HB 429 - AS INTRODUCED

2003 SESSION

03-0552

08/09

HOUSE BILL 429

AN ACT relative to processing excavating and dredging permits.

SPONSORS: Rep. Camm, Rock 79

COMMITTEE: Resources, Recreation and Development

ANALYSIS

This bill provides specific time limits for processing excavation and dredging permits.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Explanation: Matter added to current law appears in bold italics.

Matter removed from current law appears [in brackets and struckthrough.]

Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.

03-0552

08/09

STATE OF NEW HAMPSHIRE

In the Year of Our Lord Two Thousand Three

AN ACT relative to processing excavating and dredging permits.

Be it Enacted by the Senate and House of Representatives in General Court convened:

1 New Paragraph; Excavating and Dredging; Certain Exemptions. Amend RSA 482-A:3 by inserting after paragraph XIII the following new paragraph:

XIV. In processing an application, petition, or request for permits under this chapter in which a response is specifically addressed to the applicant, petitioner, or requester, the department shall:

(a) Within 30 days of receipt, examine the application, petition, or request, notify the applicant of any apparent error or omission, request any additional information that the department is permitted by law to require, and notify the applicant of the name, official title, address, and telephone number of a department official or employee who may be contacted regarding the application.

(b) Within a reasonable time, not to exceed 60 days, after receipt of a minimum impact application or a minor application, petition, or request, or the receipt of a timely request made by the department pursuant to subparagraph (a), the department shall:

(1) Approve or deny the application, in whole or in part, on the basis of non-adjudicative processes, if use of these processes is not precluded by any provision of law; or

(2) Commence an adjudicative proceeding in accordance with this chapter.

(c) Within a reasonable time, not to exceed 60 days, after receipt of a major application, petition, or request, or the receipt of a timely request made by the department pursuant to subparagraph (a), the department shall:

(1) Approve or deny the application, in whole or in part, on the basis of non-adjudicative processes, if use of these processes is not precluded by any provision of law; or

(2) Commence an adjudicative proceeding in accordance with this chapter.

(d) The time limits prescribed by this paragraph shall supersede any time limits provided in any other provision of law. If the department fails to render a decision within the time frames provided in this paragraph, the application shall be deemed to be approved.

2 Effective Date. This act shall take effect 60 days after its passage.