AN ACT relative to processing excavating and dredging and terrain alteration permits, changing the fees for permits, establishing 2 new positions, and making an appropriation therefor.

SPONSORS: Rep. Dickinson, Carr 4; Rep. Babson, Carr 6; Rep. Spang, Straf 72; Rep. Phinizy, Sull 23; Rep. R. Cooney, Rock 76; Sen. Gallus, Dist 1; Sen. Kenney, Dist 3

COMMITTEE: Resources, Recreation and Development

AMENDED ANALYSIS

I. Establishes time limits for the department of environmental services to process excavating and dredging permits.

II. Increases fees for certain permits.

III. Requires a report to the wetlands council.

IV. Establishes 2 new civil engineer positions.

V. Makes an appropriation for the new positions.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Explanation: Matter added to current law appears in bold italics.

Matter removed from current law appears [in brackets and struckthrough.]

Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.

12mar03... 0560h

10apr03... 1052h

03-0852

06/10

STATE OF NEW HAMPSHIRE

In the Year of Our Lord Two Thousand Three

AN ACT relative to processing excavating and dredging and terrain alteration permits, changing the fees for permits, establishing 2 new positions, and making an appropriation therefor.

Be it Enacted by the Senate and House of Representatives in General Court convened:

224:1 New Paragraph; Excavating and Dredging; Certain Exemptions. Amend RSA 482-A:3 by inserting after paragraph XIII the following new paragraph:

XIV. In processing an application for permits under this chapter, except for a permit by notification, the department shall:

(a) Within 14 days of receipt by the department, issue a notice of administrative completeness or send notice to the applicant, the address provided on the application, identifying any additional information required to make the application administratively complete and providing the applicant with the name and telephone number of the department employee who may be contacted regarding the application. Each receipt of additional information in response to any notice shall re-commence the 14-day period until the department issues a notice of administrative completeness.

(b) Within 75 days of the issuance of a notice of administrative completeness for projects where the applicant proposes under one acre of jurisdictional impact and 105 days for all other projects, request any additional information that the department is permitted by law to require to complete its evaluation of the application, together with any written technical comments the department deems necessary. Any request for additional information shall specify that the applicant submit such information as soon as practicable and shall notify the applicant that if the requested information is not received within 120 days of the request, the department shall deny the application.

(c) Where the department requests additional information pursuant to subparagraph (b), the department shall, within 30 days of the department's receipt of the information:

(1) Approve or deny the application, in whole or in part; or

(2) Commence a non-adjudicative proceeding in accordance with this chapter and rules adopted by the commissioner; or

(3) Extend the time for response for good cause and with the written agreement of the applicant.

(d) Where no request for additional information is made pursuant to subparagraph (b), the department shall, within 75 days from the issuance of the notice of administrative completeness, or 105 days if the application proposes more than one acre of jurisdictional impact:

(1) Approve or deny the application, in whole or in part; or

(2) Commence a non-adjudicative proceeding in accordance with this chapter and rules adopted by the commissioner.

(e) Where the department has commenced a non-adjudicative hearing on an application filed under this chapter, the department shall, within 60 days following the closure of the hearing record, approve or deny the application either in whole or in part.

(f) The time limits prescribed by this paragraph shall supersede any time limits provided in any other provision of law. If the department fails to issue a notice of administrative completeness or render any other decision within the time limits provided in this paragraph, the application shall be deemed to be approved.

(g) The time limits prescribed by this paragraph shall not apply to an application where the applicant has been adjudicated after final appeal, or otherwise does not contest, the department's designation as a chronic non-complier in accordance with rules adopted pursuant to this chapter.

224:2 Excavating and Dredging Permits; Fee Changes. RSA 482-A:3, I is repealed and reenacted to read as follows:

I. No person shall excavate, remove, fill, dredge or construct any structures in or on any bank, flat, marsh, or swamp in and adjacent to any waters of the state without a permit from the department. The permit application together with a detailed plan and a map showing the exact location of the proposed project, along with 4 copies of the permit application, plan and map, shall be submitted to the town or city clerk, accompanied by a filing fee in the form of a check made out by the applicant to the state of New Hampshire. The permit application fee shall be $100 for minimum impact projects under this chapter. The permit application fee for minor and major shoreline structure projects shall be $100 plus an impact fee, based on the area of dredge, fill, or dock surface area proposed, or a combination. The shoreline structure impact fee shall be $1 per square foot for permanent dock surface area; $.50 per square foot for seasonal dock surface area; and $.10 per square foot for dredge or fill surface area or both. The permit application fees for minor or major projects shall be $.10 per square foot of proposed impact for all other projects under this chapter. For projects involving the repair, reconstruction, or reconfiguration of an existing docking structure, the application fee shall be $100. At the time the permit application is submitted to the city or town clerk, the applicant shall provide postal receipts or copies, verifying that abutters, as defined in the rules of the department, and except as further provided in said rules, have been notified by certified mail. The postal receipts or copies shall be retained by the municipality. The town or city clerk shall immediately sign the application and forward by certified mail, the application, plan, map and filing fee to the department. The town or city clerk shall then immediately send a copy of the permit application, plan and map to the local governing body, the municipal planning board, if any, and the municipal conservation commission, if any, and may require an administrative fee not to exceed $10 plus the cost of postage by certified mail. One copy shall remain with the city or town clerk, and shall be made reasonably accessible to the public. The foregoing procedure notwithstanding, applications and fees for projects by agencies of the state may be filed directly with the department, with 4 copies of the application, plan and map filed at the same time with the town or city clerk to be distributed as set forth above.

