1547-2018?product_id=1983168 for

$172.00 PDF

$215.00 Printed Edition

$271.00 Printed Edition and PDF

En 1002.09,

En 1005.01(b),

En 1013.03(b)(2)

IEEE Std 1547.1™-2020 - IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces, dated 5/21/2020

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-1547-1-2020?product_id=2045401 for

$225.00 PDF

$281.00 Printed Edition

$350.00 Printed Edition and PDF

En 1005.01(d)

IEEE Std 1547.2™-2023 – IEEE Application Guide for IEEE Std 1547™-2018, IEEE Standard for Interconnection and Interoperabililty of Distributed Energy Resources with Associated Electric Power Systems Interfaces, dated 5/20/2024

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-1547-2-2023?product_id=2248838 for

$207.00 PDF

$258.00 Printed Edition

$287.00 Printed Edition and PDF

En 1005.01(e)

IEEE Std 1547.3™-2023 – IEEE Guide for Cybersecurity of Distributed Energy Resources Interconnected with Electric Power Systems, dated 12/11/2023

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-1547-3-2023?product_id=2251331 for

$182.00 PDF

$226.00 Printed Edition

$239.00 Printed Edition and PDF

En 1005.01(f)

IEEE Std 1547.7™-2013 – IEEE Guide for Conducting Distribution Impact Studies for Distributed Resource Interconnection, dated 2/28/2014

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-1547-7-2013?product_id=1862590 for

$219.00 PDF

En 1005.01(g)

IEEE Std 519™-2022 – IEEE Standard for Harmonic Control in Electric Power Systems, dated 8/5/2022

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-519-2022?product_id=2241406 for

63.00 PDF

$79.00 Printed Edition

$84.00 Printed Edition and PDF

En 1005.01(h)

IEEE Std 1453™-2022 – IEEE Standard for Measurement and Limits of Voltage Fluctuations and Associated Light Flicker on AC Power Systems, dated 2/27/2023

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-1453-2022?product_id=2222855 for

$106.00 PDF

$132.00 Printed Edition

$140.00 Printed Edition and PDF

En 1005.01(i)

IEEE Std C37.90.2™-2024 - IEEE Standard for Relays, Relay Systems, and Control Devices used for Protection and Control of Electric Power Apparatus-Radiated Electromagnetic Interference Withstand Capability Requirements and Tests, dated 1/31/2025

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-c37-90-2-2024?product_id=2252274 for

$60.00 PDF

$75.00 Printed Edition

$87.00 Printed Edition and PDF

En 1005.01(j)

IEEE Std C37.95™-2014 - IEEE Guide for Protective Relaying of Utility-Consumer Interconnections, dated 5/5/2014

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-c37-95-2014?product_id=1861236 for

$119.00 PDF

En 1005.01(k)

IEEE Std C50.13™-2014 - IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous Generators Rated 10 MVA and Above, dated 5/9/2014

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-c50-13-2014?product_id=1877051 for

$119.00 PDF

En 1005.01(l)

IEEE Std C62.92.1™-2016 - IEEE Guide for the Application of Neutral Grounding in Electrical Utility Systems-Part I: Introduction, dated 3/31/2017

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-c62-92-1-2016?product_id=1909813 for

$71.00 Self-Extracting File Format

$87.00 Printed Edition

$92.00 Printed Edition and PDF

En 1005.01(m)

IEEE Std C62.92.2™-2017 - IEEE Guide for the Application of Neutral Grounding in Electrical Utility Systems, Part II-Synchronous Generator Systems, dated 5/19/2017

Institute of Electrical and Electronic Engineers, Inc.,445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-c62-92-2-2017?product_id=1915830 for

$71.00 PDF

$87.00 Printed Edition

$109.00 Printed Edition and PDF

En 1005.01(n)

IEEE Std C62.92.6™-2017 - IEEE Guide for Application of Neutral Grounding in Electrical Utility Systems, Part VI-Systems Supplied by Current-Regulated Sources, dated 12/22/2017

Institute of Electrical and Electronic Engineers, Inc., 445 Hoes Lane, Piscataway, NJ 08854

Available for purchase at:

https://store.accuristech.com/standards/ieee-c62-92-6-2017?product_id=1949133 for

$71.00 PDF

$87.00 Printed Edition

$92.00 Printed Edition and PDF

En 1002.09,

En 1005.01(o),

En 1005.01(p),

En 1007.03(a),

En 1013.03(c)(1)

UL 1741 - Inverters, Converters, Controllers and Interconnection System Equipment for Use with Distributed Energy Resources, dated 4/22/2025

Underwriters Laboratories, Inc., 333 Pfingsten Road, Northbrook, IL 60062

Standard 1741, Edition 3

Edition Date: September 28, 2021

Includes Supplement SB

Available for purchase at: https://www.shopulstandards.com/ProductDetail.aspx?productId=UL1741_3_S_20210928 for

$798.00 Secure PDF (Read Only)

$998.00 Secure PDF and Hardcopy Combo

$998 Premium Hardcopy

En 1005.01(q)

UL 3141 - UL LLC Outline of Investigation for Power Control Systems, dated 10/9/2024

Underwriters Laboratories, Inc., 333 Pfingsten Road, Northbrook, IL 60062

Standard 3141, Edition 1

Edition Date: December 6, 2024

Available for purchase at: https://www.shopulstandards.com/ProductDetail.aspx?productId=UL3141_2_O_20241009 for

$225.00 Secure PDF

$250.00 Secure PDF and Hardcopy Combo

$250.00 Premium Hardcopy

En 1005.01(c)

ANSI C84.1-2020 - Electric Power Systems and Equipment - Voltage Ratings (60 Hertz), dated 3/10/2020

American National Standards Institute, 1899 L Street, NW, 11th Floor, Washington, DC 20036

Standard C84.1, 2020 Edition

Edition Date: March 10, 2020

Available for purchase at: https://webstore.ansi.org/search/find?in=1&st=ANSI+C84.1-2020 for

$179.00 PDF

$198.32 Stapled Hardcopy

$201.54 Spiral Hardcopy

$205.84 Binder Hardcopy