224:3 Excavating and Dredging Permits; Fee Changes. Amend RSA 482-A:3, I to read as follows:

I. No person shall excavate, remove, fill, dredge or construct any structures in or on any bank, flat, marsh, or swamp in and adjacent to any waters of the state without a permit from the department. The permit application together with a detailed plan and a map showing the exact location of the proposed project, along with 4 copies of the permit application, plan and map, shall be submitted to the town or city clerk, accompanied by a filing fee in the form of a check made out by the applicant to the state of New Hampshire. The permit application fee shall be $100 for minimum impact projects under this chapter. The permit application fee for minor and major shoreline structure projects shall be $100 plus an impact fee, based on the area of dredge, fill, or dock surface area proposed, or a combination. The shoreline structure impact fee shall be $1 per square foot for permanent dock surface area; $.50 per square foot for seasonal dock surface area; and $.10 per square foot for dredge or fill surface area or both. The permit application fees for minor or major projects shall be [$.10] $.06 per square foot of proposed impact for all other projects under this chapter. For projects involving the repair, reconstruction, or reconfiguration of an existing docking structure, the application fee shall be $100. At the time the permit application is submitted to the city or town clerk, the applicant shall provide postal receipts or copies, verifying that abutters, as defined in the rules of the department, and except as further provided in said rules, have been notified by certified mail. The postal receipts or copies shall be retained by the municipality. The town or city clerk shall immediately sign the application and forward by certified mail, the application, plan, map and filing fee to the department. The town or city clerk shall then immediately send a copy of the permit application, plan and map to the local governing body, the municipal planning board, if any, and the municipal conservation commission, if any, and may require an administrative fee not to exceed $10 plus the cost of postage by certified mail. One copy shall remain with the city or town clerk, and shall be made reasonably accessible to the public. The foregoing procedure notwithstanding, applications and fees for projects by agencies of the state may be filed directly with the department, with 4 copies of the application, plan and map filed at the same time with the town or city clerk to be distributed as set forth above.

224:4 New Section; Wetlands Program Annual Report. Amend RSA 482-A by inserting after section 482-A:15 the following new section:

482-A:15-a Wetlands Program Annual Report. The department shall report annually to the wetlands council on the wetlands program. The report shall include, but not be limited to, the status of the wetlands program including program performance, rules, and funding and the status of the Clean Water Act section 404 program in New Hampshire.

224:5 Terrain Alteration; Fee Increase. Amend RSA 485-A:17, II to read as follows:

II. The department shall charge a fee for each review of plans, including project inspections, required under this section. The fee shall be based on the extent of contiguous area to be disturbed. Except for RSA 483-B:9, the fee for plans encompassing an area of at least 100,000 square feet but less than 200,000 square feet shall be [$100] $500. For the purposes of RSA 483-B:9, the fee for plans encompassing an area of at least 50,000 square feet but less than 200,000 square feet shall be [$100] $500. An additional fee of [$100] $200 shall be assessed for each additional area of up to 100,000 square feet to be disturbed. No permit shall be issued by the department until the fee required by this paragraph is paid. All fees required under this paragraph shall be paid when plans are submitted for review and shall be deposited in the treasury as unrestricted funds.

224:6 Positions Established; Civil Engineer V and Civil Engineer IV. There are created within the department of environmental services the classified, full-time positions of civil engineer V, at labor grade 30, and civil engineer IV at labor grade 27 which shall be under the direction of the commissioner under RSA 485-A:30, I-a. The employees in these positions shall be responsible for duties relative to RSA 485-A:17 and for multi-program permitting.

224:7 Appropriation. The sum of $131,000 is hereby appropriated to the department of environmental services for the fiscal year ending June 30, 2004, and the sum of $131,000 is hereby appropriated to the department of environmental services for the fiscal year ending June 30, 2005, for the purposes of funding salary, benefits, current expenses, and equipment for the civil engineer V and civil engineer IV positions established in section 5 of this act. These sums are in addition to any other funds appropriated to the department of environmental services. The governor is authorized to draw a warrant for said sums out of any money in the treasury not otherwise appropriated.

224:8 Effective Date.

I. Section 3 of this act shall take effect July 1, 2006.

II. The remainder of this act shall take effect July 1, 2003.

(Approved: Enacted in accordance with Article 44, Part II, N.H. Constitution, without signature of the Governor, July 1, 2003)

(Effective Date: I. Section 3 shall take effect July 1, 2006

II. Remainder shall take effect July 1, 2003)